Assessment, Sanction and Completion of restoration works
CHAPTER- 7: RESTORATION OF ESSENTIAL PUBLIC INFRASTRUCTURE
48 | Page PERFORMANCE AUDIT OF
Natural Disaster in Uttarakhand, June 2013 Response, Relief Restoration of the Damaged Infrastructure of Immediate Nature
During joint physical veriication of 36 villages, it was observed that electricity had not been restored in two villages six per cent New Sobla Khet, Pithoragarh as of January 2015.
Electricity was restored in 14 39 per cent villages with a delay ranging between 15 days to seven months.
ii In the absence of any SOPs or plans prepared by the Department for restoring water supply
in the disaster affected areas, audit could not ascertain how water supply was proposed to be restored. Audit scrutiny showed that no contingency plan was in place at the time of
the disaster and the water supply in the affected areas had been restored on ad-hoc basis. Proposals for restoration of damaged 651 damaged water supply schemes had been submitted
July-September 2013 by the executing agencies to the respective DDMAs. However, funds for restoration of only 393 schemes 60 per cent had been provided by the DDMAs as of
February 2015. Out of 393 water schemes sanctioned, 40 works 10 per cent had been completed within the prescribed time frame of 60 days at a total expenditure of ` 65.74 lakh.
194 works 49 per cent were completed within six months after incurring an expenditure of ` 4.96 crore and remaining 154 works 39 per cent were completed beyond six months’
period at an expenditure of ` 4.49 crore. Five works one per cent were still under progress February 2015. Failure to complete these essential works relects poorly on the DDMAs and
the executing agency.
Joint physical veriication showed that essential services, such as drinking water supply were not restored in two villages New Sobla, Pithoragarh and Phalati, Rudraprayag as on January
2015.
iii The Public Works Department a key line department is responsible for the construction
maintenance of the road network in the State. It comprises National Highways, State Highways, major District roads, other District roads, Village roads and Border tracks. Audit
scrutiny showed that the line department had neither prepared SOPs nor had any contingency plan in place to counter the situation that arose in the period of 15-17 June 2013. Out of
733 works amounting to ` 64.94 crore sanctioned in the ive test-checked districts, 705 works were completed February 2015 after incurring an expenditure of ` 46.38 crore and
remaining 28 works were in progress.