LPSE Kabupaten Labuan Batu Selatan PAKET 5 (II)
DAFTAR KOREKSI ARITM ATIK
NO. PAKET
: 5
KEGIATAN
: LANJUTAN PENGASPALAN JALAN DARI DUSUN BANDAR PALAS M ENUJU DUSUN SIDONOK DESA UJUNG GADING
KEC. SEI KANAN
HPS
:
Rp
258.119.000
URAIAN
CV. DW ITAM A M ULIA
CV. M ULIA RAYA
CV. PUTRA GAM AK
HARGA TERKOREKSI
257.603.156,62
255.041.067,04
256.926.826,86
PEMBULATAN HARGA TERKOREKSI
257.603.000,00
255.041.000,00
256.926.000,00
HARGA PENAWARAN
257.603.000,00
255.041.000,00
256.926.000,00
PERSENTASE
RANKING
KETERANGAN
99,80%
3
98,81%
1
99,54%
2
NO. PAKET
: 5
KEGIATAN
: LANJUTAN PENGASPALAN JALAN DARI DUSUN BANDAR PALAS M ENUJU DUSUN SIDONOK DESA UJUNG GADING
KEC. SEI KANAN
HPS
:
Rp
258.119.000
URAIAN
CV. DW ITAM A M ULIA
CV. M ULIA RAYA
CV. PUTRA GAM AK
HARGA TERKOREKSI
257.603.156,62
255.041.067,04
256.926.826,86
PEMBULATAN HARGA TERKOREKSI
257.603.000,00
255.041.000,00
256.926.000,00
HARGA PENAWARAN
257.603.000,00
255.041.000,00
256.926.000,00
PERSENTASE
RANKING
KETERANGAN
99,80%
3
98,81%
1
99,54%
2