Institutional Repository | Satya Wacana Christian University: Manajemen Proyek Sistem Integrasi Data Sensus Pajak dengan Perizinan: studi kasus DPPKAD Kota Salatiga dengan BPPT dan PM
Manajemen Proyek
Sistem Integrasi Data Sensus Pajak dengan Perizinan
(Studi Kasus : DPPKAD Kota Salatiga dengan BPPT dan PM)
Fakultas Teknologi Informasi
Universitas Kristen Satya Wacana
Jl. Diponegoro no. 52-60, Salatiga 50711, Indonesia
Email : 1)[email protected],edu, 2)[email protected],
3)
[email protected]
Abstract
Today, information technology is needed by many companies and establishing government institutions in supporting
performance improvement . Companies and government agencies need to develop and make the software so that
operations can be done more effectively and efficiently . DPPKAD as government agencies , requires an application
to manage the tax census data ( DPPKAD ) that can be integrated with permissions ( BPPT and PM ) . The purpose
of the study is to conduct project management system the tax census data integration with permissions so that the
project can be in accordance with the scope , cost , resources and time specified as well as testing the feasibility of
using the system cost and benefit analisys . Construction method using inclusive design project . This study resulted
in the tax census data integration system with permissions include system design , database design , network design
, budget , and scheduling projects using a Gantt Chart . Testing the feasibility of using a cost and benefit analysis
that generates payback period = 11 856 a month , ROI = 66.78 % , NPV = Rp . 15 840 . 347 , 4 , and IRR = 19 % .
It can be concluded that project management can overcome the problem of inaccurate budget and turnaround time
as well as to prove that the design of the tax system of census integration with licensing worthy to be accepted
Keyword : integration, cost and benefit analisys, inclusive design, Gant Chart, payback period, ROI, NPV, IRR.
1) Mahasiswa Fakultas Teknologi Informasi Jurusan Sistem Informasi, Universitas Kristen Satya Wacana
2) Staff Pengajar Fakultas Teknologi Informasi, Universitas Kristen Satya Wacana
3) Staff Pengajar Fakultas Teknologi Informasi, Universitas Kristen Satya Wacana
1
Manajemen Proyek
Sistem Integrasi Data Sensus Pajak dengan Perizinan
(Studi Kasus : DPPKAD Kota Salatiga dengan BPPT dan PM)
Fakultas Teknologi Informasi
Universitas Kristen Satya Wacana
Jl. Diponegoro no. 52-60, Salatiga 50711, Indonesia
Email : 1)[email protected],edu, 2)[email protected],
3)
[email protected]
Abstract
Sekarang ini, teknologi informasi sangat dibutuhkan oleh banyak perusahaan dan lembaga pemeritahan dalam
mendukung peningkatan kinerja. Perusahaan dan lembaga pemerintah perlu mengembangkan dan membuat
perangkat lunak agar kegiatan operasional dapat dilakukan dengan lebih efektif dan efisien. DPPKAD sebagai
lembaga pemerintahan, membutuhkan suatu aplikasi untuk mengelola data sensus pajak (DPPKAD) yang dapat
terintegrasi dengan perizinan (BPPT dan PM). Tujuan penelitian adalah melakukan manajemen proyek sistem
integrasi data sensus pajak dengan perizinan sehingga proyek dapat sesuai dengan scope, biaya, sumber daya dan
waktu yang telah ditentukan serta pengujian kelayakan sistem menggunakan cost and benefit analisys. Metode
pembangunan proyek menggunakan metode inclusive design. Penelitian ini menghasilkan perencanaan sistem
integrasi data sensus pajak dengan perizinan meliputi desain sistem, desain database, desain jaringan, anggaran
biaya, dan penjadwalan proyek menggunakan Gantt Chart. Pengujian kelayakan menggunakan analisa cost and
benefit yang menghasilkan payback period = 7,462 bulan, ROI = 40,74 %, NPV= Rp. 61.177.283,5, dan IRR=
26%. Sehingga dapat disimpulkan bahwa manajemen proyek dapat mengatasi masalah kurang tepatnya anggaran
biaya dan waktu penyelesaian proyek serta membuktikan bahwa rancangan sistem integrasi data sensus pajak
dengan perizinan layak untuk diterima.
Kata kunci: integrasi, cost and benefit analisys, inclusive design, Gant Chart, payback period, ROI, NPV, IRR.
