Jurnal Teknik Industri, Vol. 11, No. 1, Juni 2009, pp. 33-42
ISSN 1411-2485

MULTI OBJECTIVE MODEL FOR BALANCING U-TYPE
ASSEMBLY LINE WITH PERMANENT AND TEMPORARY
WORKERS
Gede Agus Widyadana
Department of Industrial and System Engineering, Chung Yuan Christian University
Chung Li 320, Taiwan
Faculty of Industrial Technology, Department of Industrial Engineering, Petra Christian University
Jl. Siwalankerto 121-131 Surabaya 60236, Indonesia
Email: gede@petra.ac.id

ABSTRACT
Assembly line balancing is one of the most important management decisions for reducing production
costs. So far, many researches have been done in this area. In this research, we expand the U-type linebalancing using goal programming for multi objective model with two goals, i.e., minimized the number of
temporary workers and number of cycle time in each station. Additionally, an example to illustrate the model,
as well as some analyses is presented. Different amount of time for temporary worker to accomplish their
tasks were generated. For some cases, the U-type assembly line is more efficient than the straight one.
However, the goal 1 and goal 2 are conflicted
Keywords: line balancing, U-type line, permanent and temporary workers, goal programming


1. INTRODUCTION
As a medium term decision, line balancing is applied when management want to have an
efficient production line. An assembly line consists of some workstations. Every workstation does
some consecutive tasks in a determined cycle time and process flow restrictions. The cycle time is
determined by customers, so it can vary among different production planning periods. When the
cycle time is changed, the number of workstations may change either. These changes force the
management to hire temporary workers to fulfill the demand, especially in a peak demand period.
Usually, temporary workers are less skillful so as need longer processing time compared to
permanent workers. Thus a good line balancing model of temporary and permanent workers plays
an important role to get a more efficient production line.
The U-line is a production line with U-shape layout. One uniqueness of U-line balancing
problem is that one workstation can do task which is not in sequence. In reality, U-shapes type has
been utilized in many production lines. Many researches in the U-type line balancing problem
have been developed continuously in recent years. Miltenburg (1998) developed dynamic
programming model to solve U-line balancing problem. In his problem, more than one U-line
assembly lines in one production line are considered. He found an optimal solution when
individual U-lines do not have more than 22 tasks and do not have wide, sparse precedence
graphs. A heuristic method to solve U-shape line balancing problem was developed by Nakade
and Ohno (1999). They assumed workers have to be allocated to machines so that the walking

routes of workers are not crossed. In their model, waiting times and walking times between
machines are considered and assumed deterministic. Kara et al. (2007) studied the mixed model
U-lines utilized in just-in-time (JIT). Mixed-model production is a production environment where

33

Gede A. W. / Multi Objective Model for Balancing U-Type / JTI, Vol. 11, No. 1, Juni 2009, pp. 33-42

more than one product with similar production characteristic is produced on the same line. They
solved the problem using simulated annealing method. Nakade and Nishiwaki (2008) developed
an algorithm to solve U-shaped production line problem with different workers skill. They
assumed processing, operation and walking times are deterministic and different among workers.
Learning effect in simple assembly line balancing problem and U-type line balancing problem was
studied by Toksari et al. (2008). They found that more computational effort is needed to solve line
balancing with learning effect than without learning effect problem.
Some researchers have focused on developing model for multi objective U-line assembling
problem. Baykasoglu (2005) proposed multi objective U-line model by integrating COMSOAL
method, task assignment heuristic and simulated algorithm to solve simple line and U-type
assembly line balancing problem. He developed an algorithm to find optimal solutions in a short
computational time. A goal programming model for simple U-line balancing problem was

developed by Gokcen and Akpag (2006). They concluded that goal programming approach is a
realistic and natural approach for solving U-line balancing problem. Their model increased
flexibility to decision maker in evaluating different alternatives. Kara et al. (2009) developed
models for balancing straight and U-shaped assembly lines with fuzzy goals. Ozcan and Toklu
(2009) developed a mathematical model, a pre-emptive goal programming model for precise goals
and a fuzzy goal programming model. They applied their model for solving two-sided assembly
line balancing.
Corominas et al. (2008) presented method of rebalancing line at a motorcycle company. The
company had to hire temporary workers due to customer demand and they wanted to minimize
number of temporary worker that will be hired. They developed a mixed integer programming
model and solved it using ILOG CPLEX. In addition to minimization temporary workers, there
are also many goals should be considered such as minimizing quality deviation because of the skill
of temporary workers. So, it is reasonable in some situation to consider some goals instead of one
optimizing goal. However computation time of mixed integer programming method sometime is
not reasonable, so heuristic method is preferred. The comparison of performance and computation
time of mixed integer programming and heuristic method for scheduling problem was compared
by Widyadana (2001). Many researchers have developed heuristic methods to solve assembly line
balancing problems. Some of them are Agrawal (1985), Shin and Min (1991) and Erel et al.
(2005).
The literature search above shows there are no researchers developed a U-line balancing

