Overview MP2 [Compatibility Mode]
Project lifecycle
What is a Project?
A project is a temporary endeavor undertaken to accomplish a unique purpose.
Projects normally involve several people performing interrelated activities, and the main sponsor for the project is often interested in the effective use of resources to complete the project in an efficient and timely manner.
A project has a unique purpose.
A project is temporary.
A project requires resources, often from various area.
A project should have a primary sponsor or customer.
A project involves uncertainty.
A Balancing Act
Schedule requirements cost
The Project
Source: William Gendron, presentation at 1998 PMI Global Forum
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
A Balanced Project
Time
Cost
Scope
Quality
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Expectation and Objective Congruency
Client/Customer Expectations
Low
High Customer wants
Low
OK
more than the
organization
Business
intends to provide.
Objectives
Business needs High more from the project
OK
than the customer.
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
What is Project Management?
Project management is the application of knowledge, skills, tools, and techniques to project activities in order to meet project requirements.
Project managers must not only strive to meet specific scope, time, cost, and quality goals of projects, they must also facilitate the entire process to meet the needs and expectations of the people involved in or affected by project activities.
Project Management Framework
Mapping Of Project Management Processes and PMBOK Knowledge Areas
What is Project Management, Continued
Stakeholders are the people involved in or affected by project activities and include the project sponsor, project team, support staff, customers, users, suppliers, and even opponents to the project.
Successful project managers work on developing good relationships with project stakeholders to ensure their needs and expectations are understood and met.
What is Project Management, Continued
Knowledge areas describe the key competencies that project managers must develop.
• The four core knowledge areas of project management include
project scope, time, cost, and quality management.
• These are considered to be core knowledge areas because they lead to specific project objectives.
• The four facilitating knowledge areas of project management are
human resources, communications, risk, and procurement management .
• These are called facilitating areas because they are the means through which the project objectives are achieved.
• Project integration management, the ninth knowledge area, is an
overarching function that affects and is affected by all of the other knowledge areas.
What is Project Management, Continued
Project management tools and techniques assist project managers and their teams in carrying out scope, time, cost, and quality management.
• Some popular time management tools and techniques include Gantt charts, network diagrams (sometimes referred to as PERT charts), and critical path analysis.
Additional tools help project managers and teams carry out human resource, communications, risk, procurement, and integration management.
Project management software is a tool that can facilitate management processes in all the knowledge areas.
Project Management and Other Disciplines
Much of the knowledge needed to manage projects is unique to the discipline of project management.
However, project managers must also have knowledge and experience in general management and must understand the application area of the project in order to work effectively with specific industry groups and technologies.
Managemen Proyek dan Disiplin
Lain
Contrast Projects and Operations
Projects
Operations
Create own charter,
Semi-permanent charter,
organization, and goals
organization, and goals
Catalyst for change
Maintains status quo
Unique product or service
Standard product or service
Heterogeneous teams
Homogeneous teams
Start and end date
Ongoing
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Integration Management
Cost
Time
Integration
Quality
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Summary
Defined key PM concepts Described why PM is needed Explained difference between projects and operations Identified trends in the PM environment Discussed project success and failure factors Identified potential benefits of PM
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Unit 2: Project Life Cycle Models
Upon completion, you will be able to …
List the purpose and types of project life cycle models Distinguish between project and product life cycle Define the role of phase reviews in PM Apply a model to a hypothetical and a real project
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Key Concepts
Project phase: “A collection of logically related project activities usually culminating in the completion of a major deliverable.”
Project life cycle: “Collectively the project phases are known as the project life cycle.”
Product life cycle: The natural grouping of ideas, decisions, and actions into product phases, from product conception to operations to product phase-out.
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Generic Cost and Staffing Life Cycle
Cost and
Intermediate Phases
Staffing
(one or more)
Level
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Project Life Cycle
Example Phases
Concept and Proposal
Initial Phase
Intermediate Phases
Final Phase
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Unit 3: Initiating Projects
Upon completion, you will be able to …
List the main functions of each PM process group Describe the purpose of the initiation process Identify its inputs and outputs, tools and techniques Develop a sample project charter Give an example of how process groups can apply to the project as a
whole or to a project phase
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Process Definition
“A series of actions people take to bring about a desired result.” Types of processes
Project management processes Product-oriented processes Business-oriented processes
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Process Groups
Closing Processes
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Process Group Overview
Initiating Processes
To the Planning 5.1 Processes
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Purpose of Initiation Process
1. To commit the organization to a project or phase
2. To set the overall solution direction
3. To define top-level project objectives
4. To secure the necessary approvals and resources
5. Validate alignment with strategic objectives
6. To assign a project manager
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Initiating Core Process—Initiation
1. Product description
“Initiation is the process of
1. Project charter
2. Strategic plan
formally recognizing that a new
2. Project manager identified/
3. Project selection criteria
project exists or that an existing
assigned
4. Historical information
project should continue into its next phase.”
