Ses2.02 JCM project development process in Indonesia

JCM project development
process in Indonesia
Keni Atika
Indonesia JCM Secretariat

1

Basic concept of the JCM







The Joint Crediting Mechanism as a G-to-G scheme which encourages private sector organizations
to invest in Low Carbon Development activities in Indonesia through incentive from the
Government of Japan.
JCM cooperation is not only conducted by Japan and Indonesia, but also with other 16 developing
countries.
Bilateral Cooperation on the Joint Crediting Mechanism for the Low Carbon Growth Partnership

between the Republic of Indonesia and Japan has been signed by the Coordinating Minister for
Economic Affairs of Indonesia and Minister for Foreign Affairs of Japan.
Objectives of the JCM:
1.Facillitate diffusion of leading low carbon technologies, products, systems, services, and
infrastructure as well as implementation of mitigation actions, and contributing to sustainable
development of developing countries.
2. Evaluate contributions to GHG emission reductions/removals from developed countries in a
quantitative manner, through mitigation actions implemented in developing countries and use
those emission reductions or removals to achieve emission reduction targets of the developed
countries.
3. Contribute to the ultimate objective of the UNFCCC by facilitating global actions for emission2
reductions or removals.

JCM Scheme
Japan
Government
Issuance of credit

Notifies
registration

of projects
Report
issuance
of credits

Joint Committee
Japanese
Indonesian
Side communication Side

Request
issuance of
credits

Implementation &
monitoring of
projects

Report
issuance

of credits

Request
issuance of
credits

• Validate projects

Inform results
of validation /
verification

Issuance of credit

Request registration of
projects

Third Party Entities
Submit PDD /
monitoring

report

Indonesia
Government

Secretariat

Request registration of
projects

Project Participants

Notifies
registration
of projects

• Verify amount of
GHG emission
reduction or removal


Submit PDD /
monitoring
report

Inform results
of validation /
verification

Implement project together
May contact TPE and Secretariat through one Contact Entity

Project Participants
Implementation &
monitoring of
projects
3

3

From FS to Project


use PIN (Project Idea Note) to submit application
(recommended)

Exact procedures described
in application guidelines of
respective schemes should
be referred to.

FS Participant Candidates
apply for FS support scheme

METI/NEDO or
MOE Japan
approved

not approved

FS implementation (1 study or more)


No support for
FS(*)

Feasible

Not feasible

Apply for subsidy or
entrustment(**)

Not apply(*)

METI/NEDO or
MOE Japan
approved

JCM Project with subsidy or
entrustment

need further study


No
implementation
as JCM project

(*)except for FS
reapplication
not approved

No subsidy or
Entrustment(*)

(**)PP candidate may
apply without conducting
4
FS

From FS to Project
Since JCM bilateral agreement in 2013, several guidelines, procedure,
rules, registry system and methodologies have been developed


2.
3.
4.

5.

ISO 14065 based

1.

Guideline:
Project Design
Document
Proposed
Methodology
Third Party Entity
Validation and
Verification
Sustainable

Development
Implementation Plan
and Report

Rules: 1. Rules of Implementation
2. Rules of Procedure for JC
Procedure: Project Cycle Procedure
Methodologies:
10 methodologies in energy
conservation sectors have been
developed
Registry system:
We have developed the first climate change
mitigation registry system in Indonesia, and it is
expected to connect with the National Registry
5

Steps in the JCM
Project Participant / Each Government
Joint Committee


Submission of
Proposed
Methodology

Can be conducted by the same TPE
Can be conducted simultaneously

Measurable
Joint Committee

Approval of
Proposed
Methodology

Project Participant

Development
of PDD*

Third Party Entities

Validation

Joint Committee

Registration

Project Participant

Monitoring

Third Party Entities

Verification

Joint Committee decides the amount
Each Government issues the credit

Issuance
of credits

Reportable

Verifiable
6
*PDD: Project Design Document

JCM Project In Practice :
Start of Project
Start of project (i.e
design, procurement,
etc)

