PENGENDALIAN BIAYA DAN WAKTU DENGAN MENERAPKAN METODE EARNED VALUE ANALYSIS (EVA) MENGGUNAKAN SOFTWARE MICROSOFT PROJECT 2007 (STUDI KASUS: PROYEK PEMBANGUNAN HOTEL BROTHER 2 SOLO BARU, SUKOHARJO)

  

PENGENDALIAN BIAYA DAN WAKTU DENGAN

MENERAPKAN METODE

EARNED VALUE ANALYSIS (EVA)

SOFTWARE MICROSOFT PROJECT 2007

  MENGGUNAKAN

  

(STUDI KASUS: PROYEK PEMBANGUNAN HOTEL

BROTHER 2 SOLO BARU, SUKOHARJO)

JUDUL

CONTROL OF COST AND TIME BY APPLYING EARNED VALUE

  

ANALYSIS (EVA) BY USING MICROSOFT PROJECT 2007

(A CASE STUDY: CONSTRUCTION PROJECT OF BROTHERS 2 HOTEL

SOLO BARU, SUKOHARJO)

  

SKRIPSI

  Disusun Sebagai Salah Satu Syarat Memperoleh Gelar Sarjana Teknik Program Studi Teknik Sipil Fakultas Teknik

  Universitas Sebelas Maret Surakarta

  

Oleh :

ENDAR PANCANINGRUM

NIM. I0113042

PROGRAM STUDI TEKNIK SIPIL FAKULTAS TEKNIK

UNIVERSITAS SEBELAS MARET

SURAKARTA

  

2017

  

HALAMAN PERSETUJUAN

PENGENDALIAN BIAYA DAN WAKTU DENGAN

MENERAPKAN METODE EARNED VALUE ANALYSIS (EVA)

MENGGUNAKAN SOFTWARE MICROSOFT PROJECT 2007

  

(STUDI KASUS: PROYEK PEMBANGUNAN HOTEL

BROTHER 2 SOLO BARU, SUKOHARJO)

CONTROL OF COST AND TIME BY APPLYING EARNED VALUE

ANALYSIS (EVA) BY USING MICROSOFT PROJECT 2007

  

(A CASE STUDY: CONSTRUCTION PROJECT OF BROTHERS 2 HOTEL

SOLO BARU, SUKOHARJO)

SKRIPSI

  Disusun Sebagai Salah Satu Syarat Memperoleh Gelar Sarjana Teknik Program Studi Teknik Sipil Fakultas Teknik

  Universitas Sebelas Maret Surakarta

  

ENDAR PANCANINGRUM

NIM. I0113042

  Telah disetujui untuk dipertahankan dihadapan Tim Penguji Pendadaran Program Studi Teknik Sipil Fakultas Teknik Universitas Sebelas Maret Surakarta

HALAMAN PERSETUJUAN

  Persetujuan : Dosen Pembimbing I, Dosen Pembimbing II, Widi Hartono, S. T., M.T. Ir. Sugiyarto, M.T.

  NIP. 19730729 199903 1 001 NIP. 19551121 198702 1 002

  

HALAMAN PENGESAHAN

PENGENDALIAN BIAYA DAN WAKTU DENGAN MENERAPKAN

METODE EARNED VALUE ANALYSIS (EVA) MENGGUNAKAN

  3. Ir. Koosdaryani Soeryodarundio, M.T.

  NIP. 19681007 199502 1 001

  

HALAMAN PE

NGESAHAN

Wibowo, S.T., D.E.A.

  Disahkan, Tanggal : ........................................ Kepala Program Studi Teknik Sipil Fakultas Teknik UNS

  NIP. 19720224 199702 1 001 ..................................

  4. Setiono, S.T., M. Sc.

  NIP. 19541127 198601 2 001 ..................................

  NIP. 19551121 198702 1 002 ..................................

