Investigasi kesiapan implementasi concurrent engineering pada devisi general engineering PT. PAL Indonesia (Persero) - ITS Repository
By:
ARGON FAISAL MARCONI
2511100108
SUPERVISOR:
IMPLEMENTATION READINESS IN GENERAL
ENGINEERING DIVISION OF PT. PAL INDONESIA
(PERSERO)
PUTU DANA KARNINGSIH
OUTLINE INTRODUCTION
Background
Problem Formulation
Research ObjectiveINTRODUCTION Research Benefit Research Scope
BACKGROUND 15%
Heavy and Civil Total world engineering
GDP in 2020
13%
Total world General
GDP in 2013 Construction
Construction Industry Construction Project
(Schilling,2013) Market %GDP
7.8% GDP 2008 BACKGROUND
Late Schedule
Alwi et. Al (2002)
Damage Material Waiting time for maintenance
External conditions (26.79%)
Hari et al (2009)
Change of drawing document (21.43%) Condition of the field (19.64%)
Sukirno Change of technical BACKGROUND
NAVAL SHIP BUILDING MERCHANT OR COMMERCE SHIP BUILDING HARKAN SERVICE PRODUCT GENERAL ENGINEERING BACKGROUND 57% 30%
New sector focus GENERAL ENGINEERING
Edi Widiarto Powerplant
Late material (KMPG, 2013) delivery
(Agus, 2014)
Inadequate expert DO “RECOVER”
Increase By:
High Frequency of Design Change Production increase speed, Cost 10%-20%
Increase man power Increase BACKGROUND
Evboumwan and Anumba (1998) defined Concurrent Engineering (CE) as an optimise the design of the
“...attempt to project and its construction process to achieve reduced lead times, and improved quality and cost by the integration of design, fabrication, construction and erection activities and by
GENERAL ENGINEERING
maximising concurrency collaboration
and in working practices”. BACKGROUND 2. Assessment
(Pawar, et al., 1996)
Readiness Assessment Readiness Level Problem Formulation how to minimize engineering design change that often occurred in General Engineering Division by implementing CE , and to measure the readiness level of CE implementation in General Engineering Division
PT. PAL Indonesia (Persero) with BEACON Model Problem Formulation
To know readiness level of CE implementation in General Engineering division PT. PAL Indonesia (Persero)
Research Research Objective
To provide recommendation for lowest factor
Objective
of readiness level to implement CE in General Engineering Division PT. PAL Indonesia (Persero). Research Research benefit
Benefit
know the readiness level of CE implementation. get improvement recommendation Research Scope LIMITATION
This research is done until
improvement suggestion and
not until improvement
implementation.
This research is conducted in
General Engineering Division
PT PAL Indonesia (Persero)ASSUMPTION
There are no company policy changing that influence significantly to the research.
The improvement suggestion can be done by the company
Financial problem is not influence the project implementation
Research scope
LITERATURE REVIEW
Concurrent Engineering Concurrent Engineering in Construction Literature Review
Readiness Assessment of Concurrent Engineering Summary of Previous Research
CONCURRENT ENGINEERING
Winner (1998) defined CE as
integrated , concurrent design of products and their related
‘ processes, including manufacture and support’ with the ultimate goal of customer satisfaction through the reduction of cost and
time-to-market , and the improvement of product quality’
(Soruce: Moges, 2007) CE IN CONSTRUCTION BENEFIT REASON TO ADOPT
READINESS ASSESSMENT BENEFITBEACON MODEL
More effective and better in implementing CE in construction industry.
Make the industry can evaluate and benchmark its project operation process.