3. Constraints 4. Assumptions
Tools and Techniques
1. Project selection methods 2. Expert judgment
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Project Charter
“A document issued by senior management that provides the project manager with the authority to apply organizational resources to project activities.”
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Project Charter Content
Business need Project objectives Project deliverables Assumptions Constraints Key staff Written authorization
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Exercise 3-1
Project Charter
Using the handout, complete the sample project charter Assume you are the project manager As an example, choose an anticipated major project assignment
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Sample Initiating Activities
Negotiate, write, and refine the project charter Confirm how the project links to the business need Identify management responsibilities Identify geographic locations involved Test top-level objectives versus strategic business plans Make strategic procurement decisions, e.g., make, buy, or identify
qualified vendors
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Key Outputs of Initiation Process
Project charter Project manager identified/assigned Other key positions identified/assigned Constraints identified Assumptions identified
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Table 5.1. Sample Project Charter
Table 5.1. Sample Project Charter (cont’d)
Unit 4: Planning Projects
Upon completion, you will be able to …
Describe the purposes of the planning processes Identify the inputs and outputs of core planning processes Describe the function and develop sample planning deliverables such as
a scope statement, WBS, and milestone chart List the major tools and techniques used in the core planning processes Identify the planning facilitating processes and their functions
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Planning Process Group
Closing Processes
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Purpose of Planning Processes
To develop a project plan that:
Facilitates later accomplishment* Ensures project wide integration Monitors change effectively Provides decision support information to stakeholders Can be updated by iterative planning activities
* Project Management—A Managerial Approach, 1995, by Jack R. Meredith and Samuel J. Mantel Jr.
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Core Processes
Planning Scope 5.2
Schedule Definition 6.4 Activity 6.1 Sequencing Activity Development
5.3 Activity 6.3 Duration
Definition Scope
Estimating
Budgeting Cost
Planning Resource 7.1 7.2
Estimating Cost
Processes Initiating
From the
4.1 Project Plan
Executing (Figure 3–6) Processes
Controlling From the
Facilitating Processes
(Figure 3–7) Processes
Quantification Risk 11.2 Planning 11.3 Planning Development Risk Response
Quality 8.1 Communications 10.1 11.1 Identification Risk
Planning Organizational
Acquisition Staff
Planning Procurement
Planning Solicitation
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Core Planning Processes
Scope Planning
1. Product description
"… the process of developing a
1. Scope statement
2. Project charter
written scope statement as the
2. Supporting detail
3. Constraints
basis for future project
3. Scope management plan
4. Assumptions
decisions including, in particular, the criteria used to determine if the project or phase has been completed successfully.”
Tools and Techniques
1. Product analysis 2. Cost/Benefit analysis 3. Alternative identification 4. Expert judgment
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Project Scope Statement Purpose
To provide a general description of the sum of the products and services to be provided by the project
To develop a common understanding of project scope among stakeholders
May make explicit some exclusions that, based on the audience, would
be assumed to be part of the project
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Scope Statement
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Scope Definition and the Project Scope Statement
The preliminary scope statement, project charter, organizational process assets, and approved change requests provide a basis for creating the project scope statement.
As time progresses, the scope of a project should become clearer and more specific.
Table 5-2. Further Defining Project
Scope
Core Planning Processes
Scope Definition
1. Scope statement
“… subdividing the major project
1. Work breakdown structure
2. Constraints
deliverables (as identified in the
3. Assumptions
scope statement) into smaller
4. Other planning outputs
more manageable components …”
5. Historical information
Tools and Techniques
1. Work breakdown structure templates
2. Decomposition
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Work Breakdown Structure (WBS)
“A deliverable oriented grouping of project elements which organizes and defines the total scope of the project.
Each descending level represents an increasingly detailed definition of a project component.
Project components may be products or services.”
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
WBS Purpose
To define: Solution strategy or general approach Implementation tactics
To support more accurate estimates of project duration and cost than can
be made at the project level To provide a basis for estimating project resources:
Departmental or subcontractor support Vendors and their products Services Any other identifiable resource
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Work Package
Deliverables and Milestones
Deliverables
– Tangible, independent, verifiable work products – Reports, presentations, prototypes, etc.
Milestones
– Significant events or achievements – Acceptance of deliverables or phase completion – Cruxes (proof of concepts) – Quality control – Keeps team focused
Contoh WBS
Level Level Level Level
Work Breakdown Structure Work Breakdown Structure Work Breakdown Structure Work Breakdown Structure
Level Level Level Level
Description Description Description Description
Total Total Total Total
Gedung Gedung Gedung Gedung
Project Project Project Project
Administrasi Administrasi Administrasi Administrasi Mobilisasi/ Mobilisasi/ Mobilisasi/ Mobilisasi/ Pek. Pek. Pek. Pek.