  

SOFTWARE MICROSOFT PROJECT 2007

(STUDI KASUS: PROYEK PEMBANGUNAN HOTEL BROTHER 2 SOLO

BARU, SUKOHARJO)

  2. Ir. Sugiyarto, M.T.

  NIP. 19730729 199903 1 001 ..................................

  Tim Penguji Nama/NIP Tanda Tangan 1. Widi Hartono, S.T., M.T.

  Hari : Tanggal :

  Telah dipertahankan dihadapan Tim Penguji Pendadaran Program Studi Teknik Sipil Fakultas Teknik Universitas Sebelas Maret Surakarta pada :

  

Oleh :

ENDAR PANCANINGRUM

NIM. I0113042

  

CONTROL OF COST AND TIME BY APPLYING EARNED VALUE

ANALYSIS (EVA) BY USING MICROSOFT PROJECT 2007

(A CASE STUDY: CONSTRUCTION PROJECT OF BROTHERS 2 HOTEL

SOLO BARU, SUKOHARJO)

  

MOTTO

  Bermimpilah, karena Tuhan akan memeluk mimpi-mimpimu.

  Bermimpilah dalam hidup, jangan hidup dalam mimpi.

  ~ Andrea Hirata, Sang Pemimpi ~

  

PERSEMBAHAN

  Puji syukur kepada Allah SWT yang telah menuntun perjalanan kuliah di S1 Teknik Sipil tahun 2013-2017 yang ditandai selesainya skripsi ini. Dengan ini saya mempersembahkan karya ini kepada:

  1. Bapak Sodiri dan Ibu Maryamah yang sangat saya cintai, hormati dan banggakan. Terima kasih atas semua curahan do’a, dukungan dan harapan baik lahir maupun batin.

  Dukungan dan do’a restu kalian berdua sangat berarti bagi perjalanan hidup saya.

  2. Saudara-saudara saya, Mas Rudi, Mas Bekti, Mas Oki, Mbak Tari, dan Mbak Rini serta keponakan saya yang saat ini masih lucu Alifa. Terima kasih atas semua dukungan , do’a dan semangatnya.

  3. Sahabat geng “Ngapak :D”: Ayu yang sekaligus teman seperjuangan skripsi dan Eno si penyihir sholehah yang baik hati. Terimakasih kalian sudah mewarnai hari-hari selama 4 tahun ini. Sahabat banget dikala suka duka, dengan perjalanan manis, pahit, asam dan asin semuanya sama-sama. GOOD

  LUCK GIRLS ! 4.

  Teman-teman Sahabat “Klayar Bukan Wacana”: Alif, DPR, Rheza, Gicung, Adianto, Fai, Naufal Hakim, Naufal Bison, Rama dan Upang. Terima kasih ya sudah banyak tempat yang diwacanakan untuk kita liburan! Terimakasih atas semua bantuannya selama ini dan selalu mengingatkan agar tidak malas serta saling menyemangati.

  5. Teman dari Tim Manajemen Konstruksi: Visa, Suci, Intan, Vinca, Shofie dan Astri, yang tidak lelahnya untuk saling menyemangati dan memberikan informasi tentang dosen-dosen pembimbing serta pemberi saran dari beberapa permasalahan skripsi.

  6. Teman-teman S1 Teknik Sipil Angkatan 2013 yang selalu menemani dari perjuangan awal bersama saat introweek sampai lulus. See You On Top,

  Guys !!! 7.

  Sahabat “Liburan akan Datang”: Bowo, Rara, Naelul, Fitriyan dan terutama Muhammad Yusron Nafi yang selalu memberikan banyak kebahagiaan lahir dan batin, yang selalu menemani pahit manisnya hidup terutama di dunia perkuliahan, yang tidak pernah lelah memberikan motivasi dan selalu menginspirasi untuk terus berbuat kebaikan serta yang tidak bosan mengingatkan untuk selalu menyertai Alloh dalam segala hal. Terimakasih sudah menjadi tempat mencurahkan isi hati, teman penghilang penat dengan jalan-jalannya dan teman untuk berbagi ilmu serta diskusi-diskusi seru nan lucu lainnya. Terimakasih atas dukungan , semangat serta do’a yang selalu kalian curahkan.