)
Develop appropriate tools to implement CE in the industry
, 2000 ba
Make the industry can identify which area that need
um
an improvement or changes
An dan
Make the industry realized the needs of implement
SUMMARY OF PREVIOUS
RESEARCH
Khalfan et al. (2001) Khalfan et al. (2000)
Cheria, S (2014) Marconi, F.A (2015)
An investigation of the readiness of the Concurrent engineering readiness assessment of sub-contractors within the
UK construction industry Preparing concurrent engineering implementation
Investigation Of Concurrent Engineering Implementation
Readiness In General Engineering Division of PT. Pal Indonesia (Persero) METHODOLOGY
METHODOLOGYResearch Problem
Literature CE Team
Data Collection Objective
Formulation Review
Forming Determination
Start A
Field Study Problem Identification and Formulation Phase METHODOLOGY
Research Problem
Literature CE Team
Data Collection Objective
Formulation Review
Development Determination
Start A
Field Study Problem Identification and Formulation Phase METHODOLOGY
Field Study In Depth Interview
Focus Group Discussion METHODOLOGY
Field Study In Depth Interview
Focus Group Discussion Data Collection
CE Team Engineering design Procurement QC/QA METHODOLOGY
Measuring BEACON
Readiness level Conclusion and
Questionnaire Gap Analysis Improvement of CE Suggestion
Filling Implementation
A END
Assessment of CE Readiness Phase METHODOLOGY
Score of questionnaire measure by summarize all of score from each question Measuring divided by number of question and times 4. Readiness level of CE
Implementation Fill by Expert
BEACON Questionnaire
Filling NEVER SELDOM
1 SOMETIME
OFTEN
2
3 METHODOLOGY
Measuring BEACON
Readiness level Conclusion and
Questionnaire Gap Analysis Improvement of CE Suggestion
Filling Implementation
A END
Assessment of CE Readiness Phase
CE READINESS ASSESSMENT
Existing new project development CE implementation planning CE READINESS ASSESSMENT
CE readiness assessment Improvement Existing New Project
Marketting Diivision PMO PPC Dept ENG Dept ADA Div MANPRO MES & RA Dept FV Dept QA GE Dept. CUST/AI
Development START C IPP Accept from Head of division Design Schedule Contract receive material spec, list Paint estimation Annext to oder of material/eq Document: Production Production schedule schedule Shop drw Marketing Bidding by division Project progress and constraint report Creating scope of workload Creating work Inspection spec Create: Shop drw, Cutting equipment & picture Material/equip procurement process IPP Receive paint area data weight data Shop drw paint area data cutting plan weight data Material & verification Equipment progress Project C N Success? planning Organic data, weight data plan, pPaint area mat/eq Annex to Project Create: list of order Service process monitoring & Create PCCL Create PCCL Equipment equipment equipment Material/ Material/ Material/ Design schedule Production & Y OK report Contract accept B Y Y using suggestion Sub contractor enough? N paint estimation material spec coordination Project progress report ready? ready? Mat & Mat & Pers ` Pers N NCR N schedule and production Creating design C Production Production process process A B Inspection Inspection invitation invitation List material and equioment Invite QA/Cust/ n by QA? inspectio Need Y Inspection A Create Mo1 & M04 N by cust/ witness Need AL OK CE Implementation PlanNew Project of GE Division EPCI of Madura BD Field
Jacket 100 Meters x 75 Meters Topside 75 meters x 25 meters x 19 meters CE Implementation Plan
- Engineering department In charged in coordinating of all of members during design phase of project implementation.
- Procurement department In charged of purchasing materials that is needed to fabricate the component after design phase.
- Fabrication & installation department In charged in fabricating component after design and material arrived.
- PPC department In charged in planning all activities from beginning of the project until the end of the project.
- QA/QC department
In charged of product or component’s quality. The quality of components that have been CE Team fabricated has to meet customer requirement and quality regulation.
- Finance & Tax department In charged of managing budget in project development process.
- Marketing department
In charged in getting order from client. Marketing member is also in charged to inform clear information about requirement of customer to all member of team CE Readiness Assessment Questionnaire Verification
EXPERT JUDGEMENT
Assessment Questionnaire Verification
Mr. Agus Budiyanto As
General Manager Q Assessment Desired Condition Assessment
Existing Condition Assessment Existing Condition and Existing Condition Q Assessment
Filed by Mr. Bambang Setyawan As Deputy project manager Q Existing Condition Assessment
AD HOC REPEATABLE CHARACTERIZED MANAGED OPTIMIZING Management System Process Focus Organizational Framework Strategy Deployment Agility Team in Organization Discipline Team Leadership and Management Quality Assurance Client Focus Communication Support Coordination Support
Information Sharing
Integration Support Task Support TECHNOLOGYELEMENT PROCESS
ELEMENT Plot the result in Spider Diagram Desired Condition Q Assessment