model considering multi objectives and temporary workers. In this study, goal programming
models for U-line and straight line balancing problem with permanent and temporary workers are
developed. The first goal is minimizing deviation of workers before and after temporary workers is
added. The second goal is minimizing quality deviation. Quality deviation can occur if skill of
temporary workers is not similar than permanent workers. As the skill of permanent workers is
better than the skill of the temporary workers, the permanent workers can be assigned to more
tasks than the temporary workers. The third goals is minimizing the deviation of the workstation
cycle time which is determined by customer demand. When goal programming model has been
developed then the model will be solved using LINGO mathematical programming language.
The organization of this paper is as follows. In the first section, background of the study and
some literatures review are presented. The developing goal programming model for U-line and
straight line balancing are explained briefly in Section 2. Some illustrative examples will be shown
to illustrate how the model works and the trade offs among the goals in Section 3 and in the last
section, some conclusions and future researches recommendation are derived.

34

Gede A. W. / Multi Objective Model for Balancing U-Type / JTI, Vol. 11, No. 1, Juni 2009, pp. 33-42

2. GOAL PROGRAMMING MODELING

Line balancing problem is a problem of assigning number of tasks to some workstations such
that the total task time does not bigger than the predetermined cycle time, and the precedence
relations are satisfied. U-line balancing problem has different characteristic than straight line one.
In U-line balancing problems, forward and backward task assignment must be allowed and the
first and last task can be assigned in the same workstation.
Urban (1998) carried out the forward and backward assignment by introducing a “phantom”
network and add this network to the original network. The example of precedence network with
phantom network that was introduced by Urban (1998) is shown in Figure 1. The task assignment
to workstation can be made forward through original network or backward through phantom
network or simultaneously in both directions.
2

6

8

2

10


3
11

5

8

10

3

1
4

6

7

9


11

1
4

7

9

5

Figure 1. Precedence diagram with phantom network (Urban, 1998)
The assumptions:
1. Permanent and temporary workers tasks times are known and constant.
2. Operators walking times are ignored.
3. The line work continuously and there is no buffer between workstation.
4. Precedence relations between the tasks are known.
5. There is no extra cost for permanent workers.
The notations used in this paper are as follows:
i

index of tasks
j
index of stations
N
total number of tasks
Kmax maximum number of workstation
C
cycle time
P
subset of all precedence tasks in original and phantom diagram
PW number of permanent workers
MP number of tasks allows to be assigned to workstation with a permanent worker
MT number of tasks allows to be assigned to workstation with a temporary worker
TPi task time for permanent workers to process task i
TTi task time for temporary workers to process task i
CBT temporary workers cost per worker per day
CAP- cost of more task for permanent workers in each work station per task per day

35


Gede A. W. / Multi Objective Model for Balancing U-Type / JTI, Vol. 11, No. 1, Juni 2009, pp. 33-42

CAP+
CATCAT+
CCP+
CCPCCT+
CCT-

cost of less task for permanent workers in each work station per task per day
cost of more task for temporary workers in each work station per task per day
cost of less task for temporary workers in each work station per task per day
cost of over cycle time in each work station per minute for permanent workers
cost of under cycle time in each work station per minute for permanent workers
cost of over cycle time in each work station per minute for temporary workers
cost of under cycle time in each work station per minute for temporary workers

Decision variables:
Vij
1, if task i in phantom precedence diagram with a permanent worker is assigned
workstation j; 0, otherwise, i = 1,..,N, j = 1,…,Kmax

Xij
1, if task i in original precedence diagram with a permanent worker is assigned
workstation j; 0, otherwise, i = 1,..,N, j = 1,…,Kmax
Uij
1, if task i in phantom precedence diagram with a temporary worker is assigned
workstation j; 0, otherwise, i = 1,..,N, j = 1,…,Kmax
Yij
1, if task i in original precedence diagram with a temporary worker is assigned
workstation j; 0, otherwise, i = 1,..,N, j = 1,…,Kmax
PWj 1, if there is a permanent worker assigned to workstation j; 0, otherwise, j = 1,…,Kmax
TWj 1, if there is a temporary worker assigned to workstation j; 0, otherwise, j = 1,…,Kmax

to
to
to
to

2.1 U-line balancing model
The U-line goal programming balancing problem is developed first and then in the second
part straight assembly line balancing model is constructed. The goals of the line balancing problem

are:
Goal 1

∑ TW

Number of temporary worker should be minimized to reduce cost.
j =1

− d BT = 0
+

K max

j

(1)

Goal 2
To assure the product quality, one worker should not do too many jobs, so number of tasks that
can be done by one worker should be restricted. Number of tasks assigns in each workstation for
permanent worker and temporary worker should not difference to the number of tasks allowed.

