PERENCANAAN PEMBANGKIT LISTRIK TENAGA MIKRO (MICRO HYDRO POWER PLAN-MHPP)DI UNIVERSITAS MUHAMMADIYAH MALANG

PERENCANAAN PEMBANGKIT LISTRIK TENAGA MIKRO(MICRO HYDRO
POWER PLAN-MHPP)DI UNIVERSITAS MUHAMMADIYAH MALANG
Oleh: ULUNG RINENGGO PERBOWO ( 01520080 )
Civil Engineering
Dibuat: 2007-09-11 , dengan 3 file(s).

Keywords: Dimensi Struktur , Daya Dukung Tanah
Proyek pembangunan Pembangkit Listrik Tenaga Mikro Hidro (PLTMH) di
kampus III Universitas Muhammadiyah Malang bertujuan untuk memanfaatkan potensi
sumber daya alam yang ada di sekitarnya.
Dan berdasarkan pada studi pendahuluan yang telah ada sebelumnya, tercatat
data debit sungai Kali Brantas rata -rata bulanan maksimum 17,872 m3/dt (Januari 2004)
dan debit rata-rata bulanan minimum 0,808 m3/dt (Nopember 1997). Dengan luasan baku
sawah D.I Sengkaling Kanan & 2200 Ha (1897), menyusut menjadi 194,00Kiri awal
Ha di D.I. Sengkaling Kiri (2006) dan 81,00 Ha pada D.I Sengkaling Kanan (2006).
Potensi sumber daya air yang tersisa akibat pengurangan kebutuhan air irigasi, ditunjang
dengan kondisi topografi yang ada di sekitar Kampus UMM memungkinkan untuk
dikembangkan Pembangkit Listrik Tenaga Mikro Hidro (PLTMH).
Dari hasil pembahasan dan analisa desain rencana didapatkan dimensi saluran
pembawa b = 1,00 m dan h = 0,50 m. Kolam penampung (L) = 12,00 m, (B) = 6,00 m
dan (H) = 4,00 m. Pipa pesat d = 0,711 m dan ketebalan 0,60 cm, turbin Type X-Flow T15, D500-160. Pondasi blok untuk generator dan coupling B = 1,2 m, L = 2,0 m, H = 0,8

m, dengan daya dukung tanah ijin qijin = 30,52 t/m2.

Abstract

Project development Micro-Hydro Power Plant (MPP) in
Muhammadiyah University of Malang Campus III aims to harness the potential of
natural resources around him.
And based on preliminary studies that have been there before, carrying
Brantas river discharge data on average monthly maximum 17.872 m3/sec (January 2004)
and debit the minimum monthly average 0.808 m3/sec (November 1997). With raw area
IN fields Sengkaling Right & Left early   2200 Ha (1897), shrank to 194.00
Ha at D.I. Sengkaling the Left (2006) and 81.00 hectares at AT Sengkaling Right (2006).
Potential water resources are left due to the reduction of irrigation water requirements, supported
with the existing topography around campus UMM allows for
developed Micro Hydro Power (MHP).
From the results of the discussion and analysis, plan design channel dimensions obtained
carrier b = 1.00 m and h = 0.50 m. Ponds (L) = 12.00 m, (B) = 6.00 m
and (H) = 4.00 m. Rapid pipe d = 0.711 m and 0.60 cm thick, Type X-Flow turbine T15, D500-160. The foundation blocks for the generator and the coupling B = 1.2 m, L = 2.0 m, H
= 0.8
m, with a carrying capacity of land a permit qijin = 30.52 t/m2.