Format Penilaian Refrigeration LKS 2017

Skill name
Refrigeration and Air Conditioning
Criteria

Mark

A

Component Fabrication

12.00

12.000

B

Component & System Installation

20.00

20.000


C

Electrical Installation

12.00

12.000

D

Commissioning & Adjustment

24.00

24.000

E

Mechanical Fault Finding & Repair


10.00

10.000

F

Refrigerant Recovery & Emission control

13.00

13.000

G

Work practices and Safety

9.00

9.000


100.00

Total

Sub
Criteria
ID
A1

WSSS
Section

Sub - Criteria
Name or Description
Module A: Copper Fabrication

Aspect
No


Aspect
Type
O = Obj
S = Sub

1

O

3

4

O

O

O

Aspect - Description


Fabricated headers has inlet and outlets pipes arrangesd as per specifications at 90 degress to headers

0
1st side

Fabricated headders are squared and lies flat on the tables

A1

Fabricated headders arranges as per specifications at 90 degrees to 1/2" soft drawn copper tubes

Overall width D1 is as per specifications

1st Side

2nd Side

5


O

Overall width D2 is as per specifications

1st Side

2nd Side

6

O

100.000
For Objective Assessment Only

2nd side

2

Mark


Overall width D3 is as per specifications

1st Side

2nd Side

Add - (Extra Aspect Information)

Max
Mark

0 - 1 degree

0.40

1 - 3 degree

0.20


>3 degree

0.00

0 - 1 degree

0.40

1 - 3 degree

0.20

>3 degree

0.00

0 - 1 mm

0.80


1 - 3 mm

0.40

>3 mm r

0.00

0 - 1 degree

0.80

1 - 3 degree

0.40

>3 degree

0.00


0 - 1 mm refer drawing

0.40

1 - 3 mm refer drawing

0.20

>3 mm refer drawing

0.00

0 - 1 mm refer drawing

0.40

1 - 3 mm refer drawing

0.20


>3 mm refer drawing

0.00

0 - 1 mm refer drawing

0.40

1 - 3 mm refer drawing

0.20

>3 mm refer drawing

0.00

0 - 1 mm refer drawing

0.40

1 - 3 mm refer drawing

0.20

>3 mm refer drawing

0.00

0 - 1 mm refer drawing

0.40

1 - 3 mm refer drawing

0.20

>3 mm refer drawing

0.00

0 - 1 mm refer drawing

0.40

1 - 3 mm refer drawing

0.20

>3 mm refer drawing

0.00

7

O

Overall width D4 is as per specifications

1st Side

2nd Side

8

O

Overall width D5 is as per specifications

1st Side

2nd Side

3rd Side

4st Side

0 - 1 mm refer drawing

0.40

1 - 3 mm refer drawing

0.20

>3 mm refer drawing

0.00

0 - 1 mm refer drawing

0.40

1 - 3 mm refer drawing

0.20

>3 mm refer drawing

0.00

0 - 1 mm refer drawing

0.20

1 - 3 mm refer drawing

0.10

>3 mm refer drawing

0.00

0 - 1 mm refer drawing

0.20

1 - 3 mm refer drawing

0.10

>3 mm refer drawing

0.00

0 - 1 mm refer drawing

0.20

1 - 3 mm refer drawing

0.10

>3 mm refer drawing

0.00

0 - 1 mm refer drawing

0.20

1 - 3 mm refer drawing

0.10

>3 mm refer drawing

0.00

Pressure tested to 10 bars +/-

1.50

9

O

Fabricated copper tube is leak tight on first attemp

10

O

Brazed joint B1 is made to acceptable standard

Yes/No

2% solder used

0.40

11

O

Brazed joint B2 is made to acceptable standard

Yes/No

2% solder used

0.40

12

O

Brazed joint B3 is made to acceptable standard

Yes/No

2% solder used

0.40

13

O

Brazed joint B4 is made to acceptable standard

Yes/No

2% solder used

0.40

14

O

Brazed joint B5 is made to acceptable standard

Yes/No

2% solder used

0.40

15

O

Nitrogen was used while brazing a pipework

16

O

The competitor prevented moisture contamination inside the pipe during the assembly process.

Yes

17

O

The bare coil is fabricated according to the drawing and specification.

