PEKERJAAN BETON 5.BQ ANALISA RSUD TUGUREJO

0.6200 oh Pekerja 0.3500 oh Tukang batu 0.0350 oh Kepala tukang 0.0300 oh Mandor 10 03-7395-2008 1 M Pasang nozing tangga 5x20 : 5.000 bh Nozing 5x20 2.600 kg Portland Cemen PC 0.405 kg PC warna 0.011 m3 Pasir pasang 0.088 oh Tukang 0.009 oh Kepala tukang 0.155 oh Pekerja 0.008 oh Mandor 11 03-7395-2008 1 M Pasang keramik border dinidng kmwc 5x30 : 4.000 bh Keramik border 5x30 1.140 kg Portland Cemen PC 0.025 kg PC warna 0.003 m3 Pasir pasang 0.090 oh Tukang 0.009 oh Kepala tukang 0.090 oh Pekerja 0.005 oh Mandor 12 1 M Pasang plint kaca rayband 5 mm L = 10 cm 0.1000 m2 Plint kaca rayband 5 mm L = 10 cm 1.1400 kg Portland Cemen PC 0.090 oh Pekerja 0.090 oh Tukang 0.009 oh Kepala tukang 0.005 oh Mandor 13 03-7395-2008 1 M Pasang kuku macan 2,5x10 : 10.000 bh Kuku macan 2,5x10 0.945 kg Portland Cemen PC 0.147 kg PC warna 0.004 m3 Pasir pasang 0.032 oh Tukang 0.003 oh Kepala tukang 0.056 oh Pekerja 0.003 oh Mandor 14 03-7395-2008 6.57 1 M2 Pasang batu serit mortar 1.1000 m2 Batu serit 11.7500 kg Portland Cemen PC 0.0350 m3 Pasir pasang 0.6200 oh Pekerja 0.3500 oh Tukang batu 0.0350 oh Kepala tukang 0.0300 oh Mandor

E. PEKERJAAN BETON

1 03-7394-2008 6.4 1 M3 Beton lantai kerja mutu fc = 7,4 Mpa K100 slum 3-6 cm wc = 0,87 230.0000 kg Portland Cemen PC 893.0000 kg Pasir beton 1,024.0000 kg Kerikil maksimum 30 mm 200.0000 ltr air 1.2000 oh Pekerja 0.2000 oh Tukang batu 0.0200 oh Kepala tukang 0.0060 oh Mandor 2 03-7394-2008 6.5 1 M3 Beton mutu fc = 9,8 Mpa K175 slum 12±2 cm wc = 0,66 326.0000 kg Portland Cemen PC 760.0000 kg Pasir beton 1,029.0000 kg Kerikil maksimum 30 mm 215.0000 ltr air 1.6500 oh Pekerja 0.2500 oh Tukang batu 0.0250 oh Kepala tukang 0.0800 oh Mandor 3 03-7394-2008 6.7 1 M3 Beton mutu fc = 19,3 Mpa K225 slum 12±2 cm wc = 0,58 371.0000 kg Portland Cemen PC 698.0000 kg Pasir beton 1,047.0000 kg Kerikil maksimum 30 mm 215.0000 ltr air 1.6500 oh Pekerja 0.2500 oh Tukang batu 0.0250 oh Kepala tukang 0.0800 oh Mandor 4 03-7394-2008 6.9 1 M3 Beton mutu fc = 24 Mpa K275 slum 12±2 cm wc = 0,53 406.0000 kg Portland Cemen PC 684.0000 kg Pasir beton 1,026.0000 kg Kerikil maksimum 30 mm 215.0000 ltr air 1.6500 oh Pekerja 0.2500 oh Tukang batu 0.0250 oh Kepala tukang 0.0800 oh Mandor 5 03-7394-2008 6.9 1 M3 Beton mutu fc = 26.4 Mpa K300 slum 12±2 cm wc = 0,52 413.0000 kg Portland Cemen PC 681.0000 kg Pasir beton 1,021.0000 kg Kerikil maksimum 30 mm 215.0000 ltr air 1.6500 oh Pekerja 0.2750 oh Tukang batu 0.0280 oh Kepala tukang 0.0830 oh Mandor 6 03-7394-2008 6.17 10 kg Pembesian dengan besi polos ulir 10.5000 kg Besi polos ulir 0.1500 kg Kawat beton 0.0700 oh Pekerja 0.0700 oh Tukang batu 0.0070 oh Kepala tukang 0.0040 oh Mandor 1 kg Pembesian dengan besi polos ulir 7 03-7394-2008 6.21 1 M2 Memasang Bekisting