  8. Teman-teman KKN Desa Gasang Januari-Februari 2017 yang selalu menyemangati satu sama lain.

  9. Sahabat-sahabat dari “WC X4” yang sampai sekarang yang masih kompak: (Rizka, Soraya, Fitroh dan Hafizha). Terima kasih selalu menyemangati dan memberikan do’a.

  10. Semua pihak yang mendukung dan memberi semangat dalam penyelesaian Skripsi ini.

  

ABSTRAK

  Endar Pancaningrum, Widi Hartono, Sugiyarto, 2017. Pengendalian Biaya dan

  

Waktu dengan Menerapkan Metode Earned Value Analysis (EVA)

Software Microsoft Project 2007. (Studi Kasus: Proyek

  Menggunakan

  Pembangunan Hotel Brothers 2 Solo Baru,, Sukoharjo). Skrispsi. Program Studi Teknik Sipil. Fakultas Teknik. Universitas Sebelas Maret Surakarta. Untuk mencapai keberhasilan pada sebuah proyek, diperlukan adanya manajemen yang baik yaitu dengan adanya fungsi pengendalian yang dapat mempengaruhi hasil akhir suatu proyek serta dapat meminimalisasi penyimpangan yang terjadi selama proyek berlangsung. Tujuan penelitian ini adalah mengetahui hasil EVA dengan menggunakan Microsoft Project 2007, mengetahui skenario percepatan yang mengalami keterlambatan, dan mengetahui besarnya perkiraan biaya akhir proyek dan waktu yang dibutuhkan untuk menyelesaikan proyek. Metode yang digunakan dalam penelitian ini adalah deskriptif kuantitatif. Analisis data menggunakan metode analitis dan deskriptif. EVA adalah metode pengendalian biaya dan waktu proyek yang mampu menunjukkan indeks kinerja biaya dan jadwal pada setiap pelaporan, sehingga proyek dapat dilihat kemajuan per pelaporan. Analisis data menunjukkan bahwa perhitungan konsep nilai hasil untuk bulan Februari-Maret menunjukkan SPI < 1 yang artinya penyelenggaraan proyek terlambat, sementara untuk bulan April nilai SPI =1 yang artinya penyelenggaraan proyek tepat waktu. Nilai CPI > 1 untuk bulan Februari-Maret artinya pengeluaran proyek lebih kecil dari anggaran dan CPI = 1 untuk bulan April artinya sesuai rencana anggaran biaya. Hasil ETC 3 bulan berturut turut (Februari-April) yaitu Rp. 1.085.123.685, Rp. 357.971.843, Rp. -54.262.692. Hasil EAC 3 bulan berturut turut (Februari-April) yaitu Rp. 21.946.845.982, Rp. 21.980.555.782, Rp. 21.981.362.911. Hasil sisa anggaran berturut-turut selama 3 bulan menunjukkan angka positif berarti anggaran proyek lebih kecil dari rencana anggaran biayanya. Kata kunci: Earned Value Analysis (EVA), Microsoft Project 2007, Pengendalian Biaya, Pengendalian Waktu, Hotel Brothers 2 Solo Baru.

  

ABSTRACT

Endar Pancaningrum, Widi Hartono, Sugiyarto, 2017. Control of Cost and Time

by Applying Earned Value Analysis (EVA) by Using Microsoft Project 2007 (A

Case Study: Construction Project of Brothers 2 Hotel Solo Baru, Sukoharjo).

  

Thesis, Civil Engineering. Engineering Faculty. Sebelas Maret University.

Surakarta.

The success on the project, there should be good management to control the

influences of project’s product also minimize deviation on the project. The

objective of the research is to know how extent EVA’s result by using Microsoft

Project 2007, to know the scena rio’s acceleration which is delayed, and to know the estimation cost of project and time needs to finish the project.

