Proyek Perluasan Pabrik Feronikel Pomalaa Pomalaa Ferronickel Plant Expansion Project
q. Proyek Perluasan Pabrik Feronikel Pomalaa q. Pomalaa Ferronickel Plant Expansion Project
(”P3FP”) (lanjutan)
(“P3FP”) (continued)
Tanggal 26 Maret 2012, Perusahaan dan PT On March 26, 2012, the Company and PT Adhi Adhi Karya (Persero) Tbk menandatangani
Karya (Persero) Tbk entered into an agreement perjanjian
for the latter to procure and install a jetty and dermaga dan fasilitas dengan nilai kontrak
facilities with a contract value of US$32,874,083. AS$32.874.083. Perjanjian tersebut berlaku
The agreement is valid until June 26, 2013. The sampai 26 Juni 2013. Perusahaan dan PT Adhi
Company and PT Adhi Karya (Persero) Tbk has Karya (Persero) Tbk menyetujui perpanjangan
agreed a contract extension which is valid until kontrak sampai dengan 15 Agustus 2013.
August 15, 2013. As at December 31, 2013, PT Hingga 31 Desember 2013, PT Adhi Karya
Adhi Karya (Persero) Tbk has not completed the (Persero) Tbk belum menyelesaikan pekerjaan
project and the Company did not approve the tersebut dan Perusahaan tidak menyetujui
second amendment to the contract so the target perpanjangan kedua atas kontrak tersebut,
date was still on August 15, 2013. Because of sehingga target date tetap berlaku pada 15
that, the Company has the rights to impose fines Agustus 2013. Karena itu, Perusahaan berhak
due to late completion of work and started occur untuk memberlakukan denda keterlambatan
based on contract (6 weeks after target date). berdasarkan kontrak (6 minggu setelah target
Construction in progress as of December 31, date). Persentase penyelesaian konstruksi
2014 was 100%.
hingga 31 Desember 2014 adalah 100%. Tanggal 28 Maret 2012, Perusahaan dan PT
On March 28, 2012, the Company and PT Wijaya Karya (Persero) Tbk menandatangani
Wijaya Karya (Persero) Tbk entered into an perjanjian
agreement for the latter to procure and install Refining-3
contract value of Perjanjian tersebut berlaku sampai 28 Januari
US$35,475,000. The agreement was valid until 2014. Perpanjangan atas kontrak tersebut tidak
January 28, 2014. The extension of the contract diterima dan COD tetap berlaku pada 28 Januari
was not accepted and COD remained effective 2014. Karena itu, denda atas keterlambatan
on January 28, 2014. Because of that, fines due penyelesaian kerja akan mulai diberlakukan
to late completion of the work started to occur berdasarkan kontrak (6 minggu setelah COD).
based on the contract (6 weeks after COD). The Tahap konstruksi telah selesai pada 31 Oktober
phase was completed on 2014.
construction
October 31, 2014.
Tanggal 10 Desember 2012, Perusahaan dan On December 10, 2012, the Company and Sumitomo
Sumitomo Corporation entered into an perjanjian pembangunan Pembangkit Listrik
Corporation
menandatangani
agreement related to the construction of the Tenaga Uap (“PLTU”) Pomalaa dengan nilai
Pomalaa coal-fired power plant with total kontrak keseluruhan sebesar AS$57.275.290,
of US$57,275,290, JPY3.439.137.022 dan Rp412.748.103.
contract
values
JPY3,439,137,022 and Rp412,748,103. Tanggal 17 Mei 2013, Perusahaan dan
On May 17, 2013, the Company and Sumitomo Sumitomo Corporation telah menandatangani
Corporation entered into a Notice to Proceed to Notice to Proceed untuk memulai pembangunan
start construction of Coal Fired Power Plant PLTU yang ditargetkan selesai pada atau
which is expected to be completed on or before sebelum tanggal berakhirnya yaitu 25 bulan dan
the date falling 25 months and 28 months after
28 bulan setelah tanggal Notice to Proceed the date of the Notice to Proceed for Unit 1 and tersebut masing-masing untuk Unit 1 dan Unit 2.
Unit 2, respectively. On April 15, 2013, the Pada tanggal 15 April 2013, Perusahaan dan
Company and Sumitomo Corporation signed Sumitomo
Corporation
Amendment I to amend the provisions on the Amendment I untuk mengubah ketentuan
menandatangani
standby letter of credit stated under the contract mengenai standby letter of credit yang
signed on December 10, 2012. Construction in dinyatakan dalam perjanjian yang ditandatangani
progress as of December 31, 2014 was 63.30%. pada
penyelesaian konstruksi hingga 31 Desember 2014 adalah 63,30%.
32. PERJANJIAN PENTING,
IKATAN
DAN
32. SIGNIFICANT AGREEMENTS, COMMITMENTS