untuk sloof 0.0450 m3 Kayu kelas III terentang 0.3000 kg Paku biasa 2-5 0.1000 ltr Minyak bekisting 0.5200 oh Pekerja 0.2600 oh Tukang batu 0.0260 oh Kepala tukang 0.0260 oh Mandor 8 03-7394-2008 6.22 1 M2 Memasang Bekisting untuk kolom 0.0400 m3 Kayu kelas III terentang 0.4000 kg Paku biasa 2-5 0.2000 ltr Minyak bekisting 0.0150 m3 Balok kayu kelas II 0.3500 lbr Multiplex 6 mm 2.0000 btg Dolken kayu dia 8-10 cm 4 m 0.6600 oh Pekerja 0.3300 oh Tukang batu 0.0330 oh Kepala tukang 0.0330 oh Mandor 9 03-7394-2008 6.23 1 M2 Memasang Bekisting untuk balok 0.0400 m3 Kayu kelas III terentang 0.4000 kg Paku biasa 2-5 0.2000 ltr Minyak bekisting 0.0180 m3 Balok kayu kelas II 0.3500 lbr Multiplex 6 mm 2.0000 btg Dolken kayu dia 8-10 cm 4 m 0.6600 oh Pekerja 0.3300 oh Tukang batu 0.0330 oh Kepala tukang 0.0330 oh Mandor 10 03-7394-2008 6.24 1 M2 Memasang Bekisting untuk lantai 0.0400 m3 Kayu kelas III terentang 0.4000 kg Paku biasa 2-5 0.2000 ltr Minyak bekisting 0.0150 m3 Balok kayu kelas II 0.3500 lbr Multiplex 6 mm 2.0000 btg Dolken kayu dia 8-10 cm 4 m 0.6600 oh Pekerja 0.3300 oh Tukang batu 0.0330 oh Kepala tukang 0.0330 oh Mandor 11 03-7394-2008 6.26 1 M2 Memasang Bekisting untuk tangga 0.0300 m3 Kayu kelas III terentang 0.4000 kg Paku biasa 2-5 0.1500 ltr Minyak bekisting 0.0150 m3 Balok kayu kelas II 0.3500 lbr Multiplex 6 mm 2.0000 btg Dolken kayu dia 8-10 cm 4 m 0.6600 oh Pekerja 0.3300 oh Tukang batu 0.0330 oh Kepala tukang 0.0330 oh Mandor 12 Dihitung 1 M3 Beton bertulang praktis 15 x 15 : 1.0000 m3 Beton K 225 149.5207 kg Besi 13.3332 m2 Bekisting Jml Total 13 Dihitung 1 M3 Beton bertulang sloof 15 x 20 : 1.0000 m3 Beton K 225 173.2849 kg Besi 13.3320 m2 Bekisting Jml Total 14 Dihitung 1 M3 Beton bertulang sloof 15 x 25 Asrama : 1.0000 m3 Beton K 225 144.9191 kg Besi 13.3335 m2 Bekisting Jml Total 15 Dihitung 1 M3 Beton bertulang sloof 20 x 40 Asrama : 1.0000 m3 Beton K 225 153.8700 kg Besi 10.0000 m2 Bekisting Jml Total 16 Dihitung 1 M3 Beton bertulang sloof 20 x 30 Aula : 1.0000 m3 Beton K 225 197.3039 kg Besi 10.0002 m2 Bekisting Jml Total 17 Dihitung 1 M3 Beton bertulang balok 20 x 40 B1 Aula : 1.0000 m3 Beton K 225 144.1000 kg Besi 12.5000 m2 Bekisting Jml Total 18 Dihitung 1 M3 Beton bertulang balok 20 x 30 B2 Aula : 1.0000 m3 Beton K 225 177.6702 kg Besi 13.3336 m2 Bekisting Jml Total 19 Dihitung 1 M3 Beton bertulang balok 15 x 25 B3 Aula : 1.0000 m3 Beton K 225 187.2023 kg Besi 17.3336 m2 Bekisting Jml Total 20 Dihitung 1 M3 Beton bertulang balok 15 x 20 B4 Aula : 1.0000 m3 Beton K 225 219.5311 kg Besi 18.3332 m2 Bekisting Jml Total 21 Dihitung 1 M3 Beton bertulang balok 30 x 70 B1 Asrama : 1.0000 m3 Beton K 225 153.5364 kg Besi 5.2382 m2 Bekisting Jml Total 21 Dihitung 1 M3 Beton bertulang balok 25 x 50 B2 Asrama : 1.0000 m3 Beton K 225 