  

The research method used in the reseaerch was a quantitative descriptive. The

data analysis was using analitical and descriptive method. EVA is a cost control

and project time method which shows cost and time work index of report, so that

the progress of project could be seen in per reports.

The analysis of data shows that the calculation of value result concept for

February

  • – March showed that SPI was less than 1 (SPI<1), means the project

    was delayed, while in April, SPI was equal to 1 (SPI=1), means the project itself

    was on time. CPI Value was more than 1 (CPI >1) for Februari – March, it

    means the project output was less than the estimation cost and CPI was equal to 1

    on April, means that the output is proper with the estimation cost. The results of

    ETC in 3 months (February
  • – April) were 1,085,123,685 IDR, 357,971,843 IDR, and 54,262,692 IDR. The EAC result in 3 months (February
  • – April) were

    21,946,845,982 IDR, 21,980,555,782 IDR, and 21,981,362,911 IDR. The remain

    cost in three months shows in positive number, means the project cost estimation

    is less than the cost estimation itself.

    Keywords: Earned Value Analysis (EVA), Microsoft Project 2007, Cost Control,

    Time Control Brothers 2 Hotel Solo Baru.

KATA PENGANTAR

  Puji syukur Penulis panjatkan kepada Allah SWT atas berkat dan rahmat-Nya, akhirnya Penulis dapat menyelesaikan skripsi dengan judul “Pengendalian Biaya dan Waktu dengan Menerapkan Metode Earned Value Analysis (EVA)

  Menggunakan Software Microsoft Project 2007 ” tepat pada waktunya. Penelitian ini disusun guna memenuhi salah satu syarat dalam meraih gelar Sarjana Teknik pada Program Studi S1 Teknik Sipil Universitas Sebelas Maret Surakarta.

  Penulis mendapat bantuan dan bimbingan dari berbagai pihak dalam penulisan skripsi ini sehingga semuanya dapat berjalan lancar. Oleh karena itu Penulis mengucapkan terima kasih kepada: 1.

  Bapak Widi Hartono, S.T., M.T., selaku dosen pembimbing 1 yang telah memberikan pengarahan selama penulisan skripsi.

  2. Bapak Ir. Sugiyarto, M.T., selaku dosen pembimbing 2 yang telah memberikan pengarahan selama penulisan skripsi.

  3. Bapak Ir. Antonius Mediyanto, M.T., selaku dosen pembimbing akademik yang telah memberikan bimbingan akademik selama kuliah.

  4. Rekan-rekan mahasiswa Teknik Sipil UNS 2013 yang terus memberikan semangat dan bantuan dalam penulisan skripsi.

  5. Keluarga Penulis yang selalu memberikan dukungan dalam penulisan skripsi.

  6. Semua pihak yang telah membantu terselesainya skripsi ini. Penulis menyadari bahwa skripsi ini masih jauh dari sempurna. Oleh karena itu, Penulis mengharapkan kritik dan saran yang bersifat membangun demi kesempurnaan skripsi ini. Semoga skripsi ini dapat bermanfaat bagi pembaca khususnya mahasiswa Teknik Sipil.

  Surakarta, 3 Agustus 2017 Penulis

  

DAFTAR ISI

  JUDUL ........................................................................................................ i HALAMAN PERSETUJUAN .................................................................... ii HALAMAN PENGESAHAN ..................................................................... iii MOTTO....................................................................................................... iv PERSEMBAHAN ....................................................................................... v ABSTRAK .................................................................................................. vii

  

ABSTRACT .................................................................................................. viii

  KATA PENGANTAR ................................................................................ ix DAFTAR ISI ............................................................................................... x DAFTAR GAMBAR .................................................................................. xiii DAFTAR TABEL ....................................................................................... xv BAB 1 PENDAHULUAN .........................................................................

  1 1.1 Latar Belakang ..........................................................................

  1 1.2 Rumusan Masalah .....................................................................

  3 1.3 Batasan Masalah ........................................................................

  3 1.4 Tujuan Penelitian .......................................................................

  3 1.5 Manfaat Penelitian .....................................................................