Filed by MrAgus Budiyanto As General manager of Division Q Desired Condition Assessment
Plot the result in Spider Diagram AD HOC REPEATABLE CHARACTERIZED MANAGED OPTIMIZING Management System Process Focus Organizational Framework Strategy Deployment Agility Team in Organization Discipline Team Leadership Quality Assurance and Management Client Focus Communication Support Coordination Support Information Sharing Integration Support Task Support
TECHNOLOGY
ELEMENT
PROCESS ELEMENT Q Existing Condition Analysis
AD HOC REPEATABLE CHARACTERIZED MANAGED OPTIMIZING Management System Process Focus Organizational Framework Strategy Deployment Agility Team in Organization Discipline Team Leadership and Management
Quality Assurance
Client Focus Communication Support Coordination Support Information Sharing Integration Support Task Support TECHNOLOGYELEMENT PROCESS
ELEMENT Existing Condition Q Analysis
TEAM IN ORGANIZATION
Individual reward Team reward
EXISTING CONDITION
IT System Q
Gap Analysis
AD HOC REPEATABLE CHARACTERIZED MANAGED Management System Process Focus Organizational Framework Strategy Deployment Agility Team in Organization Discipline Quality Assurance Client Focus Communication Support Coordination Support Information Sharing Integration Support Task Support TECHNOLOGY ELEMENT
PROCESS ELEMENT AD HOC REPEATABLE CHARACTERIZED MANAGED Management System Process Focus Organizational Framework Strategy Deployment Agility Team in Organization Discipline Quality Assurance Client Focus Communication Support Coordination Support Information Sharing Integration Support Task Support
TECHNOLOGY ELEMENT PROCESS ELEMENT
AD HOC REPEATABLE CHARACTERIZED MANAGED Management System Process Focus Organizational Framework Strategy Deployment Agility Team in Organization Discipline Quality Assurance Client Focus Communication Support Coordination Support Information Sharing Integration Support Task Support TECHNOLOGY ELEMENT
PROCESS ELEMENT
IMPROVEMENT
IMPROVEMENT
RECOMMENDATION RECOMMENDATION
FOR FOR
IT SYSTEM REWARD SYSTEM
IMPROVEMENT Potential alternatives Extra Benefit Implementa Discussion
Benefit tion analysis plan Q
IMPROVEMENT ALTERNATIVES
Stajkovic & Luthans, (1997)
& Reward System Team Member of the month Personal Recognition
- 1 thank you card = a voucher for car wash
- 5 thank you card = a voucher for dinner in a restaurant
IMPROVEMENT ALTERNATIVES
that re-engineering the manufacturing process, distribution, finance, human resource and other business process in a company to increase the efficiency, agility, and profitability (O’Brien, 2005)
MORSE SAP R/3 marine construction company content of messages exchanged between an LDAP client and an LDAP server. LDAP
IT System 4 3 (Read/Write) Master LDAP Client 2
5 Q
IMPLEMENTATION PLAN
(outstanding employee/group in term of performance) WHO
WHAT (cash prizes, merchandize, etc) (the nomination procedures, committee, point system, etc)
HOW
Reward System
(Nelson, 1994) an effort to increase motivation of team member.
So, it can increase the readiness level of WHY
Concurrent Engineering Implementation WHO Employee in each team
The alternatives: thank you card,
team member of the month,
WHAT
manager congratulates directly Q
IMPLEMENTATION PLAN
- The top management of PT PAL Indonesia (Persero) is commit to implement the improvement alternatives
- PT PAL Indonesia (Persero) has good financial ability to implement the improvement alternatives
Assumption
- Understand why company want to implementer so they support
IT System the improvement alternatives implementation
- All employee support the implementation process
IMPLEMENTATION PLAN
Project Busine Final Simula Validat prepar ss blue prepar tion ion ation print ation
IT System project preparation, 2 weeks;
Average Time: business blue print, 6 weeks;
12 Months simulation, 10 weeks; validation, 21 weeks; (Fleisch et al., 2004) and final preparation, 13 weeks Q Implementation plan
Total investment in year 1 = 10 x $220 = $2,200 Total investment in year 2 = 10 x $85 = $850
Invest yearly
Total investment in year 3 = 10 x $85 = $850 And etc
IT System
Q BENEFIT ANALYSIS
- Motivation of all member of team will increase Expected benefits
- Build a better work environment • Savings $200,000 in a year. Savings = Expected cost reduction x total cost of production x number of project
Reward System
= 5% x $2,000,000 x 2 = $200,000
- In a year there are two milestone
- There are two teams for two projects in a year
- Team of the month cost Rp 200.000 once or equal to $15.9 or $127.22 in a year
- Thank you card reward cost thank you card reward is assumed
Rp 1.000.000 once or equal to $79.51 or $636.08 in a year Assumption
- manager congratulates directly reward is assumed Rp 50.000 once or equal to $3.98 or $31.81 in a year
BCR = savings/total cost = $200,000/ $127.22 = 1.572,125
Team Member of the month Benefit
BCR = savings/total cost = $200,000/ $636.08
Cost
= 314.43
Ratio Thank You Card
BCR = savings/total cost = $200,000/ $31.81 = 6.288,5 Q BENEFIT ANALYSIS
- Administrative costs of fax and telephone is going down Expected benefits
- Order processing will be simpler
- Support more integration between departments • Savings $200,000 in a year.
