DRPLN-JM dan DRPPHLN

List of Planned Priority
External Loans (DRPPLN)
2011

Ministry of National Development Planning/
National Development Planning Agency
- 2011-

Foreword

The Government of Indonesia has compiled the annual List of Planned
Priority External Loan/Daftar Rencana Prioritas Pinjaman Luar Negeri (DRPPLN) for 2011
known as Green Book. The Green Book is one of the planning documents in the
process of planning projects that are eligible for being funded by external loan. The
projects that are listed in the Green Book are planned to be executed in the near future.
The 2011 Green Book contains 37 proposed projects in the total amount of
USD 5,279,427 billion, including grants in the total amount of USD 18,960 billion. The
2011 Green Book covers the projects of central and local governments, as well as
several state-owned enterprises.
The Green Book 2011 is published through the Decree of the Minister for
National Development Planning/Chairman of the National Development Planning

Agency Number KEP.95/M.PPN/HK/10/2011 with the publication of the 2011 Green
Book, it is expected that the planning and management of projects that are funded by
external loan become more effective and efficient to optimally benefit national
development and to increase the people welfare.

Minister for National Development Planning/
Chairman of the National Development Planning Agency,

Armida S. Alisjahbana

-i-

LIST OF PROJECT
Government Internal Control Agency
1.

State Accountability Revitalization (STAR) .................................................................................3

Ministry of Home Affairs
2.


Simeulue Physical Infrastructure - Phase II .................................................................................7

3.

National Program for Self-Reliant Rural Community Empowerment (PNPM IV) ................9

Ministry of Marine Affairs and Fisheries
4.

Infrastructure Development of Space Oceanography (INDESO Project) .............................. 13

5.

Coastal Community Development .............................................................................................. 18

Ministry of Public Works
Directorate General of Highways
6.


Bandung Intra Urban Toll Road (BIUTR) Development Project – Phase I ............................ 23

7.

Regional Roads Development – Phase I ..................................................................................... 25

8.

Tanjung Priok Access Road - Phase III ....................................................................................... 27

9.

Western Indonesia National Road Improvement Project (WINRIP) ......................................29

Directorate General of Human Settlements
10. Emission Reduction in Cities - Solid Waste Management ....................................................... 33
Directorate General of Water Resources
11. Construction of Karian Multipurpose Dam ............................................................................... 37
12. Jakarta Urgent Flood Mitigation Project (JUFMP) ....................................................................39
13. Upper Citarum Basin Flood Management Sector Loan............................................................ 42


Ministry of Education and Culture
14. Sustainable Economic Development Supported by Improving Technical and Vocational
Education ........................................................................................................................................47
15. Polytechnic Education Development Project .............................................................................49

Ministry of Transportation
Directorate General of Land Transportation
16. Intelligent Traffic Transport System in Jabodetabek ................................................................ 55
Directorate General of Sea Transportation
17. Improvement and Development of Indonesia Aids to Navigation ........................................59

- iii -

Directorate General of Railways
18. Procurement of Diesel Electric Locomotives ............................................................................. 63

Ministry of Agriculture
19. Sustainable Management of Agricultural Research and Technology Dissemination
(SMART-D) Project ....................................................................................................................... 67


Ministry of Manpower and Transmigration
20. Revitalization of Vocational Training Center ............................................................................ 73

Indonesian National Police
21. Integrated Trunking Radio Communication for Indonesian National Police – Phase I ...... 79
22. National Criminal Information Center for Indonesian National Police - Phase II ............... 81
23. Fast Patrol Boat for the Indonesian National Police ................................................................. 83

Indonesia Infrastructure Guarantee Fund
24. Indonesia Infrastructure Guarantee Fund ................................................................................. 87

PT. PERTAMINA
25. Geothermal Total Project Development in Lahendong, Unit 5&6 (2x20 MW) ..................... 91
26. Geothermal Total Project Development in Lumut Balai, Unit 3&4 (2x55 MW) .................... 93
27. Geothermal Total Project Development in Ulu Belu, Unit 3&4 (2x55 MW) .......................... 95

State Electricity Company
28. Containerized Diesel Power Plant .............................................................................................. 99
29. Engineering Service of Tulehu 1&2 Geothermal Power Plant (2x10 MW) .......................... 101

30. Java-Bali Submarine Cable 150 kV Circuit 3&4....................................................................... 103
31. Muara Tawar Add-on Block 2 Combined-Cycle Power Plant (500 MW) ............................ 105
32. Scattered Transmission and Sub-Station in Indonesia ........................................................... 107
33. Tulehu 1&2 Geothermal Power Plant (2x10 MW) .................................................................. 109
34. Upper Cisokan Pumped Storage Hydro Electrical Power Plants (1,000 MW).................... 111
35. Engineering Design Indramayu Steam Coal Power Plant 2x1,000 MW - Phase I .............. 113
36. Engineering Service of Hululais 1&2 Geothermal Power Plant (2x55MW) ........................ 115
37. Strenghthening West Kalimantan Power Grid ....................................................................... 117

- iv -

Government Internal Control Agency
(Badan Pengawas Keuangan dan Pembangunan / BPKP)

-1-

GB-11-1-001-0-1
1.

Project Title


: State Accountability Revitalization (STAR)

2.

Executing Agency

: Government Internal Control Agency (BPKP)

3.

Implementing Agency : Government Internal Control Agency (BPKP)

4.

Duration

: 60 months

5.


Location

: DKI Jakarta and 50 Inspectorates in Province/ Regency/ City.

6.

Objectives
The proposed STAR is expected to support the government for the implementation of GICS
(Government Internal Control System), improvement of capacity accountability of government
financial management and handling of public complaint. The performance targets are:
 2.500 accountants majoring in Government Audit and Accounting to be located in central
and local government institutions;
 10.000 internal auditors and financial management staff to follow short-term training in
order to increase capacity in monitoring the implementation of internal control
implementation and increase capacity, and accountability of state finance management.

8.

9.


Scope of Projects
a.

Degree scholarship program for government internal auditors, finance officials of central
and local government institutions;

b.

Non degree scholarship program for government internal auditors, finance officials of
central and local government institutions;

c.

Establishment of public complaint unit in local inspectorates.