Yes

18

O

No extra material used due to mistake during the process

Yes

0.50
LIVE MARKING

0.50
0.70

LIVE MARKING

0.40
12.00

Sub
Criteria
ID
B1

B2

B3

B4

B6

WSSSS
section

Sub - Criteria
Name or Description
Module B - Major Components

Module B - Refrigerant Controls

Module B - Low Presure Vapor Lines

Module B - High Pressure Liquid Line

Module B - High Pressure Discharge Line

For Objective Assessment Only

Aspect
Type
Aspect no
O = Obj
S = Sub

Aspect - Description

Requirement
or Nominal
Size

Add - (Extra Aspect Information)

Max
Mark

19

O

Electrical switchboard installed in specified location and securely fixed to wall

0.4

20

O

Condensing unit installed in specified location and securely fixed to cradle

0.4

21

O

Tube in tube heat exchanger installed in specified location and securely fixed to wall

0.4

22

O

Glycol tank is installed as speciffied

0.4

23

O

Fabricated copper coil installed in ice ring as specified

0.2

24

O

All pipework is installed within boundaries of supplied cradle

0.4

25

O

TXV installed in correct location in system, with correct flow and as per manufacturer instruction.

0.50

26

O

Sigh glass & filter dryer installed in correct location in system with correct flow direction

Yes

0.50

27

O

Dual pressure control pipes installed as per specification

Yes

0.50

28

O

Pressure control is leveled and securely mounted to wall

Yes

0.30

29

O

All pipe installed in vertical and horizontal planes and the pipe work is vertically and horizontally straight.

Yes

0.30

30

O

All bends of appropriate radius with no kinks

Yes

0.10

31

O

Suction line is securely fastened using appropriate method

Yes

0.30

32

O

Installed pipe work does not rub on any components when operating (fan blades, penetration, etc)

Yes

0.20

33

O

Nitrogen was used while brazing a pipework

34

O

Brazed joint 1 is made to acceptable standard

0.40

35

O

Suction, low pressure liquid and low pressure lines are set out so that these pipes don't cross each other.

0.20

36

O

All Suction line is neatly insulated the entire length of the installation

37

0

Single gauge installed as specified and standard

38

O

All pipe installed in vertical and horizontal planes and the pipe work is vertically and horizontally straight.

39

O

All bends of appropriate radius with no kinks

0.10

40

O

Liquid line is securely fastened using appropriate method

0.30

41

O

Installed pipe work does not rub on any components when operating (fan blades, penetration, etc)

42

O

Nitrogen was used while brazing a pipework

43

O

Brazed joint 2 is made to acceptable standard

0.40

44

0

Single gauge installed as specified and standard

0.20

45

O

All pipe installed in vertical and horizontal planes and the pipe work is vertically and horizontally straight.

46

O

All bends of appropriate radius with no kinks

0.10

47

O

High Pressure line is securely fastened using appropriate method

0.30

48

O

Installed pipe work does not rub on any components when operating (fan blades, penetration, etc)

49

O

Nitrogen was used while brazing a pipework

50

O

Brazed joint 3 is made to acceptable standard

51

O

Ball valve installed as specified and standard

LIVE MARKING

Yes

0.20

0.20
0.20

Yes

0.30

Yes

0.20
LIVE MARKING

Yes

0.20

0.30

Yes

0.20
LIVE MARKING

0.20
0.40

Yes
Yes

0.20

B6

Module B - Tube in Tube Heat Exchanger

B7

Module B - Pressure Test

B8

Module B - Evacuation

52

O

Heat Exchanger is piped as per diagram

0.50

53

O

Brazed joint 4 on refrigerant side of heat exchanger is acceptable

0.40

54

O

Glycol pipework installed as per diagram

0.40

55

O

All glycol pipework lines are insulated

0.20

56

O

Glycol pipework has no kinks on copper and plastic tubing

0.10

57

O

All pipe work does not rub on any components when operating (fan blades, penetration, etc)

0.10

58

O

All pipe installed in vertical and horizontal planes.