Pek. Pek. Pek. Pek.
Pek. Pek. Pek. Pek.
Subproject Subproject Subproject Subproject
Demobilisasi Demobilisasi Demobilisasi Demobilisasi Persiapan Persiapan Persiapan Persiapan Struktur Struktur Struktur Struktur
atap atap atap atap
Category of Category of Category of Category of
Sitework Sitework Sitework Sitework Pondasi Pondasi Pondasi Pondasi
Sloof Sloof Sloof Sloof
Kolom Kolom Kolom Kolom
Balok Balok Balok Balok
Plat Plat Plat Plat
Work Work Work Work
Work Work Work Work
Galian Galian Galian Galian Penulangan Penulangan Penulangan Penulangan
Cor Cor Cor Cor
Package Package Package Package
beton beton beton beton
Aircraft System
Project Management
Training
Data
Air Vehicle
Equipment Support
Facilities
Test and Evaluation
Engineering Systems
Equipment
Technical Orders
PM Activities Supporting
Facilities
Engineering Data
Intermediate Level
Maintenance
Operational Test
Services
Management Data
Level Depot
Developmental Test
Fire Control
This WBS is illustrative only. It is not intended to represent the full project scope of any specific project, nor to imply that this is the only way to organize a WBS on this type of project.
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Waste Water Treatment Plant
Project Management
Project Management
Civil Drawings
Headworks
Architectural Drawings
Aeration Basin
Structural Drawings
Effluent Pumping Station
Mechanical Drawings
Air Handling Building
HVAC Drawings
Sludge Building
Plumbing Drawings
Instrumentation Drawings
Electrical Drawings
This WBS is illustrative only. It is not intended to represent the full project scope of any specific project, nor to imply that this is the only way to organize a WBS on this type of project.
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Contoh WBS
51
Contoh WBS Proyek gudang kerangka Besi
Tingkat I
Tingkat II
Tingkat III
1. Membuat Gambar
1. Gambar Bangunan
1. Gambar bangunan
2. Instalasi Listrik
2. Instalasi listrik
3. Instalasi air
2. Membeli material
3. Material Bangunan
4. Material Tiang
4. Material pondasi
5. Material dinding
3. Menyiapkan Lahan
5. Menggali tanah
6. Material atap
7. Besi beton
8. Adukan
4. Membuat Pondasi
6. Cor pondasi
9. Memadatkan tanah
10. Menggali tanah
11. Cor Pondasi
5. Pabrikasi (tiang dan
7. Pabrikasi Tiang
12. Pabrikasi Tiang
kerangka atap)
8. Pabrikasi kerangka atap
13. Pabrikasi kusen
6. Mendirikan bangunan
9. Mendirikan tiang
14. Pabrikasi kerangka atap
10.Membuat dinding 15. Mendirikan tiang
11. Menaikkan atap 16. Membuat dinding
17. Pasang kusen
18. Pasang atap
19. Pasang pintu & cat
52
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Benefits of the WBS
Risk and Contingency
WBS
Risk Control
Project Control
Change
Control Activity List Communication Control
Project Plan
Progress
Reports
Validate Your WBS
All major elements been identified at top level? Decomposed into measurable components? Lower level(s) items necessary? All inclusive? Would stakeholders agree WBS is satisfactory? Can elements be scheduled, budgeted, and assigned to a unit that will
accept responsibility? Too much or too little visibility and control ? Can status reports be generated at all levels?
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Using the WBS to Estimate Cost
Project manager establishes work requirements by defining the What—“shalls” and “wills” When—sequence Why—dependencies
Functional managers estimate cost by determining How—equipment and methods Who—type and level of expertise Where—location, department
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Exercise 4-2
Work Breakdown Structure
Using “Post-it® Notes,” construct a WBS for your project or subproject Apply the WBS validation criteria Discuss any learning or insights with a classmate, including any learning
from applying the WBS test criteria
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Pendekatan dalam menyusun WBS
Top Down
Brainstorming all work to be done and then grouping
Using a general-to- into a hierarchy.
specific structure to progressively detail
the work.
Bottom Up
Core Planning Processes
Activity Definition
“Identifying the specific
1. Activity list
2. Scope statement
activities that must be
2. Supporting detail
3. Historical information
performed to produce the
3. WBS updates
4. Constraints
various project deliverables.”
5. Assumptions
Tools and Techniques
1. Decomposition 2. Templates
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Core Planning Processes
Activity Sequencing
1. Activity list
“… identifying and
1. Project network
2. Product description
documenting interactivity
2. Activity list updates
3. External dependencies
dependencies.”