198.1280 kg Besi 10.0000 m2 Bekisting Jml Total 22 Dihitung 1 M3 Beton bertulang balok 20 x 30 B3 Asrama : 1.0000 m3 Beton K 225 184.0703 kg Besi 13.3336 m2 Bekisting Jml Total 23 Dihitung 1 M3 Beton bertulang balok 15 x 25 B3 Asrama : 1.0000 m3 Beton K 225 153.3032 kg Besi 17.3336 m2 Bekisting Jml Total 24 Dihitung 1 M3 Beton bertulang balok 15 x 25 B4 Asrama : 1.0000 m3 Beton K 225 156.4393 kg Besi 17.3336 m2 Bekisting Jml Total 25 Dihitung 1 M3 Beton bertulang plat konsol penyangga talang t = 15 cm : 1.0000 m3 Beton K 225 21.068 kg Besi 6.667 m2 Bekisting Jml Total 26 Dihitung 1 M3 Beton bertulang ring balok 15 x 25 RB1 Asrama Aula : 1.0000 m3 Beton K 225 144.9191 kg Besi 13.3335 m2 Bekisting Jml Total 27 Dihitung 1 M3 Beton bertulang ring balok 15 x 20 RB 2 Asrma : 1.0000 m3 Beton K 225 173.2849 kg Besi 13.3332 m2 Bekisting Jml Total 28 Dihitung 1 M3 Beton bertulang ring balok 15 x 25 RB3 Aula : 1.0000 m3 Beton K 225 144.9191 kg Besi 13.3335 m2 Bekisting Jml Total 29 Dihitung 1 M3 Beton bertulang kolom 30 x 50 K1 Asrama : 1.0000 m3 Beton K 225 149.3515 kg Besi 10.6672 m2 Bekisting Jml Total 30 Dihitung 1 M3 Beton bertulang kolom 30 x 30 K2 Asrama : 1.0000 m3 Beton K 225 106.9012 kg Besi 13.3332 m2 Bekisting Jml Total 31 Dihitung 1 M3 Beton bertulang kolom 20 x 20 Asrama Aula : 1.0000 m3 Beton K 225 135.8600 kg Besi 20.0000 m2 Bekisting Jml Total 32 Dihitung 1 M3 Beton bertulang kolom atas talang 15 x 30 Asrama : 1.0000 m3 Beton K 225 126.0032 kg Besi 19.9998 m2 Bekisting Jml Total 33 Dihitung 1 M3 Beton bertulang kolom 15 x 50 Asrama : 1.0000 m3 Beton K 225 79.2687 kg Besi 17.3329 m2 Bekisting Jml Total 33 Dihitung 1 M3 Beton bertulang kolom 30 x 70 K1 Aula : 1.0000 m3 Beton K 225 169.9082 kg Besi 9.5240 m2 Bekisting Jml Total 34 Dihitung 1 M3 Beton bertulang kolom 30 x 30 K2 Aula : 1.0000 m3 Beton K 225 157.8651 kg Besi 13.3332 m2 Bekisting Jml Total 35 Dihitung 1 M3 Beton bertulang balok tangga 15 x 25 Asrama : 1.0000 m3 Beton K 225 192.2264 kg Besi 17.3336 m2 Bekisting Jml Total 36 Dihitung 1 M3 Beton bertulang kolom 15 x 20 Pos jaga : 1.0000 m3 Beton K 225 169.3550 kg Besi 23.3331 m2 Bekisting Jml Total 37 Dihitung 1 M3 Beton bertulang kuda-kuda 15 x 25 B3 Mushola : 1.0000 m3 Beton K 225 187.2023 kg Besi 17.3336 m2 Bekisting Jml Total 38 Dihitung 1 M3 Beton bertulang kolom 30 x 30 Doorlupe : 1.0000 m3 Beton K 225 70.8615 kg Besi 13.3332 m2 Bekisting Jml Total 39 Dihitung 1 M3 Beton bertulang pedestal 30x40 Aula : 1.0000 m3 Beton K 225 52.4896 kg Besi 5.8331 m2 Bekisting Jml Total 40 Dihitung 1 M3 Beton bertulang pedestal 25x30 Asrama : 1.0000 m3 Beton K 225 76.1248 kg Besi 7.3332 m2 Bekisting Jml Total 41 Dihitung 1 Bh Pondasi foot plat 175x175 F1 Asrama : 4.5938 m3 Galian tanah 1.8375 m3 Urugan kembali 0.3063 m3 Urugan pasir 0.1531 m3 Beton