Activities
Activities

Implementation Locations


a. Scholarship program
b. Establishment of public
complaint Unit

Project Implementation Units

DKI
Jakarta
and
50 BPKP
Inspectorates in Province/
Regency/ City.

10. Funding Source
Implementing
Agency
BPKP
Total


Funding (US $ 000)
Loan

Grant

Local

Total

57,800

1,400

59,200

57,800

1,400

59,200

-3-

Source
ADB

GB-11-1-001-0-1
11. Disbursement Plan
Disbursement Plan (US $ 000)
1st

2nd

3rd

4th

5th

3.213

11.831

11.831

20.494

11.831

Total
59.200

12. Funding Allocations *)
Activities

Categories (US $ 000)
Services

Constructions

*) data not available

13. Project References
BB 2011 - 2014 ID: BB-1114-R0-001-0

-4-

Goods

Trainings

Others

Ministry of Home Affairs
(Kementerian Dalam Negeri)

-5-

GB-11-1-002-0-1
1.

Project Title

: Simeulue Physical Infrastructure - Phase II

2.

Executing Agency

: Ministry of Home Affairs

3.

Implementing Agency : Local Government of Simeulue District

4.

Duration

: 48 months

5.

Location

: Simeulue, Nanggroe Aceh Darussalam

6.

Objectives

7.

8.

a.

To increase human resources mastering general knowledge and technology for plantation;

b.

To increase the facilities and infrastructure to support the growth of agriculture and
trading sectors;

c.

To strengthen the structure of agriculture and trading sectors in order to boost the
economic growth;

d.

To create a conducive business atmosphere in the development of agriculture and trading
sector to face the global market.

Scope of Projects
a.

Establishment of infrastructure for Palm Plantation and Palm Oil Factory;

b.

Procurement of equipment for palm oil factory;

c.

Provision of consultancy.

Activities
Activities

Implementation Locations

a. Civil works

Simeulue District

Project Implementation
Units
Local Government of
Simeulue District

b. Procurement of equipment
c. Procurement of furniture
d. Consulting services
e. PMU
9.

Funding Source
Implementing Agency
Local Government of
Simeulue District
Total

Funding (US $ 000)
Loan

Grant

Local

Total

20,000

3,071

23,071

20,000

3,071

23,071

-7-

Source
IDB

GB-11-1-002-0-1
10. Disbursement Plan
Disbursement Plan (US $ 000)
2nd
3rd
4th

1st
2,600

6,000

6,600

Total

5th

23,071

7,871

11. Funding Allocations
Activities

Categories (US $ 000)
Services

Constructions

Goods

Trainings

Others

a. Civil works:
- palm plantation

9,437.34

- palm oil factory

1,793.10

b. Procurement of equipment

5,836.21

c. Furniture

50.00

d. Capacity building and
training
e. Consulting services

123.43
916.73

f. Project management unit

25.00

g. Contingency
Total

4,889.19
916.73

11,230.44

12. Project References
BB 2011-2014 ID: BB-1114-R0-006-0

-8-

5,986.21

123.43

4,914.19

GB-11-1-003-0-1
1.

Project Title

: National Program for Self-Reliant Rural Community Empowerment
(PNPM IV)

2.

Executing Agency

: Ministry of Home Affairs

3.

Implementing Agency : Directorate General of Community Empowerment, Ministry of
Home Affairs

4.

Duration

: 24 months

5.

Location

: Nationwide

6.

Objectives
To accelerate poverty alleviation that based on community self-reliant empowerment through
community and local government capacity improvement, and basic social and economy
infrastructure provision.

7.

8.

Scope of Projects
a.

To promote community participation in development planning and management;

b.

To fill infrastructure gap as well as to promote more efficient delivery of services to the
rural communities;

c.

To develop local government capacities in the formulation and implementation of propoor policies and approaches.

Activities
Implementation
Locations

Activities
Facilitation support

Nationwide

Implementation support and technical
assistance
Project management support
9.

Project Implementation
Units
Directorate General of
Community
Empowerment, Ministry
of Home Affairs

Funding Source
Implementing Agency
Directorate General of
Community
Empowerment,
Ministry of Home
Affairs
Total

Funding (US $ 000)
Loan

Grant

Local

Total

Source

131,000

131,000 Word Bank

131,000

131,000

-9-

GB-11-1-003-0-1
10. Disbursement Plan
Disbursement Plan (US $ 000)
2nd
3rd
4th

1st
29,758

Total

5th

131,000

101,242

11. Funding Allocations
Activities

Categories (US $ 000)
Services

Facilitation support

99,110

Implementation support and
technical assistance

30,790

Project management support

1,100

Total

Constructions

131,000

12. Project References
BB 2011-2014 ID: BB-1114-R0-005-0

- 10 -

Goods

Trainings

Others

Ministry of Marine Affairs and Fisheries
(Kementerian Kelautan dan Perikanan

- 11 -

GB-11-1-004-0-1
1.

Project Title

: Infrastructure Development of Space Oceanography (INDESO
Project)

2.

Executing Agency

: Ministry of Marine Affairs and Fisheries

3.

Implementing Agency : a. Institute of Marine Research and Observation, Perancak, Bali
b. Agency for Marine and Fisheries Research, Ministry of Marine
Affairs and Fisheries

4.

Duration

: 36 months

5.

Location

: DKI Jakarta and Bali

6.

Objectives
To develop space oceanography infrastructure and several of its applications which will
support the Ministry of Marine Affairs and Fisheries programs.

7.

Scope of Projects
a.

Development of Oceanic and Biological Modeling, including:
1)

2)

Observation network including both satellite and in situ data to monitor the state of
ocean in near-real time (water temperature, phytoplankton, sea level, currents) and
provide all data needed to run numerical models of the ocean physics,
biogeochemistry and ecosystems;
3-D regional ocean modeling system including:
a) Ocean model simulating the oceanic circulation and biogeochemistry of the
Indonesian seas;
b)

3)
b.

Marine ecosystem and fish population dynamics model;

Marine information system, includes advanced data visualization software.

