Contoh format RAB FORMAT RENCANA ANGGARA

Contoh format RAB
FORMAT RENCANA ANGGARAN BIAYA BIDANG EKONOMI
RENCANA ANGGARAN BIAYA
Kota
: Kediri
Kecamatan: .......................
Kelurahan : .......................
No

URAIAN

(1)
1

(2)
BAHAN
1. ...................
2. ...................
3.   ...................
4.   ...................
5.   dst.


2

ALAT BANTU
1. ....................
2. dst

Jenis Kegiatan : Ekonomi
Volume
: .....................
Lokasi RT
: .....................
Satuan

Volume

(3)

(4)


Harga Satuan
(Rp)
(5)

Total Biaya
(6) = (4) x (5)

Sub Total Upah (1)

Sub Total Bahan (2)
Jumlah Total Biaya (1+2)

Disusun oleh :
Kepala Seksi Ekonomi dan
Pembangunan
Kelurahan.................................

Pendamping

(.........................................................

)

(..........................................................
..)

Mengetahui
Lurah ................................................

(..................................................................
)
NIP. ......................................................

FORMAT RENCANA ANGGARAN BIAYA BIDANG SOSIAL
RENCANA ANGGARAN BIAYA
Kota
: Kediri
Kecamatan: .......................
Kelurahan : .......................
No


URAIAN

(1)
1

(2)
BAHAN
1. ...................
2. ...................
3.   ...................
4.   ...................
5.   dst.

2

ALAT BANTU
1. ....................
2. dst

Jenis Kegiatan : Sosial

Volume
: .....................
Lokasi RT
: .....................
Satuan

Volume

(3)

(4)

Harga Satuan
(Rp)
(5)

Total Biaya
(6) = (4) x (5)

Sub Total Upah (1)


Sub Total Bahan (2)
Jumlah Total Biaya (1+2)

Disusun oleh :
Kepala Seksi Ekonomi dan
Pembangunan
Kelurahan.................................

(.........................................................
)

Pendamping

(..........................................................
..)

Mengetahui
Lurah ................................................


(..................................................................)
NIP. ...........................................................

Opsi 1 *)
 FORMAT RENCANA ANGGARAN BIAYA  BIDANG INFRASTRUKTUR
RENCANA ANGGARAN BIAYA
Kota
: Kediri
Kecamatan: .......................
Kelurahan : .......................
No
(1)
1

URAIAN
(2)
UPAH KERJA
1. Tukang
2. Pekerja


Jenis Kegiatan : Infrastruktur
Volume
: .....................
Lokasi RT
: .....................
Satuan

Volume

(3)

(4)

Harga Satuan
(Rp)
(5)

Total Biaya
(6) = (4) x (5)


HOK
HOK
Sub Total Upah (1)

2

BAHAN
1. Semen 50 kg
2. Pasir beton
3. Agregat Kasar
4. Agregat Halus
5. Wermes
6. dst

Zak
M3
M3
M3
roll
Sub Total Bahan (2)


3

ALAT BANTU
1. Alat
 
(lungsum)
2. dst

Bantu

LS
Sub Total Alat (3)
Jumlah Total Biaya (1+2+3)

Disusun oleh :
Kepala Seksi Ekonomi dan
Pembangunan
Kelurahan.................................


(.........................................................
)

Pendamping

(..........................................................
..)

Mengetahui
Lurah ................................................

(..................................................................)
NIP. ...........................................................

Opsi 2 *)
 FORMAT RENCANA ANGGARAN BIAYA  BIDANG INFRASTRUKTUR
RENCANA ANGGARAN BIAYA
Kota

:

Kediri

Jenis
Kegiatan

: Infrastruktur (Jalan Paving)

Kelurahan

:

...........

Volume

: ........m2

Kecamatan

:

...........

RT

: ..........

NO.

URAIAN PEKERJAAN

1

2

NOMOR
ANALISA
3

VOLUME

SAT.

4

5

I.

ALAT

1

Cangkul

3

bh

2

Sekop

3

bh

3

Palu besar/bodem

2

bh

4

Timba Kecil

6

bh

HARGA

JUMLAH

SATUAN (Rp.)

(Rp.)

6

7
80.0
00
80.0
00
47.0
00
6.0
00

Jumlah Sub I

240.000,00
240.000,00
94.000,00
36.000,00
610.000,00

II.

PEKERJAAN TANAH

1

Menggali tanah biasa

B6.1

2

Mengurug pasir urug

3

Membuang Tanah

25,00

m3

31.500,00

787.500,00

B6.11

5,00

m3

72.600,00

363.000,00

B6.8

25,00

m3

13.800,00

345.000,00

Jumlah Sub II

1.495.500,00

III.

PEKERJAAN PASANGAN

1

Pasang dinding bata merah t= 1/2 bata, 1 PC : 4 PP

D6.11

60,00

m2

73.800,00

4.428.000,00

2

Pasang plesteran 1 PC : 5 PP, tebal 15 mm

E6.5

60,00

m2

32.300,00

1.938.000,00

3

Memasang 1 m2 paving blok abu-abu hexagonal

Ls.3a

250,00

m2

61.200,00

15.300.000,00
21.666.000,0
0
23.771.500,0
0
23.771.000,0

Jumlah Sub III
JUMLAH I+II+III
DIBULATKAN

0

CATATAN :
Yang Harus Tertuang di dalam RAB dan sebagai Acuan
dalam Penyusunan RKA
(tidak bisa dirubah ketika dalam pelaksanaan kegiatan):





Judul / Jenis Kegiatan
Lokasi
Volume
Anggaran / Nilai / Biaya

*) Pilih salah satu format penyusunan RAB INFRASTRUKTUR dari
2 OPSI diatas.