ANN based Optimized Battery Energy Storage System Size and Loss Analysis for Distributed Energy Storage Location in PV-Microgrid

  

ANN based Optimized Battery Energy Storage System Size

and Loss Analysis for Distributed Energy Storage Location in PV-Microgrid

  

Thongchart Kerdphol, Ravi N. Tripathi, Tsuyoshi Hanamoto, Khairudin, Yaser Qudaih, Yasunori Mitani

  Department of Electrical and Electronics Engineering, Kyushu Institute of Technology 1-1 Sensui-cho, Tobata-ku, Kitakyushu-shi, Fukuoka, 804-8550, Japan

  

E-mail: n589504k@mail.kyutech.jp

yaser_qudaih@yahoo.com, hanamoto@life.kyutech.ac.jp, mitani@ele.kyutech.ac.jp

  Abstract— This paper proposes a method to determine the optimum Battery Energy Storage System (BESS) size, considering how the location of BESS affects the micro-grid and analysis of power loss for the consideration of different locations of BESS. The possibility of installing an optimum BESS as the distributed BESS at different locations is proposed. Artificial neural network (ANN) was established to evaluate the optimum size of BESS based on frequency and voltage regulation. To investigate and improve system performance, a BESS installation is considered as the distributed BESS at different locations. Then, power compensation to local loads is analyzed to obtain the improvement for entire system performance. Results show that the proposed ANN can achieve the very good performance in predicting the optimum size of BESS compared to the measured targets. In terms of BESS location, the optimum BESS size located at local loads shows better performance than the optimum BESS size located at a main substation.

  Index Terms—ANN, Battery energy storage system, Frequency and voltage control, Micro-grid, Optimization.

  I. I

  NTRODUCTION

  After the great east Japan earthquake and Tsunami in March 2011, the Fukushima Daiichi nuclear station raised the safety concerns which led to the shutdown of all of Japan’s nuclear power plants by May 2012. Since that time, micro/smart grids developed in Japan have been focused on resilience. The concept of micro-grid which consists of a localized grouping of DGs, local loads and energy storage system interconnected by transmission line and communication was introduced [1]. Micro-grids can operate both in grid-connected mode and stand-alone mode. In the grid-connected mode, participants can achieve the economic benefits by participating in the electrical markets. In case of stand-alone mode (i.e., problems in the utility grid), micro- grids are able to maintenance the grid assets without de- electrifying the network downstream which occurred in Canada [2]. Isolated micro-grids can also help electrifying areas which have no grid access. This is an important contribution of micro-grids because the electrification is an essential condition for attaining a sustainable economic development. However, as the output characteristics of DGs in a micro-grid are quite different from the conventional energy sources and the output of DGs cannot predict, a micro-grid should be capable of handling unexpected fluctuation and maintaining system reliability. Thus, storage elements are essential components of a micro-grid so as to maintain stability, to simplify integration of renewable energies and enhance power quality [3].

  Battery Energy Storage System (BESS) can be applied in several features of power system as one key issue for sustainable energy in various nations mostly in Japan, America and Europe. Advantages of BESS include improvement of the system frequency especially when BESS is used for system frequency control. In the circumstance of small disturbance, BESS is discharging when the system frequency is lower than 50 or 60 Hz. On the other hand, BESS is charging when the system frequency is higher than 50 or 60 Hz. In the circumstance of large disturbance, BESS is able to improve the performance of the system frequency control by integrating BESS with under frequency load shedding scheme, or under/over frequency generation trip. With these different utilities, BESS can offer a good solution to power system. It can be summarized that BESS is a quick and flexible component for power system [4, 5].