4. Mandatory dependencies 5. Discretionary dependencies 6. Constraints 7. Assumptions
Tools and Techniques
1. Precedence diagramming method 2. Arrow diagramming method 3. Conditional diagramming
method 4. Network templates
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Learning Objectives – Chapter 12
Project scheduling terminologies Precedence relationship Draw activity-on-Arrow (AOA) diagram Calculate earliest start time, earliest finish time, latest start
time, & latest finish time Calculate slack time Find critical path Analysis of possible delays
Project Scheduling Terminologies
A project is a collection of tasks that must be completed in minimum time or at minimal cost.
Activity & Activity duration Precedence relationship , predecessor, successor Activity-On-Node (AON) diagram v.s. Activity-On-Arc
(AOA) diagram PERT (Program Evaluation and Review Technique):
stochastic CPM (Critical Path Method): deterministic
Project Scheduling
Identifying precedence relationships
Sequencing activities © 1995 Corel Corp. Determining activity times
& costs Estimating material &
worker requirements Determining critical
activities
Purposes of Project Scheduling
Shows the relationship of each activity to others and to the project as a whole
Identifies the precedence relationships among activities Encourages the setting of realistic time and cost estimates
for each activity Helps make better use of people, money, and material
resources by identifying critical bottlenecks
Project Scheduling Techniques
Gantt chart Critical Path Method (CPM) Program Evaluation & Review Technique (PERT)
© 1984-1994 T/Maker Co.
Gantt Chart
Time Period Activity J F M A M J J
Design Build
Test
Figure 16.4
Project Control Reports
Detailed cost breakdowns for each task Total program labor curves Cost distribution tables Functional cost and hour summaries Raw materials and expenditure forecasts Variance reports Time analysis reports Work status reports
PERT and CPM
Network techniques Developed in 1950’s
• CPM by DuPont for chemical plants • PERT by U.S. Navy for Polaris missile
Consider precedence relationships and interdependencies Each uses a different estimate of activity times
Questions Which May Be Addressed by Questions Which May Be Addressed by
PERT & CPM PERT & CPM
♦ Is the project on schedule, ahead of schedule, or behind schedule? ♦ Is the project over or under cost budget?
♦ Are there enough resources available to finish the project on time? ♦ If the project must be finished in less than the scheduled amount of time, what is the way to accomplish this at least cost?
The Six Steps Common to PERT & CPM
Define the project and all of its significant activities or tasks
Develop relationships among the activities. (Decide which activities must precede and which must follow others.)
Draw the network connecting all of the activities Assign time and cost estimates to each activity Compute the longest time path through the network.
This is called the critical path Use the network to help plan, schedule, monitor, and
control the project
Network Terms
Project: Obtain a college degree (B.S.) Project: Obtain a college degree (B.S.) Receive diploma Receive diploma
Register Register Attend class, Attend class,
study etc. study etc.
4 4 Years Years
Activity (Arrow) Activity (Arrow)
Event (Node) Event (Node)
Event (Node) Event (Node)
Activity Relationships
B B 33
A & B can occur A & B can occur concurrently concurrently
Activity Relationships
A must be done before A must be done before
C & D can begin C & D can begin
22 D D
B B 33
Dummy Activities
Activities are defined by beginning & ending events
• Example: Activity 2-3
Every activity must have unique pair of beginning & ending events
• Otherwise, computer programs get confused
Dummy activities maintain precedence
• Consume no time or resources
Dummy Activity Example
Incorrect Incorrect
2-3
1-2
3-4
2-3 Correct Correct
1-2
2-4
4-5
2-3
33--4: Dummy 33 4: Dummy
activity activity
Milwaukee General Hospital’s Activities and Predecessors
Activity
Description
Immediate Predecessors
A Build internal components
B Modify roof and floor
C Construct collection stack
D Pour concrete and install frame
A, B
E Build high-temperature burner
F Install pollution control system
G Install air pollution device
D, E
H Inspect and test
F, G
AON Network for Milwaukee General Hospital
Start
Example 2
buat network untuk suatu proyek dengan hubungan sebagai berikut:
Activity
Immediate predecessors
D A, C
G D,E,F
Network of Seven Activities
B dummy
C 5 We need to introduce F
a dummy activity
Precedence Relationships Chart
Immediate
Estimated
Activity
Predecessor Completion Time
A None
B A 15
D G 20
E D 21
F A 25
G C,F
H D 28
I A 30
D,I
Objective of the project scheduling: minimize the completion time of the project
Earliest Start Time / Earliest Finish Time
Make a forward pass through the network as follows:
• Evaluate all activities that have no immediate predecessors. • The earliest start for such an activity is zero (ES = 0) • The earliest finish is the activity duration (EF = Activity
duration) • Evaluate ES of the node for which EF of all its immediate
predecessors has been determined. • ES = Max (EF of all its immediate predecessors) • EF = ES + Activity duration.