Development of reception and processing satellite data, including:
1)
2)
3)
4)

Reception station satellite data to cover all area of Indonesian exclusive economic zone
and receiving data from optical and radar satellite;
Infrastructure integrated with in situ marine monitoring network for simplifying
model of arrangement and calibration;
Special physics and biochemistry sea model configuration associated with dynamics
population of large pelagic fish species model;
Indonesian oceanic model system:
a) In-situ network: drifters, floats, anchored buoys;
b) Monitoring regional sea via satellite - based on optical and Radar;
c) Dynamic fish population model adapted from an ecosystem dynamics of the
fishery resources model;
d) Specific implementation of management information infrastructure (information
technology);
e) Tools for visualization and analysis of scientific data exploitation;
f) Complete data acquisition system.

- 13 -

GB-11-1-004-0-1
8.

Activities
Project
Implementation
Implementation
Locations
Units

Activities
a. Oceanic and Biological Modeling:

DKI Jakarta

 Management
 In Situ data acquisition network based on existing
installations (tide gauges, etc) plus new moorings
to constrain models in the main inflow regions
 Acquisition of forcing and assimilation data,
specific software development for automatic
acquisition of surface forcing data, boundary
forcing data and assimilation data
 License and parameterization of software of the
INDESO specific configuration of data
management system and data visualizations
system
 Adaptation and configuration of physical ocean
model over the Indonesian waters up to the
production of a realistic one year simulation
 Adaptation and configuration of biogeochemical
model of a regional ocean biogeochemistry model
coupled with the circulation model up to the
production of a realistic one year
 Configuration of Fish Population Dynamics
Model (2 species) of a regional version of fish
population dynamics model models up to the
production of a realistic one year simulation for
two fish species
 Calibration and validation of the one-year
simulation of the regional model of the ocean
circulation, biogeochemistry and fish population
dynamics in the Indonesian waters based on
existing observations
 Transfer and installation of the complete data
acquisition and modeling software to Agency for
Marine and Fisheries Research operational center

- 14 -

Agency for
Marine and
Fisheries,
Research
Institute of
Marine
Research and
Observation

GB-11-1-004-0-1

Implementation
Locations

Activities
 Operational production of real-time
simulations with the coupled ocean model
(circulation, biogeochemistry population
dynamics, includes model runs, analysis,
dissemination, and software maintenance
and software evolutions
 Procurement of hardware to perform the initial
code development and maintenance

DKI Jakarta

DKI Jakarta

 Coordination and training activities
Bali

 Application center deployment, system, installation
and training
 Infrastructure maintenance and support to
operations, including antenna system for hotline
and preventive maintenance, Radar processing
system, optical processing system, remote support
to operations
 Satellite data, including Envisat telemetry,
Radarsat-2 telemetry, Spot-4 and Spot-5 telemetry
 Support to application development: Radar
applications, optical applications,
 Training (in Indonesia and abroad) and remote
support to process 100 satellite passes

- 15 -

Agency for Marine
and Fisheries,
Research
Institute of Marine
Research and
Observation

 Human resources development

 Infrastructure, including antenna system, optical
processing system (Spot-4 and Spot-5), Radar
processing system (Envisat and Radarsat-2), civil
works, project management

Agency for Marine
and Fisheries,
Research
Institute of Marine
Research and
Observation

 Training of the Agency for Marine and Fisheries
Research engineers/scientists

b. Reception and Processing:

Project
Implementation
Units

GB-11-1-004-0-1
9.

Funding Source
Funding (US $ 000)

Implementing Agency

Loan

Agency for Marine and
Fisheries, Research

Grant

Local

Total

30,000

1,500

31,500

30,000

1,500

31,500

Source
AFD

Institute of Marine Research
and Observation
Total
10. Disbursement Plan
Disbursement Plan (US $ 000)
1

20,000

11.

2

st

nd

7,000

3rd

4th

5th

Total
31,500

4,500

Funding Allocations
Categories (US $ 000)
Activities
a. Management
b. In Situ data acquisition
c. Acquisition of forcing and
assimilation data
d. License and parameterization of
software
e. Adaptation and configuration of
physical ocean model
f. Adaptation and configuration of
biogeochemical model
g. Adaptation of Configuration of
Fish Population Dynamics
Model
h. Calibration and Validation
i. Transfer and installation of the
complete data acquisition and
modeling software
j. Operations
k. Hardware
l. Training for engineers/ scientists
m. Human resources development

Services

Constructions

Goods

Trainings

845.25
793.80
485.10
514.50
970.20
837.90
1,043.70

749.70
514.50

1,543.50
455.70
90.00
1,017.20

- 16 -

Others

GB-11-1-004-0-1
Categories (US $ 000)
Activities
n. Coordination and training
activities
o. Infrastructure
p. Application center deployment
q. Infrastructure maintenance and
support to operations
r. Satellite data
s. Support to application
development
t. Project management office
u. Engineering support
v. Management
w. Infrastructure
x. Research
Total

ConstructServices
ions

Goods

Trainings

Others

176.40
8,522.20
805.43
999.69
7,917.00
668.22
630.00
420.00
350.00
550.00

600.00
9,172.26

12. Project References
BB 2011 - 2014 ID: BB-1114-R0-008-0

- 17 -

9,916.00

8,372.70

2,089.04

1,950.00

GB-11-1-005-0-1
1.

Project Title

: Coastal Community Development

2.

Executing Agency

: Ministry of Marine Affairs and Fisheries

3.

Implementing Agency : Ministry of Marine Affairs and Fisheries

4.

Duration

: 60 months

5.

Location

: 13 Districts : Merauke District, Yapen District, Southeast Maluku
District, Ambon City, Ternate City, Kupang City, West Lombok
District, Bitung City, North Gorontalo District, Makassar City, ParePare City, Kubu Raya District, and Badung District.

6.

Objectives
a. To reduce poverty and enhance sustainable economic growth in poor and potentially active
coastal and small island communities;
b. To increase household incomes for families involved in fisheries and marine activities in
coastal and small island communities.

7.

Scope of Projects
There are four main elements that are central to the project: (i) Community Empowerment, (ii)
Market Based Strategy (iii) Focus on the active poor, and (iv) Replication /scaling up. They are
in sense the core of the project and provide the foundation for deciding on project activities
and how they are implemented.
The Project Activities are divided into three components:

8.

1.

Community Empowerment, Development and Resource Management;

2.

District Support For Marine-Based Economic Development District Support For MarineBased Economic Development;

3.

Project Management.

