RPP 3pkn 5 english 0

FACULTY OF ENGINEERING
YOGYAKARTA STATE UNIVERSITY
TEACHING-LEARNING PLAN OF COST ESTIMATION
No. RPP/TSP/TSP 231
fifth semester

Subject
Subject code
Study program
Semester
Week
Time Alocation

Revision:
date 15
Page: 1 of 2
00
Pebruari 2009
Payment system for
2x50 mimutes
consultant and supervisor


: Cost Estimation
: TSP 231
: Civil Engineering and Planning Education
: V
: 5
: 2
X 50
menit

STANDARD OF COMPETENCY
Having knowledge about the importance of cost estimation, project resources, related
sides in project, kind of payments for planner , contractor and supervisor, and also
having ability to calculate the global cost and detail cost estimation of a project
BASIC COMPETENCE :
1. Having ability to explain the Payment system for consultant and supervisor
2. Having ability to calculate the payment
INDICATORS OF ACHIEVED COMPETENCE :
1. explain and the payment system for planner and supervisor
2. calculate payment for planner and supervisor

I.

OBJECTIVES
1. Having ability to explain the payment system for consultant and supervisor
2. Having ability to calculate the payment

II.

MATERIALS
1. meaning of relates sides in a project and the item of sides
2. meaning of sequences of a project and the item of sequences

III.

METHOD
1.presentation
2.discussion

Prepared
by: :

Sativa, MT.

Do not copy parts or all of the contens without permission from The
Faculty of Engineering
Yogyakarta State University

Checked by: :
Drs.Agus Santoso,
MPd.

FACULTY OF ENGINEERING
YOGYAKARTA STATE UNIVERSITY
TEACHING-LEARNING PLAN OF COST ESTIMATION
No. RPP/TSP/TSP 231
fifth semester

IV.

Revision:
date 15

Page: 2 of 2
00
Pebruari 2009
Payment system for
2x50 mimutes
consultant and supervisor

STEPS
A.
Opening
1.explaining course objectives
2.aperception, giving oral test
3.motivating
B. Main Activities
1. Explain the importance of cost estimation
2. Explain the project resources
3. Explain the component of project resources
C. Closing
a. Sampling oral and written post test
b. summarizing


V.

LEARNING ANDTEACHING TOOLS
1. white board and boardmarker
2. computer and LCD

VI.
REFERENCES
1. Asiyanto, 2003, Construction Project Cost Management , Pradnya Paramita,
Jakarta
2. Erviato, Wulfram I, 2005, Manajemen Proyek Konstruksi, Andi Offset, Yogyakarta
VII. SCORING
a.
Techniques: written and oral test
b.
Score range: 0-100

Prepared
by: :

Sativa, MT.

Do not copy parts or all of the contens without permission from The
Faculty of Engineering
Yogyakarta State University