• Repeat this process until all nodes have been evaluated • Max (EF of the finish nodes) is the earliest finish time of the
project.
Earliest Start / Earliest Finish
A F F G G D D H H 194
90 25 14 20 28 EARLIEST FINISH
Latest Start Time / Latest Finish Time
Make a backward pass through the network as follows: • Evaluate all activities that immediately precede the finish node(s)
• The latest finish for such an activity is LF = EF of the project
• The latest start for such an activity is LS = LF - activity duration.
• Evaluate LF of the node for which LS of all its immediate successors
has been determined. • LF = Min (LS of all its immediate successors) • LS = LF - Activity duration
• Repeat this process backward until all nodes have been evaluated.
Latest Start Time / Latest Finish Time
B C 110,115
Slack Times
• Slack time is the amount of time an activity can be delayed without delaying the project completion date, assuming no other delays are taking place in the project.
Slack Time = LS - ES = LF - EF
Slack/Float Times
Activity LS - ES Slack
A 0 -0
B 95 - 90
C 110 - 105
D 119 - 119
0 Critical activities Critical activities
E 173 - 149
F must be rigidly 90 - 90 0
G 115 - 115
0 scheduled
H 166 - 149
I 119 - 90
149 - 149
The Critical Path
The critical path is a set of activities that have no slack The critical activities (activities with 0 slack) form
at least one critical path in the network.
A critical path is the longest path in the network. The sum of the completion times for the activities
on the critical path is the EF of the project.
The Critical Path
B C 110,115
Possible Delays
We observe two different types of delays:
• Single delays. • Multiple delays.
Under certain conditions the overall project will be delayed. The conditions that specify each case are presented next.
Single Delays
A delay of a certain amount in a critical activity, causes the entire project to be delayed by the same amount.
A delay of a certain amount in a non-critical activity will delay the project by the amount the delay exceeds the slack time. When the delay is less than the slack, the entire project is not delayed.
Multiple Delays
Multiple delays of non-critical activities
• Case 1: activities are on different paths
• Case 2: activities are on the same path, separated by critical activities.
• Case 3: activities are on the same path, no critical activities separating them.
Slack/float Identification
ACTIVITY
EARLIEST START TIME EARLIEST FINISH TIME
C (8,10)
LATEST FINISH TIME TIME LATEST START TIME
Types Of Slack POSITIVE SLACK NEGATIVE SLACK
Negative Slack
FORWARD PASS BACKWARD PASS
CUSTOMER’S
CUSTOMER’S
START DATE
FINISH DATE
Schedule Compression
Elimination of some parts of the project Addition of more resources Substitution of less time-consuming components or activities Parallelization of activities Shortening critical path activities Shortening early activities Shortening longest activities
Schedule Compression
(Continued)
Shortening easiest activities Shortening activities that are least costly to speed up Shortening activities for which you have more resources Increasing the number of work hours per day
Resource Leveling
Resource leveling is an attempt to eliminate the manpower peaks and valleys by smoothing out the period-to-period resource requirements. The ideal situation is to do this without changing the end date. However, in reality, the end date moves out and additional costs are incurred.
Resource Allocation
Resource allocation (or resource limited planning) is an attempt to find the shortest possible critical path based upon the available or fixed resources. The problem with this approach is that the employees may not be qualified technically to perform work on more than one activity in a network.