0.20

59

O

Glycol line is securely fastened using appropriate method

0.10

60

O

Brazed joint 5 on glycol side heat exchanger is acceptable

0.40

61

O

Starting presure of all attempts meet required standards

0.50

62

O

The appropriate valves were opened to ensure pressure testing of entire system

0.40

63

O

Gauge were correctly fitted to the system

0.20

64

O

Nitrogen was safely added to the system to the desired test pressure

0.40

65

O

System was leak tested while under pressure

0.20

66

O

No leaks were detected on FIRST pressure attempt

2.00

67

O

System held pressure for complete standing time after any leaks repaired

0.50

68

O

Nitrogen was released from system at completion of pressure test.

0.20

69

O

The service manifold gauge lines were removed with minimal refrigerant loss

70

O

Vacuum level (value) of all atempts meet required standards

71

O

The appropriate valve were opened to ensure evacuation of the entire system

Yes/No

0.20

72

O

Vacuum gauge installed so it can be isolated from vacuum pump and still measure system

Yes/No

0.20

73

O

The vacuum held when isolated from the vacuum pump for 10 minutes after FIRST attempt

74

O

The vacuum held when isolated from the vacuum pump for 10 minutes after FINAL attempt

Yes

0.30

0.50

2.00
Yes/No

0.50
20.00

Sub
Criteria
ID
C1

WSSS
section

Sub - Criteria
Name or Description
Module B - Connect the Electrical Circuit

Aspect
No

Aspect
Type
Aspect - Description
O = Obj
S = Sub

For Objective Assessment Only
Requirement
or Nominal
Size

Add - (Extra Aspect Information)

Max
Mark

75

O

All wiring installed as per supplied drawing

Yes/No

0.50

76

O

Supply voltage is wired correctly on supplied plug

Yes/No

0.50

77

O

220V supply wired to correct terminals in switchboard, and correctly terminated

Yes/No

0.50

78

O

Condensing unit wired to correct terminal in switchboard, and correctly terminated

Yes/No

0.50

79

O

Pressure control wired to correct terminal in switchboard, and correctly terminated

Yes/No

0.50

80

O

Glycol pump wired to correct terminal in switchboard, and correctly terminated

Yes/No

0.50

81

O

All cables saddled (fixed) and secured separate to piping

Yes/No

0.80

82

O

Installed cables not to be crush by piping or other components

Yes/No

0.50

83

O

Installed cables and wires installed as per test project for adequate protection

Yes/No

0.50

84

O

All cables and conduit/wire ways is installed within boudaries of the supplied cradle

Yes/No

0.60

C2

Module B - Connect the Electronic Controls

C3

Module B - Electrical Testing

85

O

Temperature probe is wired to the correct terminals in switchboard, and terminated correctly

86

O

Temperature probe is installed in conduit/cable trunking correctly

Yes/No

0.30

87

O

Conduit/cable trunking is verticaly and horizontaly leveled and securely fastened

Yes/No

0.30

88

O

Before turning the power on: the Earth circuit was correctly tested for continuity

Yes/No

0.50

89

O

Before turning the power on: the Neutral circuit was correctly tested for continuity

Yes/No

0.50

90

O

Installation tested for earth continuity to power supply

91

O

Installation tested for earth continuity to condensing unit proir to energising

Yes/No

0.50

92

O

Installation tested for earth leakage proir energising

Yes/No

0.50

93

O

Installation tested for short between active and neutral prior energising

Yes/No

0.50

94

O

No wiring fault found on circuit testing

Yes/No

0.50

95

O

Circuit energised safely the first time without blowing fuses/circuit breaker/etc

Yes/No

1.00

96

O

circuit operated safely and correctly the first time without wiring modifications

Yes/No

0.50

97

O

Circuit operated safely and correctly after any necessary modifications

Yes/No

0.50

0.50

0.50

12.00

Sub
Criteria
ID
D1

D2

D3

WSSS
section

Sub - Criteria
Name or Description
Module B - Charge with Refrigerant Primary Circuit

Module B - Charge with Refrigerant Secondary Circuit

Module B - Commissioning report

Aspect
No

Aspect
Type
Aspect - Description
O = Obj
S = Sub

For Objective Assessment Only
Requirement
or Nominal Add - (Extra Aspect Information)
Size

Max
Mark

98

O

The correct valves were opened prior to operation

99

O

Liquid refrigeration was added to the liquid line only (not suction)

100

O

The correct refrigerant charge weighed into the system and recorded, using an acceptable method