∑V + ∑ X
N

N

i =1
N

∑U
i =1

i =1
N

ij

ij

ij

+ d −jAP − d +jAP = PW j .M p

+ ∑ Yij + d −jAT − d +jAT = TW j .M T
i =1

j = 1,..., K max

(2)

j = 1,..., K max

(3)

Goal 3

∑ TP .V + ∑ TP .X

The workstation time should be as closely as possible to the cycle time
N

N

i =1

36

i

ij

i =1

i

ij

+ d −jCP − d +jCP = PW j .C

j = 1,..., K max

(4)

Gede A. W. / Multi Objective Model for Balancing U-Type / JTI, Vol. 11, No. 1, Juni 2009, pp. 33-42

∑ TT .U

+ ∑ TTi .Yij + d −jCT − d +jCT = TW j .C

N

i =1

i

j = 1,..., K max

N

i =1

ij

∑d

∑d

∑d

The objective function can be derived from (1) to (5) as follows:

Min Z = C BT d

C


CP

∑d

K max
j =1

+C


jCP

+
BT

+
CP

+C


AP

∑d

K max
j =1

K max

+
jCP

j =1


jAP

+C


CT

+C

+
AP

∑d

K max
j =1

K max


jCT

j =1

+
jAP

+C

+
CT

+C


AT

∑d

K max
j =1

K max
j =1


jAT

+C

+
AT

+
jCT

∑d

K max
j =1

(5)
+
jAT

(6)

Constraints:

∑Vij +

∑ X ij +

∑U ij +

∑Y

1. Each task is assigned only in one workstation. The model is:
K max

K max

K max

K max

j =1

j =1

j =1

j =1

ij

=1

i = 1,..., N

(7)

2. A workstation can be assigned only with one type of worker. The constraint is modeled using
three inequalities as follows:

∑U
i =1
N

+ ∑ Yij ≤ M .TW j
N

N

ij

i =1
N

∑V + ∑ X
i =1

i =1

ij

ij

≤ M .PW j

PW j + TW j ≤ 1

j = 1,..., K max

(8)

j = 1,..., K max

(9)

j = 1,..., K max

(10)

3. Number of workstations assigned with a permanent worker is equal with number of available
permanent workers. This constraint can be modeled as follows:

∑ PW

K max
j =1

∑ (K

j

= PW

j = 1,..., K max

(11)

4. Precedence constraint for phantom and original network diagram are:
max

− j + 1)(Vsj − Vrj + U sj − U rj ) ≥ 0

(r , s) ∈ P

(12)

max

− j + 1)( X rj − X sj + Yrj − Ysj ) ≥ 0

(r , s ) ∈ P

(13)

K max
j =1

∑ (K

K max
j =1

5. Open workstation from lowest number can be modeled as:

PW j + TW j ≥ PW j +1 + TW j +1

j = 1,..., K max − 1

(14)

2.2. Straight line balancing model
Straight line balancing problem is developed by modifying U-line balancing problem. The
phantom network variables are eliminated and then (2) and (3) can be modified as (15) and (16).

∑X
N

i =1

ij

+ d −jAP − d +jAP = PW j .M p

j = 1,..., K max

(15)

37

Gede A. W. / Multi Objective Model for Balancing U-Type / JTI, Vol. 11, No. 1, Juni 2009, pp. 33-42

∑Y

+ d −jAT − d +jAT = TW j .M T

N

i =1

ij

j = 1,..., K max

(16)

In straight line balancing model, (4) and (5) can be formulated as:

∑ TP . X
N

i =1

i

∑ TT .Y

ij

N

i =1

i

ij

+ d −jCP − d +jCP = PW j .C
+ d −jCT − d +jCT = TW j .C

j = 1,..., K max

(17)

j = 1,..., K max

(18)

Constraints in (7), (8), and (9) can be remodeled as equation (19) to (21).