Activities
Implementation
Locations

Activities
a. Community Empowerment,
Development and Resource
Management;
b. District Support For Marine-Based
Economic Development District
Support For Marine-Based Economic
Development;
c. Project Management.

13 Districts : Merauke
District, Yapen District,
Southeast Maluku
District, Ambon City,
Ternate City, Kupang
City, West Lombok
District, Bitung City,
North Gorontalo
District, Makassar City,
Pare-Pare City, Kubu
Raya District, and
Badung District.

- 18 -

Project Implementation
Units
PMO DG MCSI,
Ministry of Marine
Affairs and Fisheries

GB-11-1-005-0-1
9.

Funding Source
Funding (US $ 000)

Implementing
Agency

Loan

Ministry of
Marine Affairs
and Fisheries
Total

Grant

Local

Source

Total

32,000

4,000

36,000

32,000

4,000

36,000

ADB

10. Disbursement Plan
Disbursement Plan (US $ 000)
1st

2nd

3rd

4th

5th

300

9,000

10,000

11,000

5,700

Total
36,000

11. Funding Allocations
Activities
1)

Categories (US $ 000)
Services

3,000

b. Resource Assessment,
Planning and CoManagement

2,500

c. Market Focused Village
Development

3,000

1,000

Trainings

3,500

1,500

25

4,500

5,000

155

2,000

2,400

District Support For
Marine-Based Economic
Development

a. District Investment in
Small-Scale Fisheries
b. Market/Value Chain
Support
3)

Goods

Community
Empowerment,
Development and
Resource Management

a. Community Facilitation,
Planning and Monitoring

2)

Constructions

320

Project Management

3,500

Total

12,320

500

8,000

12. Project References
BB 2011 - 2014 ID: BB-1114-R0-007-0

- 19 -

1,500
600

1,000

9,500

6,180

Others

Ministry of Public Works
(Kementerian Pekerjaan Umum)
Directorate General of Highways
(Direktorat Jenderal Bina Marga)

- 21 -

GB-11-1-006-0-1
: Bandung Intra Urban Toll Road (BIUTR) Development Project –
Phase I
: Ministry of Public Works

1.

Project Title

2.

Executing Agency

3.

Implementing Agency : Directorate General of Highways, Ministry of Public Works

4.

Duration

: 48 months

5.

Location

: Bandung, West Java

6.

Objectives

7.

8.

a.

To improve access and capacity of road networks and goods distribution leading to
improve Bandung Metropolitan Area;

b.

To enhance city development and its suburb areas to enhance the economic development;

c.

To accelerate the development of eastern Bandung area and its surrounding within
Bandung Metropolitan Area through the improvement of accessibility directly toward the
city by developing toll road network.

Scope of Projects
a.

Project pre-development (detailed engineering design, tender assistance);

b.

Construction of 54.6 km toll road;

c.

Construction supervision.

Activities
Activities

Implementation Locations

Construction and supervision Bandung

9.

Project Implementation Units
Directorate General of
Highways, Ministry of Public
Works

Funding Source
Implementing Agency
Directorate General of
Highways, Ministry of Public
Works
Total

Funding (US $ 000)
Loan

Grant

Local

Total

150,000

15,000

165,000

150,000

15,000

165,000

Source
JICA
(Japan)

10. Disbursement Plan
1st

2nd

16,500

49,500

Disbursement Plan (US $ 000)
3rd
4th
66,000

33,000

- 23 -

5th

Total
165,000

GB-11-1-006-0-1
11. Funding Allocations
Activities

Categories (US $ 000)
Services

a. Civil works
b. Consultancy services

16,500

Total

16,500

Constructions
148,500
148,500

12. Project References
BB 2011 - 2014 ID: BB-1114-R0-014-0

- 24 -

Goods

Trainings

Others

GB-11-1-007-0-1
1.

Project Title

: Regional Roads Development – Phase I

2.

Executing Agency

: Ministry of Public Works

3.

Implementing Agency

: Directorate General of Highways, Ministry of Public Works

4.

Duration

: 60 months

5.

Location

: Central Java, East Java, East Kalimantan, and West Kalimantan
Provinces

6.

Objectives

7.

a.

To improve important national or strategic road corridors in northern Kalimantan and
southern Java to encourage economic growth;

b.

To improve the connectivity and access to services in project locations, as well as
developing regional road connections from Kalimantan to adjoining countries to support
the Brunei Darussalam - Indonesia – Malaysia – Philippines – East ASEAN Growth Area
(BIMP-EAGA) initiatives by the rehabilitation, capacity expansion, and construction of
highways and rehabilitation of sub-standard bridges.

Scope of Projects
Development and improvement of roads and bridges in northern corridor of Kalimantan
Island and southern corridor of Java Island.

8.

Activities
Activities
Construction and
improvement of roads and
bridges

9.

Implementation Locations
Central Java, East Java, West
Kalimantan, East Kalimantan
Provinces

Project Implementation
Units
Road Development Project
Office in each province

Funding Source
Implementing
Agency
Directorate General
of Highways,
Ministry of Public
Works
Total

Funding (US $ 000)
Loan

Grant

Local

Total

250,000

50,000

300,000

250,000

50,000

300,000

- 25 -

Source
ADB/IDB

GB-11-1-007-0-1
10. Disbursement Plan
Disbursement Plan (US $ 000)
1

2

st

33,500

nd

53,000

Total

3rd

4th

5th

100,000

65,400

48,100

300,000

11. Funding Allocations
Activities

Categories (US $ 000)
Services

Constructions

Goods

Trainings

a. Land acquisition and
resettlement

Others
20,600

b. Civil works

223,600

c. Consultancy services

15,300

d. Road safety program

1,000

e. Java transport study

1,200

f. Capacity building for
Directorate General of
Highways

1,600

g. HIV/AIDS and antitrafficking program

200

h. Taxes and duties

20,900

i.

Contingencies

15,200

j.

Others

400
Total

17,500

223,600

12. Project References
BB 2011 - 2014 ID: BB-1114-R0-023-0

- 26 -

1,600

57,300

GB-11-1-008-0-1
1.

Project Title

: Tanjung Priok Access Road - Phase III

2.

Executing Agency

: Ministry of Public Works

3.

