PEK. BETON BERTULANG : PEKERJAAN PASANGAN : - PEK.KUSEN,PINTU JENDELA+PLAFOND : - PEKERJAAN INSTALASI LISTRIK AIR : -

HARGA SATUAN JUMLAH Rp. Rp. 2 PEKERJAAN LANTAI 2

I. PEK. BETON BERTULANG :

1 XIX. 171 22.62 m 3 4,331,560.21 97,979,891.88 2 XIX. 182 6.62 m 3 5,721,551.84 37,876,673.20 3 XIX. 180 0.53 m 3 5,454,928.44 2,891,112.07 4 XIX. 169 1.18 m 3 4,585,423.22 5,410,799.40 5 XIX. 169 0.71 m 3 4,585,423.22 3,255,650.49 6 XIX. 172 1.20 m 3 3,728,192.91 4,473,831.49 7 XIX. 172 0.14 m 3 3,728,192.91 521,947.01 8 XIX. 176 12.80 m 3 4,642,826.08 59,428,173.88 9 XIX. 176 2.43 m 3 4,393,766.31 10,676,852.13 10 XIX. 167 1.46 m 3 3,907,079.01 5,704,335.35 11 XIX. 178 5.04 m 3 5,582,446.25 28,135,529.12 - 256,354,796.03

II. PEKERJAAN PASANGAN : -

1 VIII. 005 415.47 m 2 94,247.76 39,157,116.57 2 X. 006 770.54 m 2 38,585.52 29,731,688.28 3 X. 017 60.40 m 2 58,869.15 3,555,696.95 4 XI. 012 191.29 m 2 108,780.76 20,808,671.31 5 XI. 012 28.69 m 2 108,780.76 3,120,919.96 6 XI. 017 4.65 m 2 107,141.88 498,209.75 7 XI. 018 5.85 m 2 83,613.26 489,137.58 8 XI. 018 1.40 m 2 83,613.26 117,058.57 9 XVII. 001 3.00 bh 2,203,175.75 6,609,527.25 10 XVII. 002 1.00 bh 560,225.08 560,225.08 11 XVII. 006 1.00 bh 1,581,398.86 1,581,398.86 12 XVII. 007 2.00 bh 507,752.89 1,015,505.78 13 - 4.00 bh 100,000.00 400,000.00 - 107,645,155.93 III. PEK.KUSEN,PINTU JENDELA+PLAFOND : - 1 - 3.00 Unit 2,783,966.29 8,351,898.88 2 - 1.00 Unit 4,298,332.59 4,298,332.59 3 - 4.00 Unit 609,880.54 2,439,522.14 4 - 18.00 Unit 1,773,657.21 31,925,829.76 5 - 12.00 Unit 957,710.21 11,492,522.57 6 XII. 027 5.85 m 2 87,974.84 514,652.83 7 - 191.29 m 2 121,488.28 23,239,493.73 8 - 186.95 m 1 27,000.00 5,047,650.00 - 87,309,902.51

IV. PEKERJAAN INSTALASI LISTRIK AIR : -

1 XXVII. 004 25.00 ttk 348,459.72 8,711,493.06 2 XXVII. 003 13.00 ttk 282,594.91 3,673,733.83 3 XXVII. 004 7.00 ttk 348,459.72 2,439,218.06 4 - 20.00 bh 100,000.00 2,000,000.00 5 - 11.00 bh 200,000.00 2,200,000.00 6 - 4.00 bh 100,000.00 400,000.00 7 - XVII. 016 6.00 m 1 17,691.10 106,146.62 XVII. 017 10.00 m 1 22,172.08 221,720.84 XVII. 015 15.00 m 1 15,201.67 228,025.04 8 - XVII. 021 13.00 m 1 77,152.24 1,002,979.10 XVII. 020 45.50 m 1 44,608.61 2,029,691.62 9 XVII. 023 6.00 bh 48,652.95 291,917.68 10 XVII. 025 4.00 bh 37,922.95 151,691.81 - 23,456,617.66

V. PEKERJAAN ATAP -