∑ X ij +

∑Y

K max

K max

j =1

j =1

∑Y

ij

∑X
N

i =1

=1

≤ M .TW j

N

i =1

ij

ij

≤ M .PW j

i = 1,..., N

(19)

j = 1,..., K max

(20)

j = 1,..., K max

(21)

Since (12) is equation for phantom network, so in a straight line model, the equation is
eliminated. The entire equation in a straight line balancing model is similar with the U-line
balancing model.
3. NUMERICAL EXAMPLE AND SENSITIVITY ANALYSIS
In this section, an example is shown to illustrate the goal programming model. The
permanent workers task times are cited from Gokcen and Agpak (2006) and the temporary
workers task times are generated randomly. The temporary workers task times are generated from
Uniform (1.1..2.0) times permanent workers task times. The details of task times are shown in
Table 1. Effective working hour in a day is assumed to be 8 hours and the manufacture has to
produce 40 units in a day.
The priority of the three goals that is used in the formulation is as follows:
Goal with priority level 1 (P1):
Number of maximal tasks in one workstation for a permanent or a temporary worker should
not exceed 5 and 3.
Goal with priority level 2 (P2):
Number of cycle time in each workstation should not exceed 12.
Goal with priority level 3 (P3):
Number of temporary workers should be minimized

38

Gede A. W. / Multi Objective Model for Balancing U-Type / JTI, Vol. 11, No. 1, Juni 2009, pp. 33-42

Table 1. Task times
Task
1
2
3
4
5
6
7
8
9
10
11

Task times (minutes)
Permanent workers
Temporary workers
6
11
2
4
5
8
7
13
1
2
2
4
3
4
6
7
5
7
5
8
4
8

The problem was solved using LINGO mathematical programming language on Pentium 41.8 GHz. The task assignment of the problem above is given in Table 2. If a workstation consists
of a phantom network, then the workstation is allocated with the succeeded task first. However, if
a workstation consists of an original network then the workstation is allocated with the precedence
task first. The optimal line balancing solution is shown in Figure 2.
Table 2. Task assignment
Workstation
1
2
3
4
5

Tasks
1, 2, 11
7, 9
8, 10
4, 5
3, 6

WS cycle time
12
11
11
8
12

Worker status
Permanent
Temporary
Permanent
Permanent
Temporary
WS 5

WS 1
1

Network
Original & phantom
Phantom
Phantom
Original & phantom
Original & phantom

3

2

6

4
WS 4
5

11

9

7
WS 2

8

10
WS 3

Figure 2. U-line balancing result
First, the sensitivity of the number of temporary workers in various maximal tasks is
analyzed. Table 3 shows number of temporary workers in the different number of permanent and
temporary workers maximal tasks. The table shows that in this case, number of temporary workers
is not sensitive in different of permanent and temporary workers maximal tasks.
39

Gede A. W. / Multi Objective Model for Balancing U-Type / JTI, Vol. 11, No. 1, Juni 2009, pp. 33-42

Table 3. Sensitivity analysis on worker maximal tasks
Maximal worker tasks
Permanent
Temporary
3
3
4
3
5
3
2
2
3
2
4
2
5
2

Number of temporary workers (TW)
2
2
2
3
2
2
2

In the next analyses, the goal priorities are rotated and the result can be seen in Table 4. The
table shows that the goals can not be satisfied simultaneously. The number of cycle time in each
station goal (P2) and the number of temporary workers goal (P3) are conflicting and the number of
maximal task in a workstation goal (P1) and P3 are not conflicting. When P2 is satisfied, P3 can
not be satisfied and vice versa. Table 4 also supports analysis that in this problem. P1 always can
be satisfied and when P2 has the highest priority then the solution is derived only by adding
temporary workers.
Table 4. Sensitivity analysis on sequence of priorities
Rotations

Priority 1

Priority 2

Priority 3

Unsatisfied
goals

1

P1

P2

P3

P3

d BT = 2

12

2

P1

P3

P2

P2

d 2+CP = 9

21

0

3

P2

P1

P3

P3

d BT = 2

12

3

4

P2

P3

P1

P3

d BT = 2

12

2

5

P3

P2

P1

P2

d 3+CP = 4

18

0

17

0

2

Value of non
Cycle time # of TW
zero
+

d1+CP = 1
+

+

d1+CP = 6

d1+CP = 2

6

P3

P1

P2

P2

d 2+CP = 5
d

+
3CP

=3

In the next step, performance of U-line balancing model is compared with straight line
balancing performance. The precedence diagram in Figure 1 and permanent workers tasks time in
Table 1 are used. Ten cases are generated by randomizing the temporary workers task times. The
goal programming solutions for the cases can be seen in Table 5. The table shows that U-line
balancing has better performance than the straight line balancing in three cases (case 2, 3, and 7)
and in seven cases, U-line and straight line balancing have equal performances.