Implementing Agency : Directorate General of Highways, Ministry of Public Works

4.

Duration

: 36 months

5.

Location

: DKI Jakarta

6.

Objectives

7.

8.

a.

To avoid serious traffic congestion, thereby contributing to sustainable urban activities;

b.

To supplement the function of radial toll roads and the Cengkareng access;

c.

To enhance physical distribution originating from Tanjung Priok International Port;

d.

To support improved land use in Jabodetabek area.

Scope of Projects
a.

Construction of 4 (four) packages, including Section W-1 and W-2;

b.

Consulting services.

Activities
Activities

Implementation Locations

Construction and
supervision

9.

DKI Jakarta

Project Implementation Units
Directorate General of
Highways, Ministry of Public
Works

Funding Source
Implementing Agency
Directorate General of
Highways, Ministry of Public
Works
Total

Funding (US $ 000)
Loan

Grant

Local

Total

120,000

120,000

120,000

120,000

Source
JICA
(Japan)

10. Disbursement Plan
Disbursement Plan (US $ 000)
3rd
4th

1st

2nd

36,000

48,000

5th

Total
120,000

36,000

- 27 -

GB-11-1-008-0-1
11. Funding Allocations
Activities

Categories (US $ 000)
Services

Constructions

a. Civil works
b. Consultancy services
Total

108,000
12,000
12,000

108,000

12. Project References
BB 2011 - 2014 ID: BB-1114-R0-012-0

- 28 -

Goods

Trainings

Others

GB-11-1-009-0-1
1.

Project Title

: Western Indonesia National Road Improvement Project (WINRIP)

2.

Executing Agency

: Ministry of Public Works

3.

Implementing Agency : Directorate General of Highways, Ministry of Public Works

4.

Duration

: 60 months

5.

Location

: Western Indonesia Region

6.

Objectives

7.

8.

a.

To improve national road network to an acceptable standard of service;

b.

To support local and regional economic development.

Scope of Projects
a.

Preservation of the national roads and bridges;

b.

Connection of strategic roads in western Indonesia region.

Activities
Activities

Implementation Locations

a. Civil works

Project Implementation Units

Western Indonesia Region

Directorate General of
Highways, Ministry of Public
Works

b. Consulting services
9.

Funding Source
Funding (US $ 000)

Implementing Agency

Loan

Directorate General of
Highways, Ministry of
Public Works
Total

Grant

Local

Total

250,000

20,000

270,000

250,000

20,000

270,000

Source
World
Bank

10. Disbursement Plan
Disbursement Plan (US $ 000)
1

2

st

50,000

nd

50,000

3rd

4th

5th

70,000

70,000

30,000

Total
270,000

11. Funding Allocations
Activities

Categories (US $ 000)
Services

Constructions
250,000

a. Civil works
b. Consulting services
Total

20,000
20,000

250,000

- 29 -

Goods

Trainings

Others

GB-11-1-009-0-1
12. Project References
BB 2011 - 2014 ID: BB-1114-R0-028-0

- 30 -

Directorate General of Human Settlements
(Direktorat Jenderal Cipta Karya)

- 31 -

GB-11-1-010-0-1
1.

Project Title

: Emission Reduction in Cities - Solid Waste Management

2.

Executing Agency

: Ministry of Public Works

3.

Implementing Agency : Directorate General of Human Settlements, Ministry of Public
Works

4.

Duration

: 24 months

5.

Location

: Nationwide

6.

Objectives

7.

8.

a.

To decrease greenhouse gas emission;

b.

To promote environmental friendly urban development;

c.

To enhance the prosperity and quality of life in urban area.

Scope of Projects
a.

Rehabilitation of solid waste disposal waste;

b.

Application of clean development mechanism.

Activities
Implementation
Locations

Activities
a. Evaluate performance of final disposal site

Nationwide

b. Evaluate pollution condition
c. Public campaign

Project Implementation
Units
Directorate General of
Human Settlements,
Ministry of Public Works

d. Determine the appropriate and cost
effective system
e. Detailed engineering design preparation
f. Construction
g. Environmental impact assessment
9.

Funding Source
Implementing Agency
Directorate General of
Human Settlements,
Ministry of Public
Works
Total

Funding (US $ 000)
Loan

Grant

Local

Total

32,780

20,000

52,780

32,780

20,000

52,780

- 33 -

Source
KfW
(Germany)

GB-11-1-010-0-1
10. Disbursement Plan
Disbursement Plan (US $ 000)
1st

2nd

20,000

32,780

3rd

4th

5th

Total
52,780

11. Funding Allocations *)
Activities

Categories (US $ 000)
Services

Constructions

a. Consultation service
b. Detailed Engineering
Design preparation
c. Construction
d. Environmental impact
assessment
Total
*) Data not available

12. Project References
BB 2011 - 2014 ID: BB-1114-R0-032-0

- 34 -

Goods

Trainings

Others

Directorate General of Water Resources
(Direktorat Jenderal Sumber Daya Air)

- 35 -

GB-11-1-011-0-1
1.

Project Title

: Construction of Karian Multipurpose Dam

2.

Executing Agency

: Ministry of Public Works

3.

Implementing Agency : Cidanau-Ciujung-Cidurian River Basin Organization

4.

Duration

: 84 months

5.

Location

: Lebak District, Banten Province

6.

Objectives

7.

a.

To provide domestic, municipal, and industrial water supply to Serang, Tangerang, and
DKI Jakarta, and

b.

To provide irrigation water supply for about 23,000 ha of the existing Ciujung and
Rancasumur areas.

Scope of Projects
Development of water resources in Ciujung and Cidurian river basins, including:

8.

a.

Consulting services for dam construction;

b.

River diversion;

c.

Construction of the main dam and saddle dams;

d.

Construction of spillway;

e.

Construction of intake and discharge facilities;

f.

Other supporting facilities.

Activities
Implementation
Locations

Activities

a. Organizing the project monitoring team
Lebak District,
and commission for managing the project Banten Province
b. Selection of consultant
c. Detailed design review and preparation
of bidding documents
d. Contract award
e. Construction works
f. Construction supervision
g. Impounding
h. Test run and training

- 37 -

Project Implementation
Units
Cidanau-Ciujung-Cidurian
River Basin Organization

GB-11-1-011-0-1
9.

