Slide TSP308 TSP 308 002 Metoda dan Peralatan Konstruksi

Lecture 2

PLANNING & EARTHMOVING
MATERIALS AND CONSTRUCTION
TSP-308 MPK

Ferdinand Fassa

OUTLINE










PREPARATION WORK
INTRODUCTION TO EARTHMOVING

EARTHMOVING MATERIALS
GRAPHICAL PRESENTATION OF EARTHWORK
SOIL VOLUME-CHANGE CHARACTERISTICS
EARTHWORK QUANTITIES
MASS DIAGRAM
PROBLEMS
2

PREPARATION WORK (1)
Objectives


Prepare the site ready for construction activities

Scope of Works










(Surface &) Sub-surface Exploration
Site Clearing
(Unhook utilities)
(Demolition)
Staking Out
Grading
Earth work

3

PREPARATION WORK (2)
Surface & Subsurface Exploration


Visual inspection







identification of major obstacle, location of utilities, etc.)
(sometimes reliance to as built drawing just is not
adequate)
Rough measurement

Soil test


Hand boring, test holes

4

PREPARATION WORK (3)
Site Clearing



Unhook utility lines (electricity, gas, water, telephone)



Demolition of Existing Buildings


Hand (manual) dismantling



Tractor w/ grapple



Dozing




Explosive



Wrecking balls



Remove Tress



Remove shrubs and vegetation
5

PREPARATION WORK (4)
Surveying and Staking Out

6


Temporary Post

7

Board (fixed marks)

8

Corner Excavation

9

Theodolite Positioning

10

Elevation Setting

11


Elevation Setting

12

Depth Control

13

PREPARATION WORK (5)
Digital Geodetic Surveying, Mapping, and Planning:
mapping a vast area

Geo-Satellite

Coordinate Geometry
(COGO)

Digital Surveying
with GPS


14

INTRODUCTION TO EARTHMOVING (1)
Earthmoving process is the process of moving soil or rock from one
location to another and processing it so that it meets construction
requirements of location, elevation, density and moisture content.
Activities involved in this process include:
 Excavating
 Loading
 Hauling
 Placing (dumping and spreading)
 Compacting
 Grading and finishing

15

INTRODUCTION TO EARTHMOVING (2)


16


GRAPHICAL PRESENTATION OF EARTHWORK (1)
 Plan View
 Profile View (Potongan Memanjang)
 Cross Section View (Potongan Melintang)

17

GRAPHICAL PRESENTATION OF EARTHWORK (2)

18

SOIL VOLUME-CHANGE CHARACTERISTICS (1)
Three Principal Soil Conditions:
 Bank: Called “In –Place” Material in its natural state before disturbance unit
volume  Bank Cubic Yard (BCY) or Bank Cubic Meter (BCM)
 Loose: Material that has been excavated or loaded  Loose Cubic Yard
(LCY) or Loose Cubic Meter (LCM)
 Compacted: Material after compaction  Compacted Cubic Yard (CCY) or
Compacted Cubic Meter (CCM)

Swell: Soil increase in volume when it is excavated (soil grains loose an air fills
the void spaces created)
Shrinkage
Load Factor is a conversion factor to simplify the conversion of loose volume to
bank volume
19

Soil’s Volumetric Changes

BANK

SHRINK
SWELL

Swell (%) =

bank unit weight
( loose
- 1)
unit weight


x 100%

LOOSE

Swell Factor (SwF) =

COMPACTED

loose dry unit weight
bank dry unit weight

Shrinkage Factor (ShF) =

Shrinkage (%) =

compacted dry unit weight
bank dry unit weight

(compacted dry unit weight) – (bank unit weight)
compacted unit weight

Load Factor (LF) = Swell Factor (SwF)

x 100%



Example

22



Example

23

24

Earth Work Calculation



Excavate/dig or (back) fill actual ground level to
desired Level
Average End Method (ditch/trench excavation)




Vol. = (A1 + A2) / 2 x L

Large Area



Ave. Depth = [S depth x weight] / S weight
Volume
= Ave. Depth x Area

25

Ditch / Trench Excavations


Average End Method
Vol. = (A1 + A2)/2 x L
A2

A1
L

26

Land Excavation /Filling (grid system)

27

Find the volume of excavation required for the area shown in
figure below. The figure at each grid inter-section represents the
depth of cut at that location
AVE. DEPTH = [1xCP + 2xBP + 4xIP]/TP
VOL. = L x L x AVE. DEPTH

28

29

Problem:

30