  The optimal size and location of BESS is an important aspect to maximize the benefits of BESS in the micro-grid. The inappropriate size and location of BESS can cause low or over frequency and voltage to the micro-grid system. It can also cause inefficient system in terms of BESS role for power compensation and increased losses in the system. Hence, it is essential to consider an appropriate size and location of BESS to the micro-grid in order to improve system performance, power quality and reliability [6]. In fact, BESS should be connected at a bus which BESS can provide the best reduction in losses without any violation to the frequency and voltage of the micro-grid. Several optimization techniques for optimum size of BESS are proposed in the literature [7, 8]. However, there is no clearly suggestion for choosing the optimal location of BESS in a micro-grid system [9]. Thus, the main purpose of this paper is to determine the optimal size of BESS and identify where BESS can be located in the micro-grid. Because of non-linear relationship constrains in this proposed method such as frequency and voltage of the microgrid, power capacity of BESS and system power losses, Artificial Neural Network (ANN) seems to be the most suitable for such modeling method. ANN has been proven to be a successful type of Artificial Intelligence (AI) in many applications [12], [13].

  In this paper, the main purpose is to evaluate the optimum BESS size, considering how the location of BESS affects the micro-grid, and identify where BESS can be located in the micro-grid. System losses are investigated and analyzed for different BESS locations in order to study and investigate the effect of BESS locations in terms of reduced loss and localized power compensation in the micro-grid. The location of BESS is changed from a main substation to a local substation/load. Four different cases of BESS locations were considered for improved performance based on power compensation from BESS to localized load with minimized active and reactive power loss. The rest of the paper is organized as follows: Section II presents a brief description of the micro-grid system; Section III illustrates the ANN based BESS size optimization; Section IV analyses the micro-grid performance by changing locations of BESS; Section V displays the simulation results and analysis; Section VI accomplishes the work.

A. Micro-grid Structure

  ), T

  is PV modules number, P

  rate PV

  is the PV array rated power (W), G is the global insolation on the PV array (W/m

  2

  ), G is the standard amount of insolation rating the capacity of PV modules (W/m

  2

  A

  (1) where n

  is the ambient temperature, T

  CO

  is the temperature coefficient of the maximum power of PV, ɳ

  rel

  is the relative efficiency of the PV modules,

  ɳ inv is the efficiency of the inverter.

  PV

  25 1 /

  II. S YSTEM C ONFIGURATION

  BESS

  Figure. 1. The study micro-grid

  The typical micro-grid structure, which considered in this study, is consists of four major power sources; the 1.2 MW mini-hydro generator, 2 MW hydro generator, 3 MW solar photovoltaic sources and BESS as shown in Figure 1. Each DG unit has its own local controller to handle the relevant electrical variables. This system also consists of group of load 1 and 4 are the critical load with peak power of 1.85 MW and 1.9 MW respectively. The load 2, 3 and 5 are the non-critical load with peak power of 1.7 MW, 1.75 MW and

  2.4 MW respectively.

  B. Battery Energy Storage System (BESS)

  Renewable energy sources are depending on weather conditions. Thus, BESS is used to store surplus electrical energy to maintain the system frequency, voltage and supply the power to loads in case of low solar ration or wind speed in a micro-grid. Moreover, BESS can smooth out the fluctuation of wind/solar and enhance the load availability. For future BESS information, along with most BESS models demonstrated in various researches [7-9].

  The structure of BESS consists of power converters, battery cells and control parts which are shown in Figure 2.

  Converter Control System Transformer

  T T G G P n P K K $

  3-phase system Figure. 2. A structure of BESS [7]

  In this study, when the power generated by the micro-grid system is greater than the load demand, the surplus power can be stored in BESS for future uses. On the other hand, when there is any deficiency in the power generation of the micro- grid, the stored power can be used to supply the load. Thus, this will improve the system performance and reliability.

  C. Solar Photovoltaic Generation

  The power output of solar photovoltaic (PV) is uncertain as it is mostly affected by the environmental factors, namely the environmental random changes will inevitably lead to constantly changing of output power of PV [10, 11]. In order to illustrate PV characteristics in operating condition, the influence of solar radiation and atmosphere temperature are designed. The temperature effect is denoted by a temperature coefficient of T

  co

  (1/c°). The efficiency of the inverter is multiplied by the DC output converting DC to AC output as in (1).