  4 BAB 2 LANDASAN TEORI ....................................................................

  5 2.1 Tinjauan Pustaka .......................................................................

  5 2.2 Dasar Teori ................................................................................

  7 2.2.1 Proyek..............................................................................

  7 2.2.2 Perencanaan Proyek ........................................................

  8 2.2.3 Pengendalian Proyek .......................................................

  9 2.2.4 Pengendalian Waktu dan Biaya.......................................

  10 2.2.5 Konsep Nilai Hasil ..........................................................

  10 2.2.5.A Pengertian Konsep Nilai Hasil ...........................

  10 2.2.5.B Indikator-indikator Konsep Nilai Hasil ..............

  10

  2.2.5.C Varians Biaya dan Jadwal Terpadu ....................

  12 2.2.6 Diagram Precedence .......................................................

  13 2.2.7 Microsoft Project 2007....................................................

  14 BAB 3 METODE PENELITIAN .............................................................

  17 3.1 Pendahuluan ..............................................................................

  17 3.2 Pengumpulan Data ....................................................................

  17 3.3 Tahap dan Prosedur Penelitian ..................................................

  18 BAB 4 ANALISA DATA DAN PEMBAHASAN ...................................

  21 4.1 Deskripsi Proyek .......................................................................

  21 4.2 Lokasi dan Data Proyek ............................................................

  22 4.3 Pengolahan Data dengan Microsoft Project 2007 .....................

  23 4.3.1 Membuat Dokumen Proyek Baru ....................................

  23 4.3.2 Menentukan Tanggal Mulai Proyek ................................

  24 4.3.3 Mengolah Tugas atau Nama Pekerjaan ...........................

  25 4.3.4 Membuat Pekerjaan Utama dan Rincian .........................

  26 4.3.5 Mengisi Durasi Pekerjaan ...............................................

  26 4.3.6 Mengatur Hubungan Antar Pekerjaan .............................

  27 4.3.7 Mengelola Sumber Daya dan Jadwal Proyek ..................

  29 4.3.8 Menyusun Rencana Anggaran Proyek ............................

  33 4.3.9 Mengendalikan Pengeluaran Proyek ...............................

  35 4.3.10 Evaluasi Perkembangan dan Pergerakan Proyek ..........

  38 4.4 Analisis Hasil Report Microsoft Project 2007 ..........................

  41

  4.4.1 Laporan Konsep Nilai Hasil dari Microsoft Project 2007 42

  4.4.2 Laporan Project Information dari Microsoft Project 2007 43 4.5 Perkiraan Biaya Akhir dan Penyelesaian Proyek ......................

  45 4.5.1 Analisis Data ...................................................................

  46 4.5.1.AAnalisis Laporan Bulan Februari 2017 ...............

  46 4.5.1.B Analisis Laporan Bulan Maret 2017 ..................

  51 4.5.1.C Analisis Laporan Bulan April 2017 ...................

  55

  BAB 5 KESIMPULAN DAN SARAN .....................................................

  63 5.1 Kesimpulan ................................................................................

  63 5.2 Saran ..........................................................................................

  64 DAFTAR PUSTAKA ................................................................................. xvi LAMPIRAN ................................................................................................ xvii