1) Mahasiswa Fakultas Teknologi Informasi Jurusan Sistem Informasi, Universitas Kristen Satya Wacana
2) Staff Pengajar Fakultas Teknologi Informasi, Universitas Kristen Satya Wacana
3) Staff Pengajar Fakultas Teknologi Informasi, Universitas Kristen Satya Wacana
2
Sistem Integrasi Data Sensus Pajak dengan Perizinan
(Studi Kasus : DPPKAD Kota Salatiga dengan BPPT dan PM)
Fakultas Teknologi Informasi
Universitas Kristen Satya Wacana
Jl. Diponegoro no. 52-60, Salatiga 50711, Indonesia
Email : 1)[email protected],edu, 2)[email protected],
3)
[email protected]
Abstract
Today, information technology is needed by many companies and establishing government institutions in supporting
performance improvement . Companies and government agencies need to develop and make the software so that
operations can be done more effectively and efficiently . DPPKAD as government agencies , requires an application
to manage the tax census data ( DPPKAD ) that can be integrated with permissions ( BPPT and PM ) . The purpose
of the study is to conduct project management system the tax census data integration with permissions so that the
project can be in accordance with the scope , cost , resources and time specified as well as testing the feasibility of
using the system cost and benefit analisys . Construction method using inclusive design project . This study resulted
in the tax census data integration system with permissions include system design , database design , network design
, budget , and scheduling projects using a Gantt Chart . Testing the feasibility of using a cost and benefit analysis
that generates payback period = 11 856 a month , ROI = 66.78 % , NPV = Rp . 15 840 . 347 , 4 , and IRR = 19 % .
It can be concluded that project management can overcome the problem of inaccurate budget and turnaround time
as well as to prove that the design of the tax system of census integration with licensing worthy to be accepted
Keyword : integration, cost and benefit analisys, inclusive design, Gant Chart, payback period, ROI, NPV, IRR.
1) Mahasiswa Fakultas Teknologi Informasi Jurusan Sistem Informasi, Universitas Kristen Satya Wacana
2) Staff Pengajar Fakultas Teknologi Informasi, Universitas Kristen Satya Wacana
3) Staff Pengajar Fakultas Teknologi Informasi, Universitas Kristen Satya Wacana
1
Manajemen Proyek
Sistem Integrasi Data Sensus Pajak dengan Perizinan
(Studi Kasus : DPPKAD Kota Salatiga dengan BPPT dan PM)
Fakultas Teknologi Informasi
Universitas Kristen Satya Wacana
Jl. Diponegoro no. 52-60, Salatiga 50711, Indonesia
Email : 1)[email protected],edu, 2)[email protected],
3)
[email protected]
Abstract
Sekarang ini, teknologi informasi sangat dibutuhkan oleh banyak perusahaan dan lembaga pemeritahan dalam
mendukung peningkatan kinerja. Perusahaan dan lembaga pemerintah perlu mengembangkan dan membuat
perangkat lunak agar kegiatan operasional dapat dilakukan dengan lebih efektif dan efisien. DPPKAD sebagai
lembaga pemerintahan, membutuhkan suatu aplikasi untuk mengelola data sensus pajak (DPPKAD) yang dapat
terintegrasi dengan perizinan (BPPT dan PM). Tujuan penelitian adalah melakukan manajemen proyek sistem
integrasi data sensus pajak dengan perizinan sehingga proyek dapat sesuai dengan scope, biaya, sumber daya dan
waktu yang telah ditentukan serta pengujian kelayakan sistem menggunakan cost and benefit analisys. Metode
pembangunan proyek menggunakan metode inclusive design. Penelitian ini menghasilkan perencanaan sistem
integrasi data sensus pajak dengan perizinan meliputi desain sistem, desain database, desain jaringan, anggaran
biaya, dan penjadwalan proyek menggunakan Gantt Chart. Pengujian kelayakan menggunakan analisa cost and
benefit yang menghasilkan payback period = 7,462 bulan, ROI = 40,74 %, NPV= Rp. 61.177.283,5, dan IRR=
26%. Sehingga dapat disimpulkan bahwa manajemen proyek dapat mengatasi masalah kurang tepatnya anggaran
biaya dan waktu penyelesaian proyek serta membuktikan bahwa rancangan sistem integrasi data sensus pajak
dengan perizinan layak untuk diterima.
Kata kunci: integrasi, cost and benefit analisys, inclusive design, Gant Chart, payback period, ROI, NPV, IRR.
1) Mahasiswa Fakultas Teknologi Informasi Jurusan Sistem Informasi, Universitas Kristen Satya Wacana
2) Staff Pengajar Fakultas Teknologi Informasi, Universitas Kristen Satya Wacana
3) Staff Pengajar Fakultas Teknologi Informasi, Universitas Kristen Satya Wacana
2