Funding Source
Implementing Agency
Cidanau-Ciujung-Cidurian
River Basin Organization
Total

Funding (US $ 000)
Loan

Grant

Local

Total

100,000

9,900

109,900

100,000

9,900

109,900

Source
EDCF
(Korea)

10. Disbursement Plan
Disbursement Plan (US $ 000)
1st

2nd

3rd

4th

5th

6th

7th

6,614

10,712

23,981

32,804

24,855

10,535

399

Total
109,900

11. Funding Allocations
Categories (US $ 000)
Activities

Services

Constructions

Goods

Trainings

Others

a. Direct construction


General items



River diversion

11,730



Main dam

43,232



Saddle dam



Spillway



Intake and outlet facilities

2,281



Hydro-mechanical works

5,827



Electrical works

347



Telecommunication and
control

280



O&M Equipment

b. Consulting services

1,996

1,022
17,374

117
6,851

c. Miscellaneous
TOTAL

18,843
6,851

12. Project References
BB 2011 - 2014 ID: BB-1114-R0-047-0

- 38 -

84,089

117

18,843

GB-11-1-012-0-1
1.

Project Title

: Jakarta Urgent Flood Mitigation Project (JUFMP)

2.

Executing Agency

: Ministry of Public Works

3.

Implementing Agency : a. Directorate General of Water Resources, Ministry of Public
Works

4.

Duration

: 36 months

5.

Location

: DKI Jakarta

6.

Objectives

b. Local Government of DKI Jakarta Province

7.

a.

To prioritize flood mitigation in the most flood-prone areas in DKI Jakarta;

b.

To reduce the economic and social cost of flooding by partially restoring the capacity of
the city’s flood control system;

c.

To strengthen the capacity of DKI Jakarta to operate and maintain flood control system
according to standards and practices needed for a metropolitan area of national
importance;

d.

To alleviate the impacts of annual floods in DKI Jakarta and its surrounding areas through
the rehabilitation of the existing floodways, drains, and retention basins.

Scope of Projects
a.

Urgent dredging of 4 (four) floodways under the authority of the Ministry of Public
Works (MPW), namely Cakung Floodways, Sunter River, Cengkareng Floodway, and
West Channel Flood/Banjir Canal Barat;

b.

Absorbing the dredged spoil arising which is estimated at 6.7 million m3, of which 3.5
million m3 are to be removed from floodways under MPW responsibility;

c.

Rehabilitation of pumping stations and bar screens in retention basins;

d.

Establishment/enhancement of legal, regulatory, and institutional change;

e.

Fiscal arrangement for operation and maintenance financing.

- 39 -

GB-11-1-012-0-1
8.

Activities
Activities
a. Urgent
maintenance
dredging

b. Construction of
disposal site for
dredge spoil
c. Rehabilitation of
river
embankments

Implementation Locations
Sunter River, Cengkareng Floodway, West
Banjir Canal, Lower Angke, CidengThamrin, Tanjungan
Krukut-Cideng, Sentiong-Sunter, CiliwungGunung Sahari, Pakin – Kali Besar Jelakang,
Diversion of Grogol-Sekretaris-Angke
Waduk Pluit, Waduk North Sunter, Waduk
South Sunter, Waduk East Sunter III, Waduk
Melati
Jakarta

Project Implementation
Units
MPW, Floodways
MPW, Strategic Drains
DKI Jakarta
Main Drains
DKI Jakarta
Retention Basin
PT. Pembangunan Jaya
Ancol

Sunter River, Cengkareng Floodway, West
Banjir Canal

MPW, Floodways

Lower Angke, Cideng-Thamrin, Tanjungan

MPW, Strategic Drains

Krukut-Cideng, Sentiong-Sunter, Ciliwung- DKI Jakarta
Gunung Sahari, Pakin – Kali Besar Jelakang, Main Drains
Diversion of Grogol-Sekretaris-Angke
Waduk Pluit, Waduk North Sunter, Waduk DKI Jakarta
South Sunter, Waduk East Sunter III, Waduk Retention Basin
Melati
d. Capacity building
and project
implementation
support
9.

Jakarta

DKI Jakarta

Funding Source
Implementing Agency

Funding (US $ 000)
Loan

DGWR

77,500

DKI Jakarta Province

73,000

Total

150,500

Grant
6,000

Local
12,600

Total
96,100
73,000

6,000

- 40 -

12,600

169,100

Source
World Bank

GB-11-1-012-0-1
10. Disbursement Plan
Disbursement Plan (US $ 000)
1st

2nd

3rd

4th

25,000

115,000

29,100

Total

5th

169,100

11. Funding Allocations
Activities

Categories (US $ 000)
Services Constructions

a. MPW - Dredging
Embankments, Pumps,
Racks, Maintenance

70,000

b. DKI - Dredging
Embankments, Pumps,
Racks, Maintenance

50,020

c. Supervision Consultant

Goods

Trainings

7,500

d. Resettlement

12,600

e. Ancol CDF Construction

22,980

f. Capacity Building
Support for PMU
Total

Others

6,000
7,500

143,000

12. Project References
BB 2011 - 2014 ID: BB-1114-R0-054-0

- 41 -

6,000

12,600

GB-11-1-013-0-1
1.

Project Title

: Upper Citarum Basin Flood Management Sector Loan

2.

Executing Agency

: Ministry of Public Works

3.

Implementing Agency : Citarum River Basin Organization

4.

Duration

: 72 months

5.

Location

: Bandung District, West Java Province

6.

Objectives

7.

8.

a.

To control flood which will enhance the productive activities in the project area and will
contribute to economic growth and improvement of the living standard;

b.

To promote socio-economic activities in Upper Citarum Basin by means of materializing
the mitigation of flood damages by flood control and drainage improvement works ;

c.

To create a favorable environment.

Scope of Projects
a.

Non-structural countermeasures, including strengthening of early warning system, flood
hazard mapping, community disaster prevention activities;

b.

Sediment control.

Activities
Implementation
Locations

Activities
a. Selection of consultants

Bandung, West
Java

b. Consulting services

Project Implementation
Units
Citarum River Basin
Organization

c. Selection of contractor and supervision
services for river improvement works
d. Strengthening non-structural
countermeasures
9.