  DAFTAR GAMBAR

Gambar 2.1 Hubungan Triple Constraint (Iman Soeharto; 1997; 3) ......................... 8Gambar 2.2 Node Diagram Precedence ..................................................................... 13Gambar 3.1 Bagan Alir Tahap-tahap Penelitian ........................................................ 20Gambar 4.1 Membuat Dokumen Proyek Baru ........................................................... 23Gambar 4.2 Menentukan Tanggal Mulai Proyek ....................................................... 24Gambar 4.3 Mengolah Tugas Atau Nama Pekerjaan ................................................. 25Gambar 4.4 Membuat Pekerjaan Utama dan Rincian ................................................ 26Gambar 4.5 Mengisi Durasi Pekerjaan ...................................................................... 27Gambar 4.6 Mengatur Hubungan Antar Pekerjaan .................................................... 28Gambar 4.7 Membuka Lembar Kerja Resource Sheet ............................................... 29Gambar 4.8 Menyusun Daftar Sumber Daya Didalam Tabel Resource Sheet .......... 30Gambar 4.9 Kotak Dialog Task Information.............................................................. 31Gambar 4.10 Pengisian Sumber Daya di Kotak Dialog Task Information ................ 32Gambar 4.11 Tampilan Lembar Kerja Resource Usage ............................................ 32Gambar 4.12 Tampilan Gant Chart dalam Tampilan Biaya (Cost) ........................... 34Gambar 4.13 Tampilan Kotak Dialog Assign Resources ........................................... 35Gambar 4.14 Tampilan dalam Mengendalikan Pengeluaran Biaya Tiap

  Pekerjaan ............................................................................................... 36

Gambar 4.15 Tampilan dalam Mengendalikan Pengeluaran Biaya Tiap

  Pekerjaan Menggunakan Resource Sheet ............................................. 36

Gambar 4.16 Tampilan dalam Mengendalikan Pengeluaran Biaya Tiap

  Pekerjaan Menggunakan Resource Usage ............................................ 37

Gambar 4.17 Tampilan dalam Mengendalikan Pengeluaran Biaya Tiap

  Pekerjaan Menggunakan Resource Form ............................................. 38

Gambar 4.18 Membuat Baseline pada Seluruh Proyek ............................................. 39Gambar 4.19 Memperbarui Start Date dan Finish Date ............................................ 40Gambar 4.20 Mengisikan Nilai Presentase Selesainya Pekerjaan (%

  Complete ) pada Suatu Pekerjaan .......................................................... 41

Gambar 4.21 Tampilan Kotak Dialog Report ............................................................ 42Gambar 4.22 Project Information Report Bulan Februari 2017 ................................ 43Gambar 4.23 Project Information Report Bulan Maret 2017 .................................... 44Gambar 4.24 Project Information Report Bulan April 2017 ..................................... 44

  DAFTAR TABEL

Tabel 4.1 Laporan Konsep Nilai Hasil Selama 3 Bulan Mulai dari Bulan

  Februari-April 2017 ................................................................................... 42

Tabel 4.2 Laporan Perhitungan Konsep Nilai Hasil Selama 3 Bulan Mulai dari Bulan Februari-April 2017 ................................................................. 60Tabel 4.3 Laporan Perkiraan Biaya Proyek Sampai tanggal Pelaporan Selama

  3 Bulan Mulai dari Bulan Februari-April 2017 ......................................... 61

DAFTAR PUSTAKA

  Mandey, Jasmin Christy Natalia . (2013). “Perataan Tenaga Kerja Menggunakan

  Miscrosoft Project Pada Pekerjaan Peningkatan Jalan”. Jurnal Sipil Statik.

  1(10), 671-677. Pinontoan, Mitchel Danny Maximilian, Mandagi, R J M, dan Mangare, Jantje.

  (2015). “Pengendalian Biaya dan Waktu Dengan Metode Analisis Nilai dan Hasil Dengan Microsoft Project 2010”. Jurnal Sipil Statik. 3(12), 787-803.

  I G usti Ngurah Oka Suputra. (2011). “Penjadwalan Proyek Dengan Precedence

  Diagram Method (PDM) dan Ranked Position Weight Method (RPWM)”.

  Jurnal Ilmiah Teknik Sipil. Vol. 15, No. 1. Abrar

  Husen. 2009. “Manajemen Proyek, Perencanaan, Penjadwalan dan Pengendali an Proyek”. C.V Andi Offset.Yogyakarta. Imam Soeharto . 1997. “Manajemen Proyek dari Konseptual sampai Operasional”.

  Erlangga.Jakarta. Juliana. (2016). “Analisis Pengendalian Biaya dan Waktu Pada Proyek Konstruksi

  Dengan Metode Earned Value Management (EVM) ”. Faktor Exacta. 9(3), 257-265.