Planning Objectives (Primary)
Best time Least cost Least risk
Planning Objectives
Studying alternatives Optimum schedules Effective use of resources Communications Refinement of the estimating process Ease of project control Ease of time or cost revisions
Planning Objectives (Limitations)
Calendar completion Cash or cash flow restrictions Limited resources Management approvals
Program Crashing Costs
ALL ACTIVITIES CRASHED MINIMUM COST
TOTAL CRASH
CRASH B
S 150,000 O
CRASH E
C 140,000
CRASH F
A R 130,000
CRASH A
GO
R 120,000 P
NORMAL OPERATIONS
10 12 14 16 18 20 22 24 PROGRAM COMPLETION TIME, WEEKS
Crash and Normal Times and Costs for Activity B
Time Cost approach
Consider
1. Float
2. Slope
3. Activity Crashing limit
4. Parallel Critical path Procedure
1. Determine Critical path
2. Activity crashed is one in CP with the lowest slope
3. caculate cost
4. do1,2,3 up to get the completion target
Precedence Diagram
Precedence Diagramming Method (PDM)
Aktivitas dinyatakan menggunakan kotak (boxes) Anak panah menunjukkan hubungan antara aktivitas-
aktivitas Lebih baik dalam memperlihatkan tipe-tipe ketergantungan
yg berbeda
Tipe Ketergantungan Tugas (Microsoft Project)
109
110
PERT Activity Times
3 time estimates
• Optimistic times (a) • Most-likely time (m) • Pessimistic time (b)
Follow beta distribution Expected time: t = (a + 4m + b)/6 Variance of times: v = [(b - a)/6] 2
Critical Path Analysis
Provides activity information
• Earliest ( ES ) & latest ( LS ) start • Earliest ( EF ) & latest ( LF ) finish • Slack ( S ): Allowable delay Identifies critical path
• Longest path in network • Shortest time project can be completed • Any delay on critical path activities delays project
• Critical path activities have 0 slack
Earliest Start and Finish Steps
Begin at starting event and work forward ES = 0 for starting activities
• ES is earliest start
EF = ES + Activity time
• EF is earliest finish
ES = Maximum EF of all predecessors for non-starting activities
Latest Start and Finish Steps
Begin at ending event and work backward LF = Maximum EF for ending activities
• LF is latest finish; EF is earliest finish
LS = LF - Activity time
• LS is latest start
LF = Minimum LS of all successors for non-ending activities
Critical Path in Network
Pour Pour
Do interior Do interior
foundation & foundation &
22 work work
frame frame
3 3 wk. wk.
6 wk. 6 wk.
Roof Roof
11 2 wk. 2 wk.
3 wk. 3 wk.
Buy Buy
33 Landscape Landscape
shrubs etc. shrubs etc.
4 wk. 4 wk.
Critical path is longest path: 12 weeks.
Gantt Chart Earliest Start and Finish
Build House Project Build House Project
11 11 Activity 11 Activity
1-2 Fdn & frame 1-2 Fdn & frame 1-3 Buy shrubs 1-3 Buy shrubs
2-3 Roof 2-3 Roof 2-4 Interior work 2-4 Interior work 3-4 Landscape 3-4 Landscape
Gantt Chart Latest Start and Finish
Build House Project Build House Project
11 11 Activity 11 Activity
1-2 Fdn & frame 1-2 Fdn & frame 1-3 Buy shrubs 1-3 Buy shrubs
2-3 Roof 2-3 Roof 2-4 Interior work 2-4 Interior work 3-4 Landscape 3-4 Landscape
Project Times
Expected project time (T)
Used to obtain probability of project
• Sum of critical path activity times, t
completion!
Project variance (V)
• Sum of critical path activity variances, v
PERT Probability Example
You’re a project planner for
General Dynamics. A Corel Corp. submarine project has an
expected completion time
of 40 weeks, with a standard deviation of 5 weeks. What is the probability of finishing the sub in 50 weeks or less ?
Converting to Standardized Variable
X - T 50 -
Normal Normal
Standardized Normal Standardized Normal
Distribution Distribution
Distribution Distribution
s=5
s Z =1
T = 40 50 X m
z =0 2.0 Z
Obtaining the Probability
Standardized Normal Probability Standardized Normal Probability
Table (Portion) Table (Portion)
Z .00
s Z =1
m z =0 2.0 Z
Probabilities in body Probabilities in body
Precedences And Project Activity Times
Immediate
Optimistic Most Likely Pessimistic EXP Var S.Dev
Activity Predecessor
Time Time
h c 2 12 16 11 5.4 2.32
The complete network
b (14,4) (20,0) c g
i (18,28.4)
4 4 44 h 5 55 5
Figure 8-13 The complete Network
1 11 1 33 3 3 f 77 7 7 CRIT. TIME = 43
Critical Path Analysis (PERT)
Activity
LS
ES
Slacks
Critical ?
a 0 0 0 Yes
d 20 20 0 Yes
e 25 20 5 f 29 20 9 g 21 20 1 h 14 10 4
35 35 0 Yes
Assume, PM promised to complete the project in the fifty days. What are the chances of meeting that deadline? Calculate Z, where
Z = (D-S) / √√√√ V Example,
D = 50; S(Scheduled date) = 20+15+8 =43; V = (4+25+4) =33 Z = (50 – 43) / 5.745 = 1.22 standard deviations.
The probability value of Z = 1.22, is 0.888
What deadline are you 95% sure of meeting
Z value associated with 0.95 is 1.645
D = S + 5.745 (1.645) = 43 + 9.45 = 52.45 days
Thus, there is a 95 percent chance of finishing the project by
52.45 days.