Savings = Expected cost reduction x total cost of production x number of project SAP R/3
= 5% x $2,000,000 x 2 = $200,000
- There are two teams for two projects in a year
- Planning horizon is 10 years Assumption
savings
1
2
9
10 Cash Flow
SAP R/3 Initial investment
$1,790,000
- Calculate the outflow Net Present Value (NPV) The outflow NPV is $1,790,000. It because in the next years there are no outflow.
- Calculate the inflow NPV The interest rate (i) that used to calculate the NPV is 3%. The calculation of inflow NPV is explained below.
1
10
- …..+ FV/ (1+i) NPV = FV/ (1+i)
1
10
= $200,000/ (1+0.03) + .........+ $200,000/ (1+0.03) = $618,307.90
- Calculate the ratio by dividing inflow NPV with outflow NPV
Q BENEFIT ANALYSIS
- Support good integration between department Expected benefits
- Data is more safe and secure
- Administrative costs of fax and telephone is going down • Savings $200,000 in a year.
Savings = Expected cost reduction x total cost of production x number of project = 5% x $2,000,000 x 2 = $200,000
- There are two teams for two projects in a year
- Planning horizon is 10 years Assumption
$200,000 Q BENEFIT ANALYSIS
1
2
9
10 Cash Flow $850 $2200
- Calculate the outflow Net Present Value (NPV) The interest rate (i) that used to calculate the NPV is 3%. The calculation of outflow NPV is explained below.
10 NPV = FV/ (1+i) +…..+ FV/ (1+i)
1
10
= $2,200/ (1+0.03) + $850/ (1+0.03) +…+$850/ (1+0.03) = $9,450.67
- Calculate the inflow NPV The interest rate (i) that used to calculate the NPV is 3%. The calculation of inflow NPV is explained below.
1
10 NPV = FV/ (1+i) +…..+ FV/ (1+i)
1
10
= $200,000/ (1+0.03) + …..+ $200,000/ (1+0.03) = $618,307.90
- Calculate the ratio by dividing inflow NPV with outflow NPV
Q DISCUSSION Benefit Cost Ratio SWOT analysis
Reward System Team Member of the month Thank You Card Q DISCUSSION Benefit Cost Ratio SWOT analysis
IT System SAP R/3 Q DISCUSSION
IMPROVEMENT ALTERNATIVES 1.
Thank You Card & 2.
Team Member of the month & 3.
& Q POTENTIAL EXTRA BENEFIT Improvement in rewarding system General Engineering Division of PT PAL Indonesia (Persero) Increase Motivation Employee Increase employee discipline Implement Impact Impact
Extra benefit of reward system Potential extra benefit for other part from the improvement
CONCLUSION AND SUGGESTION
1. Based on the questionnaire result, General Engineering Division
PT PAL Indonesia (Persero) reached managed level and has total average score 74,65%. The average score for each element are 78% for process element , 72% for people element , 77% for project element and 72% for technology element . The parts that need to be improved is team in organization part in people element (58%) and integration support part in technology element (53%) which means both of them categorized to characterized level.
2. There are three alternatives to improve the readiness level of
ConclusionGeneral Engineering division on team in organization part in people element. The first is implementing team member of the month . The second is implementing thank you card . The third is implementing a method that allow a top management or team leader congratulating directly to the team member who has best performance. To improve the readiness level of General Engineering division on integration support part in technology element, the alternatives are implement SAP R/3 and Lightweight Directory Access Protocol (LDAP).
1. Suggestion for PT PAL Indonesia (Persero) Top Management keep increasing the understanding about
Concurrent Engineering
Before implement CE, top management of General Engineering Division PT PAL Indonesia (Persero) has to increase the commitment to solve the part with lowest value from the result of BEACON Model by implementing the improvement recommendation before implementing Concurrent Engineering.
Top management also gives better understanding to the all Suggestion employees about Concurrent Engineering.
2. Suggestion for Next Research Focus Group Discussion (FGD) with CE team is an important activity to do. It better conduct FGD more than one time if it possible in order to make better understanding about CE in CE team member.
Besides assess the company, it needs to assess the whole company supply chain.