  Dwi Kartikasari. (2014). “Pengendalian Biaya dan Waktu Dengan Metode Earned

Value ”. Extrapolasi Jurnal Teknik Sipil Untag Surabaya. 7(2), 107-114.

  Dewa Ketut Sudarsana. (2008). “Pengendalian Biaya dan Jadual Terpadu Pada

  Pr oyek Konstruksi”. jurnal Ilmiah Teknik Sipil. Vol. 12, No.2. Adi Kusrianto. 2008. “Panduan Lengkap Memakai Microsoft Project 2007”. PT.

  Elex Media Komputindo.Jakarta. Natasya Stiefani. (2013). “Pengendalian Biaya dan Waktu Dengan Menerapkan

  Aplikasi Earned Value Analysis Pada Software Microsoft Project 2007”. Skripsi Tidak Diterbitkan. Surakarta. FT UNS. Budi Witjaksana dan Samuel Petrik Reresi.

  (2012). “Analisis Biaya Proyek Dengan Metode Earned Value dalam Proses Kinerja”. Extrapolasi Jurnal Teknik Sipil Untag Surabaya. 05(02), 45-56.

Dokumen yang terkait

ANALISA PENGENDALIAN WAKTU DAN BIAYA PROYEK DENGAN METODE PERT PADA PROYEK PEMBANGUNAN KANTOR UTAMA PT. BARATA INDONESIA-GRESIK

0 21 2

EVALUASI BIAYA DAN WAKTU TERHADAP PENJADWALAN DENGAN MENGGUNAKAN PROGRAM PRIMAVERA PROJECT PLANNER 3.0 PADA PROYEK REHABILITASI JEMBATAN BRUNJUNG PONOROGO

0 14 1

EVALUASI PENJADWALAN WAKTU DAN BIAYA PADA PROYEK PEMBANGUNAN GEDUNG KELAS DI FAKULTAS EKONOMI UNIVERSITAS JEMBER DENGAN METODE PERT

22 209 94

ANALISIS NILAI HASIL TERHADAP WAKTU PADA PROYEK KONSTRUKSI (STUDI KASUS PADA PROYEK PEMBANGUNAN HOTEL EASTPARC YOGYAKARTA)

0 1 9

APLIKASI VALUE ENGINEERING DENGAN METODE ANALYTICAL HIERARCHY PROCESS (AHP) TERHADAP STRUKTUR PELAT PADA PROYEK PEMBANGUNAN HOTEL AZIZA SOLO

3 5 7

PENGENDALIAN BIAYA DAN WAKTU PADA PROYEK PEMBANGUNAN HOTEL DENGAN MENGGUNAKAN PRIMAVERA PROJECT PLANNER P6 (Studi Kasus Pembangunan Hotel In Yogyakarta)

0 0 9

PENERAPAN TIME COST TRADE OFF DALAM OPTIMALISASI BIAYA DAN WAKTU DENGAN PENAMBAHAN SHIFT KERJA DAN KAPASITAS ALAT (STUDI KASUS PROYEK PEMBANGUNAN JALAN TOL SOLO – SEMARANG, RUAS BAWEN – SOLO SEKSI II)

0 2 11

PENGENDALIAN BIAYA DAN WAKTU DENGAN MENERAPKAN METODE EARNED VALUE ANALYSIS (EVA) MENGGUNAKAN SOFTWARE MICROSOFT PROJECT 2007 (STUDI KASUS DI PROYEK PEMBANGUNAN HOTEL BROTHERS 2 SOLO BARU, SUKOHARJO)

0 1 8

PENERAPAN METODE EARNED VALUE MANAGEMENT (EVM) DALAM PENGENDALIAN BIAYA PROYEK Sufa‟atin

0 0 11

EVALUASI PERENCANAAN DAN PENGENDALIAN PROYEK PEMBANGUNAN AIR BERSIH DENGAN MENGGUNAKAN METODE LEAN PROJECT MANAGEMENT

1 3 8