101

O

Amount of refrigerant added is within acceptable guidelines

Yes

0.80

102

O

Electronic leak check was made during charging of refrigerant

Yes

1.00

103

O

The gauge were removed from the system with no avoidable loss of refrigerant

0.80

104

O

Water added to the system was measured to ensure 60% water by volume and a 40% glycol by volume

1.00

105

O

Glycol pump circulated prior to any refrigeration being energised

0.50

106

O

Commissioning report - Ambient temperature is recorded correctly

0.40

107

O

Commissioning report - Refrigerant type is recorded correctly

Yes

0.40

108

O

Commissioning report - Mass of refrigerant is recorded correctly

Yes

0.40

109

O

Commissioning report - Suction pressure is recorded correctly

Yes

0.40

110

O

Commissioning report - Discharge pressure is recorded correctly

Yes

0.40

111

O

Commissioning report - Condenser subcooling measured and recorded correctly

Yes

0.40

112

O

Commissioning report - Total system superheat measured and recorded correctly

Yes

0.40

113

O

Commissioning report - LP control cut in set and cut out are set and recorded correctly

Yes

0.60

114

O

Commissioning report - HP cut out is set and recorded correctly

Yes

0.60

115

O

Commissioning report - Capacity regulator is set and recorded correctly

Yes

0.50

116

O

Commissioning report - Glycol supply and return temperature to and from ice rink recorded correctly

0.40

117

O

Commissioning report - Glycol pump operating current measured and recorded correctly

0.40

118

O

Commissioning report - Condensing unit operating current measured and recorded correctly

0.40
no leakage

1.00
1.00

Yes

0.40

D4

Module B - Commissioning; Complete Installation

D5

Module C - Commissioning Report

119

O

Project completed requiring no additional materilas

120

O

Covers installed securely on all equipment

Yes

0.30

121

O

Correct refrigerant type was recorded

Yes

0.30

122

O

No burn marks and no damage on any equipment from installation

0.70

123

O

System left operation at completion of module

0.50

124

O

After minimum 12hrs run time there is NO water present above the fabricated copper tubing submerged in the
ice ring

1.00

125

O

The control was correctly programmed as per test project specifications

0.50

126

O

Commissioning Report - Ambient temperature measured and recorded correctly.

0.30

127

O

Commissioning Report - return air temperature dry bulb/wet bulb measured, recorded and plotted correctly

Yes/No

1.00

128

O

Commissioning Report - supply air temperature dry bulb/wet bulb measured, recorded and plotted correctly

Yes/No

1.00

129

O

Commissioning Report - Indoor fan speed and mode of operation selected and recorded correctly

Yes/No

0.30

130

O

Commissioning report - Refrigerant type is recorded correctly

Yes/No

0.40

131

O

Commissioning report - Suction pressure is recorded correctly

Yes/No

0.50

132

O

Commissioning report - Total system superheat measured and recorded correctly

Yes/No

0.50

133

O

Commissioning report - Condensing unit operating current measured and recorded correctly

Yes/No

0.50

134

O

Commissioning report - Indoor fan operating current measured and recorded correctly

Yes/No

0.50

135

O

Supply and return air conditions were joined to indicate cooling process

Yes/No

0.50

0.30

O
D6

Module C - Commissioning - Complete Installation

136

O

Project completed requiring no additional materilas

Yes/No

0.50

137

O

Covers installed securely on all equipment

Yes/No

0.50

138

O

No burn marks and no damage on any equipment from installation

Yes/No

0.70

139

O

Installation not damaged in any ways

Yes/No

0.50

140

O

System left in correct operation

Yes/No

0.50
24.00

Sub
Criteria
ID
E1

WSSS
section

Sub - Criteria
Name or Description
ModuleC - Mechanical Fault Finding

For Objective Assessment Only

Aspect
No

Aspect
Type
O = Obj
S = Sub

141

O

The unit was tested for short circuit, insulation resistance and earth continuity prior to energising

1.00

142

O

The fault was correctly identified, repaired, recorded and reclaim started in under 30 minutes

3.00

143

O

The fault was correctly identified, repaired, recorded and reclaim started in under 60 minutes

2.50

144

O

The fault was correctly identified, repaired, recorded and reclaim started in under 90 minutes

2.00

145

O

The fault was correctly identified, repaired, recorded and reclaim started in under 120 minutes