K 100 0.7656 m3 Beton K 225 81.7020 kg Besi 1.4000 m2 Bekisting Jml Total 42 Dihitung 1 Bh Pondasi foot plat 100x100 F2 Asrama : 1.0000 m3 Galian tanah 0.4000 m3 Urugan kembali 0.1000 m3 Urugan pasir 0.0500 m3 Beton K 100 0.2500 m3 Beton K 225 32.7972 kg Besi 0.8000 m2 Bekisting Jml Total 43 Dihitung 1 Bh Pondasi foot plat 80x80 F2 Asrama : 0.6400 m3 Galian tanah 0.2560 m3 Urugan kembali 0.0640 m3 Urugan pasir 0.0320 m3 Beton K 100 0.1600 m3 Beton K 225 21.5100 kg Besi 0.6400 m2 Bekisting Jml Total 44 Dihitung 1 Bh Pondasi foot plat 120x120 F1 Aula : 1.5840 m3 Galian tanah 0.6336 m3 Urugan kembali 0.0720 m3 Urugan pasir 0.0720 m3 Beton K 100 0.3600 m3 Beton K 225 50.2048 kg Besi 0.9600 m2 Bekisting Jml Total 45 Dihitung 1 Bh Pondasi foot plat tangga 60x150 F3 Asrama : 0.9750 m3 Galian tanah 0.3900 m3 Urugan kembali 0.0488 m3 Urugan pasir 0.0488 m3 Beton K 100 0.2438 m3 Beton K 225 26.1280 kg Besi 0.8600 m2 Bekisting Jml Total 46 Dihitung 1 M3 Beton bertulang plat T = 10 cm 1.0000 m3 Beton K 225 62.000 kg Besi 10.000 m2 Bekisting Jml Total 47 Dihitung 1 M3 Beton bertulang plat lantai T = 12 cm 1.0000 m3 Beton K 225 92.996 kg Besi 8.333 m2 Bekisting Jml Total 48 Dihitung 1 M3 Beton bertulang plat tangga T = 12 cm 1.000 m3 Beton K 225 189.137 kg Besi 8.333 m2 Bekisting Jml Total 49 Dihitung 1 M3 Beton bertulang plat T = 8 cm 1.0000 m3 Beton K 225 49.1250 kg Besi 12.500 m2 Bekisting Jml Total 50 Dihitung 1 M3 Beton bertulang plat T = 6 cm 1.0000 m3 Beton K 225 65.2380 kg Besi 16.667 m2 Bekisting Jml Total 51 Dihitung 1 Bh Beton bertulang poor mini pail 60x120 t= 40 cm Aula 0.288 m3 Beton K 300 48.980 kg Besi 1.440 m2 Bekisting Jml Total F. PEKERJAAN KAYU ATAP 1 03-3434-2008 6.15 1 M3 Memasang konstruksi gording kayu kelas II 1.1000 m3 Kayu kruing balok 15.0000 kg Besi strip 3.0000 kg Paku biasa 2-5 2.4000 oh Pekerja 7.2000 oh Tukang kayu 0.7200 oh Kepala tukang 0.1200 oh Mandor 2 03-3434-2008 6,15a 1 M3 Memasang konstruksi nok jurai kayu kelas II 1.1000 m3 Kayu kruing balok 15.0000 kg Besi strip 3.0000 kg Paku biasa 2-5 2.4000 oh Pekerja 7.2000 oh Tukang kayu 0.7200 oh Kepala tukang 0.1200 oh Mandor 3 03-3434-2008 6.16 1 M2 Memasang rangka atap genteng glazur, kayu kelas II 0.0140 m3 Kayu kelas II kruing 5x7 cm 0.0080 m3 Reng bengkirai 3x5 cm 0.2500 kg Paku biasa 2-5 0.1000 oh Pekerja 0.1000 oh Tukang kayu 0.0100 oh Kepala tukang 0.0050 oh Mandor 4 03-3434-2008 6.22 1 M Memasang listplank Uk 3x30 cm kayu kelas II 0.0110 m3 Kayu kelas II bengkirai papan 0.0500 kg Paku biasa 2-5 0.1000 oh Pekerja 0.2000 oh Tukang kayu 0.0200 oh Kepala tukang 0.0050 oh Mandor 5 3434-2008 1 M Memasang reiter kayu kruing 2x20 cm 0.004 m3 Kayu kruing 0.040 kg Paku biasa 2-5 0.175 oh Pekerja 0.175 oh Tukang kayu 0.010 oh Kepala tukang 0.004 oh Mandor

G. PEKERJAAN PENUTUP ATAP