Slide TSP308 TSP 308 002 Metoda dan Peralatan Konstruksi
Lecture 2
PLANNING & EARTHMOVING
MATERIALS AND CONSTRUCTION
TSP-308 MPK
Ferdinand Fassa
OUTLINE
PREPARATION WORK
INTRODUCTION TO EARTHMOVING
EARTHMOVING MATERIALS
GRAPHICAL PRESENTATION OF EARTHWORK
SOIL VOLUME-CHANGE CHARACTERISTICS
EARTHWORK QUANTITIES
MASS DIAGRAM
PROBLEMS
2
PREPARATION WORK (1)
Objectives
Prepare the site ready for construction activities
Scope of Works
(Surface &) Sub-surface Exploration
Site Clearing
(Unhook utilities)
(Demolition)
Staking Out
Grading
Earth work
3
PREPARATION WORK (2)
Surface & Subsurface Exploration
Visual inspection
identification of major obstacle, location of utilities, etc.)
(sometimes reliance to as built drawing just is not
adequate)
Rough measurement
Soil test
Hand boring, test holes
4
PREPARATION WORK (3)
Site Clearing
Unhook utility lines (electricity, gas, water, telephone)
Demolition of Existing Buildings
Hand (manual) dismantling
Tractor w/ grapple
Dozing
Explosive
Wrecking balls
Remove Tress
Remove shrubs and vegetation
5
PREPARATION WORK (4)
Surveying and Staking Out
6
Temporary Post
7
Board (fixed marks)
8
Corner Excavation
9
Theodolite Positioning
10
Elevation Setting
11
Elevation Setting
12
Depth Control
13
PREPARATION WORK (5)
Digital Geodetic Surveying, Mapping, and Planning:
mapping a vast area
Geo-Satellite
Coordinate Geometry
(COGO)
Digital Surveying
with GPS
14
INTRODUCTION TO EARTHMOVING (1)
Earthmoving process is the process of moving soil or rock from one
location to another and processing it so that it meets construction
requirements of location, elevation, density and moisture content.
Activities involved in this process include:
Excavating
Loading
Hauling
Placing (dumping and spreading)
Compacting
Grading and finishing
15
INTRODUCTION TO EARTHMOVING (2)
16
GRAPHICAL PRESENTATION OF EARTHWORK (1)
Plan View
Profile View (Potongan Memanjang)
Cross Section View (Potongan Melintang)
17
GRAPHICAL PRESENTATION OF EARTHWORK (2)
18
SOIL VOLUME-CHANGE CHARACTERISTICS (1)
Three Principal Soil Conditions:
Bank: Called “In –Place” Material in its natural state before disturbance unit
volume Bank Cubic Yard (BCY) or Bank Cubic Meter (BCM)
Loose: Material that has been excavated or loaded Loose Cubic Yard
(LCY) or Loose Cubic Meter (LCM)
Compacted: Material after compaction Compacted Cubic Yard (CCY) or
Compacted Cubic Meter (CCM)
Swell: Soil increase in volume when it is excavated (soil grains loose an air fills
the void spaces created)
Shrinkage
Load Factor is a conversion factor to simplify the conversion of loose volume to
bank volume
19
Soil’s Volumetric Changes
BANK
SHRINK
SWELL
Swell (%) =
bank unit weight
( loose
- 1)
unit weight
x 100%
LOOSE
Swell Factor (SwF) =
COMPACTED
loose dry unit weight
bank dry unit weight
Shrinkage Factor (ShF) =
Shrinkage (%) =
compacted dry unit weight
bank dry unit weight
(compacted dry unit weight) – (bank unit weight)
compacted unit weight
Load Factor (LF) = Swell Factor (SwF)
x 100%
Example
22
Example
23
24
Earth Work Calculation
Excavate/dig or (back) fill actual ground level to
desired Level
Average End Method (ditch/trench excavation)
Vol. = (A1 + A2) / 2 x L
Large Area
Ave. Depth = [S depth x weight] / S weight
Volume
= Ave. Depth x Area
25
Ditch / Trench Excavations
Average End Method
Vol. = (A1 + A2)/2 x L
A2
A1
L
26
Land Excavation /Filling (grid system)
27
Find the volume of excavation required for the area shown in
figure below. The figure at each grid inter-section represents the
depth of cut at that location
AVE. DEPTH = [1xCP + 2xBP + 4xIP]/TP
VOL. = L x L x AVE. DEPTH
28
29
Problem:
30
PLANNING & EARTHMOVING
MATERIALS AND CONSTRUCTION
TSP-308 MPK
Ferdinand Fassa
OUTLINE
PREPARATION WORK
INTRODUCTION TO EARTHMOVING
EARTHMOVING MATERIALS
GRAPHICAL PRESENTATION OF EARTHWORK
SOIL VOLUME-CHANGE CHARACTERISTICS
EARTHWORK QUANTITIES
MASS DIAGRAM
PROBLEMS
2
PREPARATION WORK (1)
Objectives
Prepare the site ready for construction activities
Scope of Works
(Surface &) Sub-surface Exploration
Site Clearing
(Unhook utilities)
(Demolition)
Staking Out
Grading
Earth work
3
PREPARATION WORK (2)
Surface & Subsurface Exploration
Visual inspection
identification of major obstacle, location of utilities, etc.)