Funding Source
Implementing Agency
Citarum River Basin
Organization
Total

Funding (US $ 000)
Loan

Grant

Local

Total

40,000

25,000

65,000

40,000

25,000

65,000

- 42 -

Source
JICA
(Japan)

GB-11-1-013-0-1
10. Disbursement Plan
Disbursement Plan (US $ 000)
1

st

8,800

2

10,200

Total

3rd

4th

5th

6th

13,300

17,500

11,500

3,700

nd

65,000

11. Funding Allocations
Activities

Categories (US $ 000)
Services

Constructions

a. River improvement works

Goods

Trainings

Others

33,270

b. Flood plan management

1,035

c. Consulting services

8,295

d. Sediment control

1,940

e. Price escalation

9,960

f. Physical contingency

2,310

g. Administration

2,900

h. Tax and duties

5,290

Total

9,330

35,210

12. Project References
BB 2011 - 2014 ID: BB-1114-R0-056-0

- 43 -

20,460

Ministry of Education and Culture
(Kementeran Pendidikan dan Kebudayaan)

- 45 -

GB-11-1-014-0-1
1.

Project Title

: Sustainable Economic Development Supported by Improving
Technical and Vocational Education

2.

Executing Agency

: Ministry of Education and Culture

3.

Implementing Agency : a. Ministry of Education and Culture
b. Ministry of Industry
c. Ministry of Manpower and Transmigration

4.

Duration

: 36 months

5.

Location

: Yogyakarta, Central Java, West Java, Bali, South Sulawesi, East
Kalimantan, West Nusa Tenggara, South Sumatera

6.

Objectives

7.

8.

a.

To improve the quality of vocational graduates through skill-approach learning in
response to labor market demand;

b.

To improve the quality and relevancy of vocational school with international benchmark
graduates to produce skilled and adaptable workers;

c.

To improve the quality of standards of Technical and Vocational Education and Training
(TVET);

d.

To increase the participation of vocational school graduates in industries including as
entrepreneurs;

e.

To enhance the capability and facility of selected vocational schools;

f.

To improve selected training center/Balai Latihan Kerja (BLK).

Scope of Projects
a.

Developing coherent strategies to improve the quality of TVET;

b.

Broadening access to (self) employment in relevant competencies as part of lifelong
learning;

c.

Improving labor market information for TVET planning and implementation;

d.

Enhancing and recognizing the standard based national assessment and certification
system.

Activities
Activities
Civil works, equipment,
consultant, and training of
operational equipment

Implementation Locations
Yogyakarta, Central Java, West
Java, Bali, South Sulawesi, East
Kalimantan, West Nusa
Tenggara, South Sumatera

- 47 -

Project Implementation Units
Ministry of Education and
Culture,
Ministry of Industry,
Ministry of Manpower and
Transmigration.

GB-11-1-014-0-1
9.

Funding Source
Funding (US $ 000)

Implementing
Agency

Loan

Ministry of National
Education
Total

Grant

Local

Total

25,387

12,960

10,500

48,847

25,387

12,960

10,500

48,847

Source
KfW
(Germany)

10. Disbursement Plan
Disbursement Plan (US $ 000)
1

2

st

15,000

3rd

nd

18,000

4th

Total

5th

48,847

15,847

11. Funding Allocations
Activities

Categories (US $ 000)
Services

Constructions

a. Procurement of equipment

Trainings

10,000
4,300

d. Project management
supervision

2,547

e. Others
Total

Others

20,000

b. Rehabilitation/
infrastructure construction
c. Consulting services

Goods

4,300

10,000

12. Project References
BB 2011 - 2014 ID: BB-1114-R0-065-0

- 48 -

20,000

2,000

10,000

2,000

12,547

GB-11-1-015-0-1
1.

Project Title

: Polytechnic Education Development Project

2.

Executing Agency

: Ministry of Education and Culture

3.

Implementing Agency : a. Directorate General of Higher Education, Ministry of Education
and Culture

4.

Duration

: 48 months

5.

Location

: West Java, East Java, Lampung, West Sumatera, South Kalimantan,
East Kalimantan, North Sulawesi, South Sulawesi, Bali, NTT and
others

6.

Objectives

b. 18 (eighteen) State Polytechnics

To strengthen the contribution of the polytechnic graduate in five priority sectors:
(i) Agribusiness; (ii) Manufacture; (iii) Infrastructure; (iv) Mining; and (v) Tourism.
7.

Scope of Projects
a.

Increased Quality and Relevance of Polytechnic System;

b.

Increased and more equitable access to polytechnic education;

c.

Increased private sector involvement in improving polytechnic graduate competitiveness;

d.

Strengthened governance and management of polytechnic education.

- 49 -

GB-11-1-015-0-1
8.

Activities
Activities
1)

Equipment Procurement

2)

Consulting Services

3)

Capacity Development

4)

Studies and Workshop

5)

Social Marketing and
Advocacy

Implementation
Locations
Jakarta

6)

Project Management

1)

Equipment Procurement

1)

Lampung

2)

Capacity Development

2)

Payakumbuh

3)

Program and Teaching
Learning Materials

4)

National Skills Fund

3)

Bandung

5)

Project Management

4)

Jember

5)

Bandung

6)

Kupang

7)

Banjarmasin

8)

Samarinda

9)

National Skills Fund

Project Implementation Units

Manado

Directorate General of Higher
Education, Ministry of Education
and Culture

1)

Politeknik Negeri Lampung
(Center)

2)

Politeknik Pertanian
Payakumbuh (sister)

3)

Politeknik Manufaktur Negeri
Bandung (center)

4)

Politeknik Negeri Jember (sister)

5)

Politeknik Negeri Bandung
(center)

6)

Politeknik Negeri Kupang
(sister)

7)

Politeknik Negeri Banjarmasin
(center)

8)

Politeknik Negeri Samarinda
(sister)

9)

Politeknik Negeri Manado
(center)

10) Makassar

10) Politeknik Negeri Ujung
Pandang (sister)

1)

Denpasar

11) Politeknik Negeri Bali (center)

2)

Padang

12) Politeknik Negeri Padang (sister)

To be selected
from others state
polytechnics
based on
competitive
funding

- 50 -

6 (six) State Polytechnics

GB-11-1-015-0-1
9.