PV PV

  A rel inv co PV rate

  ( 1 ) ( 1 )

  III. O PTIMUM SIZE OF BESS BASED ANN

  § ª W W º · 11 21 g

  ª 1 º ¨ ¸ « ( 1 ) ( 1 ) » « »

  ¨ W W ¸ 12 22 Artificial Neural Network (ANN) models are used g 2 « » f

  « » ª º (3) ¨ ¸

  worldwide in various research areas such as engineering,

  « » f Tanh x x ˜

  « » x « » ¨ ¸ v

  « »

  classification and medicine. In the multilayer perceptron

  ¬ ¼ « x » ¨ ¸ x x

  « »

  structure, this structure is established in a layered feed-

  « » ( 1 ) ( 1 ) g i « »

  ¨¨ ¸¸ ¬ ¼ W W 1 j 2 j

  forward network and it consists of an input layer, one or more

  ¬ ¼ © ¹

  hidden layers and output layer. The weight total of the input From (3), it can be simplified as: obtain the output data. The number of hidden layers can be

  T ( 1 )

  (4)

  g f , v f W f , v Tanh

  changed based on the problem data in the training process [12, 13]. In this paper, the multilayer perceptron (MLP)

  The output of the neural network can be expressed as: neural network consists of three-layers of neurons which

  ( 2 )

  demonstrates that only one hidden layer is contained and one (5)

  P f , v f W g f , v BESS Tanh

  type of activation function (i.e. hyperbolic tangent transfer Lastly, the proposed ANN model can be designed as: function) is used in the hidden layer. Based on the measured values of output frequency and voltage in the stand-alone

  T ( 2 ) ( 1 )

  (6)

  P f , v f W f W f , v

  micro-grid, this paper can evaluate the optimal size of BESS BESS Tanh Tanh to supply the micro-grid when the micro-grid is isolated from the utility grid. As a nonlinear modelling method, the MLP Based on Table I, the parameter details for the proposed neural network has nonlinearity quality and it can guarantee ANN are shown and used in the training and the testing the accuracy of fitting. There are two inputs with the one database. output in this study as shown in Figure 3.

  TABLE I. M ULTILAYER PERCEPTRON ANN PARAMETERS Tanh 1 y Parameters ANN

  Goal (MSE) 0.00001 -1 Inputs

  2 Output

  1 W ij W i Hidden layer

  1 i = (1,2); j = (1...n) i = (1…n) H 1 Training data

  90 Testing data

  30 H 2 Hidden layer neurons

  10 Output layer neurons

  1 Transfer function Hyperbolic Tangent H 3 f

  I 1 H 4 ICROGRID NALYSIS FOR

  IFFERENT

  IV. M A D BESS

  O 1 P BESS OCATIONS BASED ON OSSES

  L L

  I v 2 Output layer The case studies are analysed and implemented for four

  Input layer

  cases with different BESS locations to consider how the BESS location affects the micro-grid and evaluate where BESS can be located in the micro-grid based on losses.

  From Figure 4, BESS is located at the main substation/bus

  H n 4 which demonstrates the case 1.

  Hidden layer d d 1 2 3 4 Figure. 3. The ANN model for BESS size estimation Hydro Gen 6/22 kV 3 MVA Loa Loa Load Load 12 4 MVA Photovoltaic system 3 MW

  where f is the frequency of the micro-grid (Hz.) while v is the 2 MW 9 10 11 0.2/22 kV voltage of the micro-grid (pu.). P means the power

  BESS 6 7 8 13 Inverter capacity of BESS (MW). 150/22 kV 30 MVA 4 22 kV

  The activation transfer function is used to convert the 17 16 1 BESS activate level of a neuron to an output value. The output value Utility grid 2 0.4/22 kV 4 MVA Converter of the network is created by transforming a weight total of 2 MVA 5 input based on a transfer function. The hyperbolic tangent 6/22 kV 3 (Tanh) activation transfer function is activated between the Mini Hydro Gen 1.2 MW Load 5 input layer and the output layer as follow:

  x x Figure. 4. The BESS installation at a main substation e e

  (2)

  y f x i Tanh i x x e e For the case 2, BESS is separated into two parts. The first