Figure 16.9
Benefits of PERT/CPM
Useful at many stages of project management Mathematically simple Uses graphical displays Gives critical path & slack time Provides project documentation Useful in monitoring costs
Advantages of PERT/CPM Advantages of PERT/CPM
♦ Networks generated provide valuable project documentation and graphically point out who is responsible for various project activities
♦ Applicable to a wide variety of projects and industries ♦ Useful in monitoring not only schedules, but costs as well
Limitations of PERT/CPM
Assumes clearly defined, independent, & stable activities Specified precedence relationships Activity times (PERT) follow
beta distribution Subjective time estimates Over-emphasis on critical path
Core Planning Processes
Schedule Development
1. Project network diagram
“… determining start
1. Project schedule
2. Activity duration estimates
and finish dates for
2. Supporting detail
3. Resource requirements
project activities.”
3. Schedule management plan
4. Resource pool description
4. Resource requirements
5. Calendars
updates
6. Constraints 7. Assumptions 8. Leads and lags
Tools and Techniques
1. Mathematical analysis 2. Duration compression 3. Simulation 4. Resource leveling heuristics 5. Project management
software
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Key Scheduling Concepts
Master schedule Crashing Hanger Workaround Schedule variance
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Milestone Chart
Data Date
Subcontracts Signed Specifications Finalized Design Reviewed Subsystem Tested First Unit Delivered Production Plan Completed
There are many other acceptable ways to display project information on a milestone chart.
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Core Planning Processes
Resource Planning
“… determining what
1. Resource requirements
2. Historical information
physical resources
3. Scope statement
(people, equipment,
4. Resource pool description
materials) and what
5. Organizational policies
quantities of each should
be used to perform project activities.”
Tools and Techniques
1. Expert judgment 2. Alternatives identification
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Core Planning Processes
Cost Estimating
“… developing an
1. Cost estimates
2. Resource requirements
approximation (estimate of the
2. Supporting detail
3. Resource rates
costs of the resources needed
4. Activity duration estimates
to complete project activities.”
3. Cost management plan
5. Historical information 6. Chart of accounts
Tools and Techniques
1. Analogous estimating 2. Parametric modeling 3. Bottom-up estimating 4. Computerized tools
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Core Planning Processes
Cost Budgeting
1. Cost estimates
“… allocating the overall cost
1. Cost baseline
2. WBS
estimates to individual work
3. Project schedule
items in order to establish a cost baseline for measuring project performance.”
Tools and Techniques
1. Analogous estimating 2. Parametric modeling 3. Bottom-up estimating 4. Computerized tools
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Core Planning Processes
Project Plan Development
1. Other planning outputs
“… taking the results of other
1. Project plan
2. Historical information
planning processes and putting
2. Supporting detail
3. Organizational policies
them into a consistent,
4. Constraints
coherent document.”
5. Assumptions
Tools and Techniques
1. Project planning methodology
2. Stakeholder’s skills and knowledge 3. Project management information systems
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Executing Processes
Closing Processes
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Purpose
To coordinate, integrate, and manage all resources
Why?
in order to achieve the project objectives
How?
by carrying out the letter and intent of the project plan
While
responding to change and mitigating risks
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Overview
Executing Processes
4.2 Project Plan Execution
Facilitating Processes
From the
Planning
Team 9.3 Processes Distribution Controlling Information Development (Figure 3–7)
Assurance Quality
To the
(Figure 3–5) Processes
5.4 Scope Verification
12.3 Solicitation
Source 12.4
From the
Selection
(Figure 3–7) Processes Controlling
Administration Contract
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Core Execution Process
Project Plan Execution
1. Project plan
“… the primary process for
1. Work results
2. Supporting detail
carrying out the project plan.”
2. Change requests
3. Organizational policies 4. Corrective action
Tools and Techniques
1. General management skills 2. Product skills and knowledge 3. Work authorization system 4. Status review meetings 5. Project management
information system 6. Organizational procedures
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Facilitating Execution Processes
Information distribution Team development Quality assurance Scope verification Solicitation Source selection Contract administration
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Sample Executing Activities
Managing work results and requests for change Using tools and techniques in project plan implementation Building effective relationships with vendors and project team members Choosing from potential sellers Distributing status information in time for stakeholders to act Other?
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Unit 6: Controlling Projects
Upon completion, you will be able to …
Describe the purposes of the controlling processes Identify the inputs and outputs of the core controlling processes List and define the major tools and techniques
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Controlling Processes
Closing Processes
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Purpose
To keep the project on track in order to achieve its objectives as outlined in the project plan by:
Monitoring and reporting variances Controlling scope changes Controlling schedule changes Controlling costs Controlling quality Responding to risks
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Overview
Controlling Processes
Change Control
Facilitating Processes
To the Planning
From the Executing
5.5 (Figure 3–5) Processes
(Figure 3–6) Processes
Scope Change
Control
Control Schedule
Control Cost
11.4 Control Quality 8.3 Risk Response Control
Closing To the Processes (Figure 3–8)
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Core Controlling Processes
Performance Reporting
1. Project plan
“… collecting and disseminating
1. Performance reports
2. Work results
performance information. This
2. Change requests
3. Other project records
includes status reporting, progress measurements, and forecasting.”
