Presentasi Ace Sharing Pengalaman 4 in 1
Sharing Pengalaman Proses lelang Civil Works (Pendanaan IDB) Oleh : Suprapto ( PIC Civil Work PMU)
IDB’s Guidelines
Two Guidelines
Process, methods, criteria, steps, review
process by IDB Concepts and approaches in procurement of goods or works are diferent from selection of consultant
Terms & Methods
Good, Work, Service
- Tender, Bidding •
- Selection •
- Request For Expression of Interest (REOI)
- Invitation for Bidding (IFB) Invitation to Prequalitifcation •
- Request for proposal (RFP)
Open competition (post qualitifcation) pre- qualitifcation
Tender or Bidding Document
- Two Envelope •
- One envelope or two-stage bidding*
- ‘substantially’ Responsive (pass) or Not ‘Substantially’ Responsive (fail)
- Technical and Financial •
- Price •
Lowest evaluated responsive bid
Consultant
Short List
Scoring ( Supported by appropriate assessment )
Highest compined score (technical and fnancial)
- No negotiation
- Negotiationrequired
- two-envelope is not acceptable
Untuk menjadi perhatian dalam evaluasi:
-) Evaluasi Penawar Terendah dengan teliti dan cermat
Procurement methods based on type of procurement
Good, Work, Service
ICB *
ICB *
ICB/MC *
ICB/MC * NCB * NCB * Shopping
Shopping Force Account Force Account Direct Contracting
QCBS * QCBS * QBS QBS FBS FBS
LCS * LCS *
CQ CQ SSS SSS
*) yang sering
digunakan
Direct Contracting Consultant (Firm)
**)Metode:
diubah oleh IDB:
ICB/MC
Ke NCB
Procurement System
based on how bids or proposals are submitted
Two-or Three-Envelope One Envelope System Two-stage Bidding
System
Qualifcation,
Technical bid is
Technical and technical &submitted &
fnancial bids are fnancial bids areevaluated,
submitted at once , submitted at oncethereafter revised
and opened but openedtechnical &
simultaneously separatelyfnancial bids are
submitted
IDB uses for Simple contract for
Consultant, and does
Complex contract
not accept 2- or 3-G/W/S (Regardless
for G/W/S
envelope system for of Value)(Regardless of
procurenment of G/W/S
Value)
Civil Works : Menggunakan Satu Sampul
Procurement and Competition based on how qualifcation is evaluated
Pre-qualifcation Post-qualifcation Short-list
For procurement of For procurement og For selection of
goods, works, service Goods, Works, Service Consultant Only pre-qualifed Open bidding, Identify pre-qualifed companies are invited qualifcation is consultans (‘long list’) for bidding evaluated with bid Complex contract Simple contract Long list reduced to 6
(regardless of value) (regardless of value) to 8 frms = ‘short list’
Steps in Procurement of Goods, Works of Service through Open Competition
Prequalifcation n
PQ preparation (≥60-90 days) Bid PQ Submission
PQ Doc Reports (*) 4 NOLs
IDB Nol required ± 3- 5 monts
) HPS tidak
Available Forms & Templates
Note : Tambahan Form/data
Eligibility Criteria
“Legally and fnancially autonomous
Not dependent on the budget of the Benefciary’s Government
Participation is critical to the consulting assignment
Located in the Benefciary’s country Operate under commercial Law Treated on a case- by-case basis
PROCUREMENT
OF WORKSDocuments Comprising a Bid
*) Jaminan Penawaran dan Dukungan Bank diklarifkasi ke Bank Penerbit
Qualifcation – Works
*) yang menandatangani Surat Penawaran harus jelas siapanya : Direktur Utama/Direktur atau yng mewakilinya
Note : Pengalaman:
Qualifcation – Works
Qualifcation-Works
Rejection of Bid
Based on level of responsiveness •
- No bid or proposal shall be rejected at bid opening except for late submission
- Sufficient documentations and justifications should be provided to IDB for review
Factors Afecting Responsiveness
When shall a bid b e rejected? • has a shorter validity period than required
• is not accompanied by a substantially responsive bid
Security • is received after the deadline for submission of bids (will be returned unopened)- ofers a completion date beyond the maximum designated period
- is not substantially responsive to the Bid’s requirements
When will a bid be rejected?
linked to corrupt, fraudulent,
- collusive, coercive or obstructive
contains an adjustable price
- quotation (for fxed price bid)
does not meet minimum acceptable
standards of completeness,
consistency and detail.
Rejection of ALL Bids
No ‘substantially’ responsive bids High and unreasonably priced bids Lack of competitions
Key Success Factors
Reference 2.
1. Guidelines for Procurement of Goods and Works Under Islamic Development Bank Financing, May, 2009
Standard Procurement Document, Prequalifcation Document for Procurement of Works, Islamic Development Bank,
3. May, 2012Standard Procurement Document, Standard Request for Proposals,Selection of Consultants,The Islamic Development
4. Bank 5. Materi Workshop The IDB Procurement Guidelines, Jakarta, 10-11 Septermber 2013Istisna’a Agreement, Project No: IND-140, The Government of The Republic Indonesia and Islamic Development Bank
.