  The output of the hidden layer can be shown as: another part is located at the main substation (i.e., bus 4) as After the inputs and targets for the training data are shown in Figure 5. initiated, the next process is the separation of the data for 3 MVA 1 2 3 4 BESS Load Load Load Load Photovoltaic system 0.4/22 kV training, validation and test. In this paper, 70 % samples of Converter 3 MVA 4 MVA 3 MW data are used for the training process, 15 % samples of data Hydro Gen 2 MW 6 6/22 kV 7 8 9 10 11 0.2/22 kV 12 13 are used for validation and 15 % for test data. 150/22 kV 30 MVA 4 22 kV Inverter From the training results, the correlation coefficient (R) 17 16 1 BESS for the activation transfer function is almost equal to 1 (i.e., Grid 2 5 0.4/22 kV Converter 0.99992) which means that the target is equal to the output of 6/22 kV 2 MVA the training data (See Figure 8). This reason indicates the Mini Hydro Gen 1.2 MW 3 Load 5 proposed ANN output. Hence, this proposed ANN model is strong correlation between the measured data and the high accuracy.

  Figure. 5. The BESS installations at a main and local substation R=0.99992

  7 In the case 3, BESS is separated into two parts. The first

  part is located at the local substation/load 1 (i.e., bus 8) and

  6

  another part is located at the local substation/load 5 (i.e., bus 5) as depicted in Figure 6. BESS Lo Lo L L Photovoltaic system 0.4/22 kV 3 MVA ad ad 1 2 oad oad 3 4

  5 Converter 3 MW

  4 6/22 kV 3 MVA 4 MVA tput Hydro Gen 11 12 0.2/22 kV u 2 MW 6 150/22 kV 30 MVA 7 8 4 22 kV 9 10 13 Inverter O

  3 Grid 17 16 1

  2 Output (Target) 2 5

  1 2 MVA Sample Data Mini Hydro Gen 0.4/22 kV 6/22 kV 3 2 MVA Converter BESS

  Best Linear Fit 1.2 MW Load 5

  1

  2

  3

  4

  5

  6

  7 Target Figure. 6. The BESS installations at local substations Figure. 8. A regression analysis between the network output and the corresponding target

  Based on the case 4, BESS is separated into two parts. The first part is located at the local substation/load 4 (i.e., bus 11) From the testing results, it is seen that the proposed ANN and another part is located at the local substation/load 5 (i.e., with the hyperbolic tangent function is able to follow the bus 5) as shown in Figure 7. BESS pattern of BESS size based on frequency and voltage control ad ad ad 1 2 3 4 0.4/22 kV 2 MVA Converter of the micro-grid as shown in Figure 9. This figure Lo Load Lo Lo Photovoltaic system 3 MW demonstrates that the proposed ANN with the hyperbolic Hydro Gen 2 MW 6 6/22 kV 3 MVA 7 8 9 10 BESS for the stand-alone micro-grid. The outputs of the 11 12 0.2/22 kV 4 MVA 13 Inverter tangent function can accurately determine the optimal size of 150/22 kV 30 MVA 4 22 kV hyperbolic tangent function are only slightly different from Grid 17 Mini Hydro Gen 0.4/22 kV 1.2 MW 16 1 6/22 kV 3 2 MVA 2 Load 5 5 2 MVA Converter BESS the measured targets (i.e. simulation result). H z. ) 60 55 45 50 equency (

  40 Figure .7. The BESS installations at local substations Fr 35 30 Measured Estimated

  V. S

  IMULATION R ESULTS AND A NALYSIS 1.1 1 2 3 4 5 6 7 This section demonstrates the comparison results of the ) 1 optimal size of BESS based ANN with different case studies pu. 0.9 of locations in the micro-grid. Vol tage ( 0.8 A. Optimal BESS Size based Proposed ANN 0.7 Estimated Measured

  In this paper, two inputs which are frequency and voltage 1 2 3 4 5 6 7 of the micro-grid are fed to the proposed neural network. The Size of BESS (MW)

  Figure. 9. A comparison between measured BESS size and predicted BESS

  output of the proposed ANN can be the predictive result of

  size based on frequency and voltage control of the micro-grid the optimal size of BESS for the stand-alone micro-grid. The mean square error (MSE) on forecasting performance shows the learning and generalization error of the normalized values of BESS size (See Table II). This value showed that the proposed ANN was able to accurately predict the optimum BESS size. MSE equation can be shown as:

  n

  2

  (7)

  MSE T O i i

  ¦

  1

  where T is the target vector, O is the output vector and n is

  i i

  the number of training data or data for each test in the testing data set.