Tools and Techniques
1. Performance reviews 2. Variance analysis 3. Trend analysis 4. Earned value analysis 5. Information distribution
systems
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Core Controlling Processes Overall Change Control
1. Project plan
“Overall change control is
1. Project plan updates
2. Performance reports
concerned with:
2. Corrective action
3. Change requests
(a) influencing the factors which
create change to ensure that
3. Lessons learned
changes are beneficial, (b) determining that a change has occurred, and (c) managing the actual change when and as they occur.”
Tools and Techniques
1. Change control system 2. Configuration management 3. Performance measurement 4. Additional planning 5. Project management
information systems
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Facilitating Controlling Processes
Scope change control Quality control Schedule control Cost control Risk response control
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Facilitating Controlling Processes
Risk Response Control
1. Risk management plan
“… involves executing the Risk
1. Corrective action
2. Actual risk events
Management Plan in order to
2. Updates to the risk
3. Additional risk identification
respond to risk events over the
management plan
course of the project.”
Tools and Techniques
1. Workarounds 2. Additional risk response
development
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Key Cost Concept
Earned Value
A method for measuring project performance The budgeted cost of work performed for an activity or group of activities Compares the planned amount of work with the accomplished amount of
work to determine if cost and scheduled performance is as planned
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Controlling Activities
Reporting status versus plan and forecasting Responding to changes in risk Completing and settling the contract, including resolving of any open items Identifying and reporting schedule slips Determining whether schedule updates require plan modifications Other?
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Unit 7: Closing Projects
Upon completion, you will be able to …
Describe the purposes of closing processes Identify the inputs and outputs of the core processes List the major tools and techniques
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Closing Processes
Closing Processes
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Purpose
Formalizing acceptance of the project and bringing it to an orderly end by:
Closing the contract Achieving administrative closure
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Overview
Closing Processes
From the
Controlling Administrative
Contract
Processes Closure (Figure 3–7)
Close-out
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Core Closing Processes
Contract Close-out
1. Contract documentation
“… involves both product
1. Contract file
verification (was all work
2. Formal acceptance and
completed correctly and
closure
satisfactorily) and administrative close-out (updating of records to reflect final results and archiving of such information for future use.”
Tools and Techniques
1. Procurement audits
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Core Closing Process
Administrative Closure
1. Performance measurement
“… verifying and documenting
1. Project archives
documentation
project results to formalize
2. Formal acceptance
2. Documentation of the
acceptance of the product by
product of the project
the sponsor, client or
3. Lessons learned
3. Other project records
customer.”
Tools and Techniques
1. Performance reporting tools and techniques
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Sample Closing Activities
Ensuring a record of lessons learned is developed, documented, and made available for future projects
Verifying acceptance of products or services Collecting all required project records Determining if final products meet specifications Assessing the quality, correctness, and completeness of all formal project
acceptance documents Give performance appraisals and assist in the planned transfer of
personnel to other projects or positions Other?
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Functional Organization
Executive Project Coordination
(Black boxes represent staff engaged in project activities.)
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Functional Organization
Discussion Question
In your opinion, what advantages and potential disadvantage does this type of organizational structure foster?
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Functional Organization
Potential Advantages
Clear reporting relationships Highly specialized expertise Homogeneous group Drive for technical excellence
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Functional Organization
Potential Issues
Project boundaries limited to discipline Barrier to customer influence and satisfaction Employee development opportunities limited Project manager dependent on personal influence Hierarchical decision and communication processes Overwork technical issues versus build to standard Fosters part-time roles
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Strong Matrix
Chief Executive
Manager of
Project Managers
Project Manager
Project Manager
Project Manager
(Black boxes represent staff engaged in project activities.)
Project Coordination
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Projectized Organization
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Projectized Organization
Discussion Question
Based on your experience, what potential advantages and disadvantage does this type of organizational approach foster?
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
An Example of Project Org.
General Manager
Project A
Project B
Project C
Manager
Manager
Manager
Design Manuf.
Design Manuf.
Design Manuf.
Project-Based Organization
Potential Advantages
Strong project manager role Full-time administrative staff Clear accountability Fosters co-location Improved focus Cost and performance tracking Decision-making Customer relationships Common processes
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Project-Based Organization
Potential Issues
Lessening of employee’s “profession” identity Reduced focus on technical competence Leadership by the nontechnically skilled Focus on administrative work versus technical Devaluing of functional managers Process versus deliverable emphasis
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
Structure Influence on Projects
Copyright © 1999 Project Management Institute, Inc. All Rights Reserved.
173