(sometimes reliance to as built drawing just is not
adequate)
Rough measurement
Soil test
Hand boring, test holes
4
PREPARATION WORK (3)
Site Clearing
Unhook utility lines (electricity, gas, water, telephone)
Demolition of Existing Buildings
Hand (manual) dismantling
Tractor w/ grapple
Dozing
Explosive
Wrecking balls
Remove Tress
Remove shrubs and vegetation
5
PREPARATION WORK (4)
Surveying and Staking Out
6
Temporary Post
7
Board (fixed marks)
8
Corner Excavation
9
Theodolite Positioning
10
Elevation Setting
11
Elevation Setting
12
Depth Control
13
PREPARATION WORK (5)
Digital Geodetic Surveying, Mapping, and Planning:
mapping a vast area
Geo-Satellite
Coordinate Geometry
(COGO)
Digital Surveying
with GPS
14
INTRODUCTION TO EARTHMOVING (1)
Earthmoving process is the process of moving soil or rock from one
location to another and processing it so that it meets construction
requirements of location, elevation, density and moisture content.
Activities involved in this process include:
Excavating
Loading
Hauling
Placing (dumping and spreading)
Compacting
Grading and finishing
15
INTRODUCTION TO EARTHMOVING (2)
16
GRAPHICAL PRESENTATION OF EARTHWORK (1)
Plan View
Profile View (Potongan Memanjang)
Cross Section View (Potongan Melintang)
17
GRAPHICAL PRESENTATION OF EARTHWORK (2)
18
SOIL VOLUME-CHANGE CHARACTERISTICS (1)
Three Principal Soil Conditions:
Bank: Called “In –Place” Material in its natural state before disturbance unit
volume Bank Cubic Yard (BCY) or Bank Cubic Meter (BCM)
Loose: Material that has been excavated or loaded Loose Cubic Yard
(LCY) or Loose Cubic Meter (LCM)
Compacted: Material after compaction Compacted Cubic Yard (CCY) or
Compacted Cubic Meter (CCM)
Swell: Soil increase in volume when it is excavated (soil grains loose an air fills
the void spaces created)
Shrinkage
Load Factor is a conversion factor to simplify the conversion of loose volume to
bank volume
19
Soil’s Volumetric Changes
BANK
SHRINK
SWELL
Swell (%) =
bank unit weight
( loose
- 1)
unit weight
x 100%
LOOSE
Swell Factor (SwF) =
COMPACTED
loose dry unit weight
bank dry unit weight
Shrinkage Factor (ShF) =
Shrinkage (%) =
compacted dry unit weight
bank dry unit weight
(compacted dry unit weight) – (bank unit weight)
compacted unit weight
Load Factor (LF) = Swell Factor (SwF)
x 100%
Example
22
Example
23
24
Earth Work Calculation
Excavate/dig or (back) fill actual ground level to
desired Level
Average End Method (ditch/trench excavation)
Vol. = (A1 + A2) / 2 x L
Large Area
Ave. Depth = [S depth x weight] / S weight
Volume
= Ave. Depth x Area
25
Ditch / Trench Excavations
Average End Method
Vol. = (A1 + A2)/2 x L
A2
A1
L
26
Land Excavation /Filling (grid system)
27
Find the volume of excavation required for the area shown in
figure below. The figure at each grid inter-section represents the
depth of cut at that location
AVE. DEPTH = [1xCP + 2xBP + 4xIP]/TP
VOL. = L x L x AVE. DEPTH
28
29
Problem:
30