1.50

Aspect - Description

Requirement
or Nominal
Size

Add - (Extra Aspect Information)

Max
Mark

10.00

Sub
Criteria
ID

Sub - Criteria

WSSS
section

F1

Name or Description
Module C - Reclaim Refrigerant

F2

Module C - Evacuation

F3

Module C - Charge with Refrigerant

Asepct
No

Aspect
Type
Aspect - Description
O = Obj
S = Sub

For Objective Assessment Only
Requirement
or Nominal Add - (Extra Aspect Information)
Size

Max
Mark

146

O

Power supply to air conditioner was isolated before refrigerant recovery started

0.60

147

O

Service manifold gauge lines were fitted to the system in the correct way with minimal loss of refrigerant

0.50

148

O

Moisture contamination was prevented without loss of refrigerant

0.50

149

O

The correct refrigerant cylinder was selected for the recovery of refrigerant

0.40

150

O

Refrigerant cylinder weighed and recorded before recovery started

1.00

151

O

Refrigerant recovery lines set up was correct first time

1.00

152

O

The full refrigerant charge was removed from the system using recovery machine

1.00

153

O

Electronic leak check was made during recovery of refrigerant

1.00

154

O

Syetem pressure were at atmospheric pressure or below after recovery was completed

1.00

155

O

All service caps repalced on the recovery unit and recovery cylinder

0.50

156

O

The quantity of refrigernat recovered from the system was recorded

0.50

157

O

First vacuum attemp meets required standards

1.00

158

O

The vacuum held when isolated from vacuum pump for 10 minutes after any attempt

1.50

159

O

The correct refrigerant charge weighed into the system and recorded, using an accetable method

1.00

160

O

Amount of refrigerant added is within accetable guidelines

1.00

161

O

The gauges were removed from the system with the minimals loss of refrigerant.

0.50
13.00

Sub
Criteria
ID
G1

G2

G3

WSSS
section

Sub - Criteria
Name or Description
Module A - Work Practices and safety

Module B - Work Practices and safety

Module C - Work Practices and safety

Aspect
No

Aspect
Type
Aspect - Description
O = Obj
S = Sub

For Objective Assessment Only
Requirement
or Nominal Add - (Extra Aspect Information)
Size

Max
Mark

162

O

Protective gloves were worn at all times when exposed to heat sources

0.50

163

O

Protective eye wear was worn at all times while brazing

1.00

164

O

The competitors always used the correct tools and safe work practices for every actvity

0.50

165

O

The competitors brazing torches and regulators are left at atmospheric prssure on completion of modules

1.00

166

O

Protective gloves were worn at all times when exposed to heat sources and cut hazards

0.50

167

O

Protective eye wear was worn at all times while brazing, drilling, handling refrigerant, glycol and nitrogen

1.00

168

O

The competitors always used the correct tools and safe work practices for every actvity

0.50

169

O

The competitors brazing torches and regulators are left at atmospheric prssure on completion of modules

1.00

170

O

Protective gloves were worn at all times when exposed to heat sources and cut hazards

0.50

171

O

Protective eye wear was worn at all times while brazing, drilling, handling refrigerant and nitrogen

1.00

172

O

The competitors always used the correct tools and safe work practices for every actvity

0.50

173

O

The competitors brazing torches and regulators are left at atmospheric prssure on completion of modules

1.00

Skill name
Refrigeration and Air Conditioning
Criteria
Marks
Section

Criterion

Modules

Objective

Total

Section

Criterion

A

B

A

Component Fabrication

12

12

A

Component Fabrication

B

Component & System Installation

20

20

B

Component & System Installation

20

C

Electrical Installation

12

12

C

Electrical Installation

12

D

Commissioning & Adjustment

24

24

D

Commissioning & Adjustment

15

E

Mechanical Fault Finding & Repair

10

10

E

Mechanical Fault Finding & Repair

F

Electrical Fault Finding & Repair

0

0

F

Electrical Fault Finding & Repair

G

Refrigerant Recovery & Emission
control

13

13

G

Refrigerant Recovery & Emission
control

H

Work practices and Safety

9

9

H

Work practices and Safety

3

3

100

100

Total

15

55

Total

12

5

Modules
C

Total
12
20

0

12

9

24

10

10
0

8

13

3

9

30

100