  TABLE II. MSE ERROR FOR BESS SIZE ESTIMATION Performance predictor MSE

  BESS size (P ) 0.0000072 BESS

  Finally, the optimal size of BESS is achieved by the proposed neural network model based on frequency and voltage control of the micro-grid as shown in Table III.

  TABLE III. O PTIMIAL PARAMETERS BASED ON ANN P BESS (MW) f (Hz.) v (pu.)

  3.3520 50.000 0.979

B. Optimal BESS Location Selection

  After the optimal size of BESS is achieved using the propose ANN, the simulation is done for four case scenarios based on BESS locations so as to consider how the BESS location affect the micro-grid and determine where BESS can

  Figure. 11. Frequency deviations for different cases after islanding

  be located. The simulation results are explained in the following: The case 1; BESS with the capacity of 3.3520 MW/6.70 MWh is located at the main substation/bus4. The case 2; BESS is separated into two parts. BESS with the capacity of 1.8520 MW/3.70 MWh is located at the main substation/bus 4 and another BESS with capacity of 1.50 MW/3.00 MWh is located at the local substation/load 1 (i.e, bus 8).

  The case 3; BESS is separated into two parts. BESS with the capacity of 1.8520 MW/3.70 MWh is located at the local substation/load 5 (i.e., bus 5) and another BESS with capacity of 1.50 MW/3.00 MWh is located at the local substation/load 1 (i.e., bus 8).

  The case 4; BESS is separated into two parts. BESS with the capacity of 1.8520 MW/3.70 MWh is located at the local substation/load 4 (i.e., bus 11) and another BESS with capacity of 1.50 MW/3.00 MWh is located at the local substation/load 5 (i.e., bus 5).

  Figure 10 and 11 depict the system frequency and voltage of four scenarios incorporating optimal BESS respectively when the micro-grid is isolated from the utility grid at 10.0s. It is clearly seen that optimal BESS can improve a fast, smooth and secure system frequency and voltage for four case scenarios from the emergency situation to the normal state equilibrium. In case of no BESS, the system frequency and voltage dropped drastically because the

  In terms of power compensation, four cases with different BESS locations are investigated and analyzed. Based on Figure 13 and Table IV, it is obvious that BESS can help all power generations to supply the reactive powers. Moreover, BESS units which are located at the local substation/load (i.e., case 3 and 4) give better performance of power compensation than BESS units are located at the main substation (i.e., case 1 and 2) . However, the BESS location at the case 4 analyzed the best performance for the micro-grid. As the reactive power loss is minimum compared to other cases with battery and without battery. Considering power compensation, the power demand from different generating sources is maximally reduced under the case 4 for the same rating of the system as it also provides the best compensation. Thus, BESS units in the case 4 have been providing the most effective compensation and minimum loss in the comparison of all cases considered for the analysis of the power compensation from BESS in the micro-grid.

  2014 of IEEE PES conf. on Innovative smart grid technologies (ISGT) Europe, pp. 1-6.

  Simard, " Planned islanding as a distribution system operator tool for reliability enhancemt," in Proc. 2007 of 19th international conf. on electricity distribution, pp. 359-366.

  [3] R. L. Vasquez-Arnez, D. S. Ramos, and T. E. Del Carpio-Huayllas, "Microgrid dynamic response during the pre-planned and forced islanding processes involving DFIG and synchronous generators," Int J Electr Power Energy Syst, vol. 62, no.1, pp. 175-182, Mar. 2015. [4] M. Aghamohammadi, and H. Abdolahinia, "A new approach for optimal sizing of battery energy storage system for primary frequency control of islanded microgrid," Int J Electr Power Energy Syst, vol. 54, no.1, pp. 325-333, Jan. 2014. [5] D. Wu, F. Tang, T. Dragicevic, J. Vasquez, and J. Guerrero, "Autonomous active power control for islanded AC microgrid with photovoltaic generation and energy storage system," IEEE Trans.