40

Gede A. W. / Multi Objective Model for Balancing U-Type / JTI, Vol. 11, No. 1, Juni 2009, pp. 33-42

Table 5. Performance comparison of U-line and straight line balancing
Case
1
2
3
4
5
6
7
8
9
10

Number of temporary workers
U-line balancing
Straight line balancing
2
2
1
2
1
2
1
1
2
2
2
2
1
2
2
2
2
2
1
1

4. CONCLUSIONS
Goal programming U-line and straight line balancing models have been developed and some
sensitivity analyses are shown. The cycle time in each station goal and the number of temporary
workers goal are conflicting goals. When one goal has a higher priority, then the other one will be
unsatisfied. The result also shows that in some cases U-line balancing model has better
performance than straight line balancing model and in some cases both of them are equal.
This study shows that the U-line balancing has more benefit than the straight line balancing,
but the U-line balancing could be not to interesting since it needs more walking time. In the future
research, considering operator walking time will be an interesting and a useful research.
ACKNOWLEDGEMENTS
The author greatly appreciates the anonymous referees for their valuable and helpful suggestions.
REFERENCES
Agrawal, P. K., 1985. “The Related Activity Concept in Assembly Line Balancing.” International
Journal of Production Research, Vol. 23, pp. 403 – 421.
Baykasoglu, A., 2006. “Multi-Rule Multi Objective Simulated Annealing Algorithm for Straight
and U Type Assembly Line Balancing Problems.” Journal Intelligent Manufacturing, Vol.
17, pp. 217 – 232.
Corominas, A., Pastor, R., and Plans, J., 2008. “Balancing Assembly Line with Skilled and
Unskilled Workers.” Omega, Vol.36, pp. 1126-1132.
Erel, E., Sabuncuoglu, I., and Sederci, 2005. “Stochastic Assembly Line Balancing Using Beam
Search.” International Journal of Production Research, Vol. 43, pp. 1411 – 1426.
Gokcen, H. and Agpak, K., 2006. “A Goal Programming Approach to Simple U-Line Balancing
Problem.” European Journal of Operational Research, Vol. 170, pp. 577-585.
Kara, Y., Ozcan, U., and Peker, A., 2007. “Balancing and Sequencing Mixed-Model Just-in-Time
U-Lines with Multiple Objectives.” Applied Mathematics and Computation, Vol. 184, pp.
566-588.

41

Gede A. W. / Multi Objective Model for Balancing U-Type / JTI, Vol. 11, No. 1, Juni 2009, pp. 33-42

Kara, Y., Paksoy, T., and Chang, C. T., 2009. “Binary Fuzzy Goal Programming Approach to
Single Model Straight and U-Shaped Assembly Line Balancing.” European Journal of
Operational Research, Vol. 195, pp. 335-347.
Miltenburg J., 1998. “Balancing U-lines in a Multiple U-Line Facility.” European Journal of
Operational Research, Vol. 109, pp. 1-23.
Nakade, K., and Ohno, K., 1999. “An Optimal Worker Allocation Problem for a U-Shaped
Production Line.” International Journal of Production Economics, Vol. 60-61, pp.353-358.
Nakade, K., and Nishiwaki, R., 2008. “Optimal Allocation of Heterogeneous Workers in a UShaped Production Line.” Computers & Industrial Engineering, Vol. 54, pp. 432-440.
Ozcan, U., and Toklu, B., 2009. “Multiple-Criteria Decision-Making in Two-Sided Assembly
Line Balancing: A Goal Programming and a Fuzzy Goal Programming Models.”
Computers & Operations Research, Vol. 36, pp. 1955-1965.
Shin, D., and Min., 1991. “Uniform Assembly Line Balancing with Sthocastic Task Times in Justin-time Manufacturing.” International Journal of Operations and Production Management,
Vol 11, No. 8, pp. 32 – 34.
Toksari, M. D., Isleyen, S. K., Guner, E. and Baykoc, O. F., 2008. “Simple and U-type Assembly
Line Balancing Problems with a Learning Effect.” Applied Mathematical Modeling, Vol.
32, pp. 2954 – 2961.
Urban, T. L., 1998. “Note: Optimal Balancing of U-Shaped Assembly Lines.” Management
Science, Vol. 44, pp. 738-741.
Widyadana, G. A., 2001. “Comparison between Mixed Integer Programming with Heuristic
Method for Job Shop Scheduling with Separables Sequence-Dependent Setups.” Jurnal
Teknik Industri, Vol. 3, No. 1, pp. 9-17.

42