Funding Sources
Funding (US $ 000)

Implementing Agency

Loan

a. Directorate General of
Higher Education,
Ministry of Education
and Culture

Grant

Local

Total

75.000

18.750

93.750

75.000

18.750

93.750

Source
ADB

b. 18 (eighteen) State
Polytechnics
Total
10. Disbursement Plan
Disbursement Plan (US $ 000)
1

2

st

8,362.2

nd

37,111.2

3rd

4th

28,317.7

19,958.90

Total

5th

93.750

11. Funding Allocations
Detail of Activities

Categories (US $ 000)
Services

Constructions

Equipment

Goods

Trainings

Others

30,750

Consultant Services

2,200

Teaching Materials

900

Program Development

300

Capacity Development

6,500

Studies and Workshop

1,400

National Skills Fund

35,750

Social Marketing and
Advocacy

550

Project Management

5,700

Contingencies

5,190

Interest

3,600

Tax and Duties
Total

910
2,200

31,650

12. Project References :
BB 2011-2014 ID: BB-1114-R0-064-0

- 51 -

6,500

53,400

Ministry of Transportation
(Kementerian Perhubungan)

Directorate General of Land Transportation
(Direktorat Jenderal Perhubungan Darat)

- 53 -

GB-11-1-016-0-1
1.

Project Title

: Intelligent Traffic Transport System in Jabodetabek

2.

Executing Agency

: Ministry of Transportation

3.

Implementing Agency : Directorate General of Land Transportation, Ministry of
Transportation

4.

Duration

: 48 months

5.

Location

: Jakarta, Bogor, Depok, Tangerang, Bekasi

6.

Objectives

7.

8.

a.

To develop the standardization of Intelligent Transport System (ITS) in Indonesia;

b.

To revise basic design of Area Traffic Control System (ATCS) Jakarta;

c.

To develop basic design of ITS in Jakarta, Bogor, Depok, Tangerang, Bekasi (Jabodetabek)
area;

d.

To implement the ITS by the construction of the system in Jabodetabek area;

e.

To transfer the technology and know‐how in traffic engineering and management to the
central and local government.

Scope of Projects
a.

Developing the standardization of ITS in Indonesia;

b.

Formulating basic design of ITS Jabodetabek;

c.

Building and installation of new ATCS center in Jakarta;

d.

Supporting operation and maintaining system;

e.

Supervision.

Activities
Implementation
Locations

Activities
Development, study, and training

9.

Jakarta, Bogor, Depok,
Tangerang, Bekasi

Project Implementation
Units
Directorate General of
Land Transportation,
Ministry of
Transportation

Funding Source
Implementing Agency
Directorate General of
Land Transportation,
Ministry of
Transportation
Total

Funding (US $ 000)
Loan

Grant

50,000

-

50,000

- 55 -

Local

Total

5,000

55,000

5,000

55,000

Source
EDCF
(Korea)

GB-11-1-016-0-1
10. Disbursement Plan
Disbursement Plan (US $ 000)
1

2

st

10,000

3rd

4th

20,000

5,000

nd

20,000

5th

Total
55,000

11. Funding Allocations
Activities
a. Development and
study

Categories (US $ 000)
Services

Constructions

Trainings

45,000

b. Training
Total

Goods

10,000
45,000

10,000

12. Project References
BB 2011 - 2014 ID: BB-1114-R0-067-0

- 56 -

Others

Directorate General of Sea Transportation
(Direktorat Jenderal Perhubungan Laut)

- 57 -

GB-11-1-017-0-1
1.

Project Title

: Improvement and Development of Indonesia Aids to Navigation

2.

Executing Agency

: Ministry of Transportation

3.

Implementing Agency : Directorate General for Sea Transportation, Ministry of
Transportation

4.

Duration

: 36 months

5.

Location

: Nationwide

6.

Objectives

7.

a.

To improve reliability of Navigational Aids Services that supports marine safety
throughout Indonesian waters;

b.

To meet international and national requirement on marine safety along Indonesian sea
lanes;

c.

To increase regional access throughout the archipelago in order to support passenger and
cargo flow using marine transportations that lead to the regional economic development
of Indonesia.

Scope of Projects
a.

8.

Capacity building in technical Aids to Navigation (AtN) and management services;

b.

Procurement of AtN equipment;

c.

Construction of AtN towers.

Activities
Implementation
Locations

Activities

9.

a.

Management and Consulting
Service

b.

Procurement of AtN equipment

c.

Training Program

Nationwide

Project Implementation
Units
Directorate General for
Sea Transportation,
Ministry of
Transportation

Funding Source
Implementing Agency
Directorate General
for Sea
Transportation,
Ministry of
Transportation
Total

Funding (US $ 000)
Loan

Grant

Local
-

78,000

78,000

- 59 -

Total

7,800

85,800

7,800

85,800

Source
EDCF
(Korea)

GB-11-1-017-0-1
10. Disbursement Plan
Disbursement Plan (US $ 000)
1

2

st

3rd

nd

35,750

35,750

4th

Total

5th

85,800

14,300

11. Funding Allocations
Activities
a.

Management and
Consulting Services

b.

Procurement of AtN
equipment

c.

Training Program

d.

Miscellaneous
Total

Categories (US $ 000)
Services

Constructions

Goods

Trainings

Others

1,850
76,727.6

1,050
1,850

76,727.6

12. Project References
BB 2011 - 2014 ID: BB-1114-R0-068-0

- 60 -

1,050

6,172.4
6,172.4

Directorate General of Railways
(Direktorat Jenderal Perkeretaapian)

- 61 -

GB-11-1-018-0-1
1.

Project Title

: Procurement of Diesel Electric Locomotives

2.

Executing Agency

: Ministry of Transportation

3.

Implementing Agency : Directorate General of Railways, Ministry of Transportation

4.

Duration

5.

Location

6.

Objectives

48 months
: Banten, DKI Jakarta, West Java, Central Java, DI Yogyakarta, and East
Java

To fulfill the demand of diesel electric locomotives for passengers and goods transportation by
railway in Java island.
7.

Scope of Projects
Procurement of 30 units of diesel electric locomotives of DC/DC type (BB-202, CC-201, and CC203) and the latest AC/DC type (CC-204 and CC-202) for transportation of passengers