  Energy Conversion, vol. 29, no. 4, pp. 882-892, Dec. 2014.

  [6] J. Smith, M. Rylander, L. Rogers, and R. Dugan, “Maximizing the benefits and minimizing the impacts of DERs in an integrated grid,"

  IEEE Power&Energy Magazine, vol. 13, no. 2, pp. 20-29, Mar. 2015.

  [7] T. Kerdphol, Y. Qudaih, Y. Mitani, “Battery energy storage system size optimization in microgrid using particle swarm optimization," in Proc.

  [8] K. Rahbar, J. Xu, and R. Zhang, “Real-time energy storage management for renewable integration in microgrid: an off-line optimization approach," IEEE Trans. on Smart Grid, vol. 6, no. 1, pp124–134, Jan. 2015. [9] K.C. Divya and J. Ostergaard, “Battery energy storage technology for power systems an overview," Electrical Power Energy Research, vol.

  No BESS 1 2 3 4 0.2 0.4 0.6 0.8 1 1.2 1.4 Case S yst em lo sses Active power (MW) Reactive power (Mvar)

  79, no. 1, pp. 511–520, Dec. 2008. [10] M. Sitbon, J. Leppaho, T. Suntio, and A. Kuperman, “Dynamic of photovoltaic-generator-interfacing voltage-controlled buck power stage," IEEE Journal of Photovoltaics, vol. 5, no. 2, pp. 633–640, Dec. 2014. [11] M. Alsayed, M. Cacciato, G. Scarcella, and G. Scelba, “Multicriteria optimal sizing of photovoltaic-wind turbine grid connected system,"

  IEEE Trans., Energy Conversion, vol. 28, no. 2, pp. 370–379, Jun.

  2013. [12] W. Jiang, and J. Lu, “Frequency estimation in wind farm integrated systems using artificial neural network," Int J Electr Power Energy

  Syst., vol. 62, no. 1, pp. 72–79, May. 2014.

  [13] G. Li, J. Na, D. Stoten, and X. Ren, “Adaptive neural network feedforward control for dynamically substructured systems," IEEE Trans., Control System Technology, vol. 22, no. 3, pp. 944–954, May.

  2014.

  EFERENCES [1] M. Patterson, N. F. Macia, and A. Kannan, " Hybrid microgrid model based on solar photovoltaic battery fuel cell systems for intermittent load applications," IEEE Trans. Energy Conversion, vol. 1, no. 1, pp. 359-366, Mar. 2015. [2] M. Gauthier, J. Pepin, C. Abbey, M. Plamondon, F. Katiraei and G.

  R

BESS LOCATIONS

  This paper deals with the optimum BESS size and investigation of locations for the micro-grid based on system losses. The proposed ANN with the hyperbolic tangent function has obtained the optimal size of BESS with a high accuracy. This is because the hyperbolic tangent neurons can have outputs over a large region of the input space. It can be concluded that the proposed ANN with the hyperbolic tangent activation function is appropriate for estimating the optimal size of BESS with only a minor change of BESS size compared to the target optimization. In order to improve the system performance by providing local compensation through BESS, four different scenarios of BESS locations are investigated effectively. The results obtained from each case are compared to determine the performance that gives the best effective power compensation for BESS location. Based on the results, the optimum BESS has shown a good performance in load frequency control and can be used for emergency control purposes. In terms of power compensation, the BESS units which are installed at bus 5 and 11 (i.e., case 4) have shown the capability of achieving the best performance based on distributed local compensation through BESS. This is because BESS units are located at local substations/loads which can support the power compensation to loads locally. It can be concluded that the micro-grid considered in this paper illustrating the best effective power compensation response for an optimized size of BESS when BESS is located at a local substation/load.

  0.04

  Figure. 13. A comparison of system losses for different BESS locations TABLE IV. T OTAL SYSTEM LOSSES FOR DIFFERENT CASES BASED ON

  Case Active power (MW) Reactive power (Mvar) No BESS

  0.20

  1.21

  1

  0.18

  0.04

  2

  0.04

  0.16

  3

  0.04

  0.13

  4