Technology
Implementation &
Registration

Verification by
TPE

Credit
issuance

Submission & validation of PDD

Secretariat ay: “Monitor the development of JCM related programs and
implementation of JCM projects, taking into account sustainable development criteria
a d e vi o e tal i teg ity.
(JCM Rule of Implementation Para 14 point (a) article (iii))
Through:
• Meetings
o The Embassy of Japan and Indonesia JCM Secretariat will arrange individual
meeting with project participants from both sides.
o The schedule will be arranged in accordance with Japanese participa t’s
visiting schedule.
• JCM Secretariat involvement (if needed)
o If requested, or when obstacles occur (such as location finding or related to
government systems, the Secretariat should be informed).
7

JCM Project in Practice: Submission
of PDD
Start of project (i.e
design, procurement,
etc)

Technology
Implementation &
Registration

Verification by
TPE

Credit
issuance

Submission & Validation of PDD

• Project Validation
Project participants: Prepare a draft PDD and submit the draft to a third-party entity
for validation and notify the Joint Committee through the JCM secretariat
(JCM Rule of Implementation Para 19 Point (b))
(note: PDD = Project Design Document)
Inform of public input

Project Participant (PP)

- TPE validate PDD
- TPE receive and check the
completeness of implementation plan

Indonesia JCM
Secretariat

Indonesia Joint
Committe

Submission
of validation
report by PP
8
Submit PDD for public input

JCM Project in Practice:
Technology Implementation
Start of project (i.e
design, procurement,
etc)

Technology
Impementation &
Registration

Verification by
TPE

Credit
issuance

Submission & validation of PDD

• Site visit after project operation
Monitor the development of JCM related programs and implementation of JCM
projects, taking into account sustainable development criteria and environmental
integrity. (JCM Rule of Implementation Para 14 point (a) article (iii))
o At least one site visit by the Indonesia JCM Secretariat (if possible, also by
the Japanese side).
o The purpose of site visit is to receive feedbacks from the Indonesian side and
to witness and confirm the technology implementation.
o If needed, more site visit may be conducted (as agreed by project
participant(s) and government side)
9

JCM Project in Practice:
Technology Implementation
Start of project (i.e
design, procurement,
etc)

Technology
Impementation &
Registration

Verification by
TPE

Credit
issuance

Submission & validation of PDD

• Registration
a project is fully acknowledged as a JCM project once it is being registered

Validation
Report
Validated
PDD &
MoC

Positively
Reviewed
SDIP
Joint
Committee

• Project has no potential
negative impacts
• Appropriate action plan is
properly described

voluntary process
10

JCM Project in Practice: Credit issuance
Start of project (i.e
design, procurement,
etc)

Technology
Implementation &
Registration

Verification by
TPE

Credit
issuance

Submission & validation of PDD

• Sustainable Development Implementation Report (SDIR)

•Submission of SDIR is currently a voluntary process, but it will be part of JCM Rules of
Implementation in the future
• Positive result of SDIR: No negative impacts or appropriate description on the corrective action
Project Participants
submission
Re-submission (within 60 days)
 Ex-post evaluation of
the contribution to
Notify the receipt of Secretariat
SD using SDIR form
the request  Completeness check [7 days]
 Local and/or national
(secretariat)
regulations must be
followed
Joint Committee
Notify the result
 Evaluation of SDIR [20 days],
including on-site visit where
necessary
 Evaluation of revised SDIR: 10 days
Positive result: to
next step

Negative result: revision of SDIR

11

JCM Project in Practice:
Verification by TPE
Start of project (i.e
design, procurement,
etc)

Technology
Implementation &
Registration

Verification by
TPE

Credit
issuance

Submission & validation of PDD

JCM Rule of Implementation Para 31 to 33
Project participants
 Conduct monitoring
 Prepare a monitoring report
*PDD Monitoring and Guidelines
*Monitoring Report Sheet

1. Submit
to TPE

TPE
 Verify emission reduction
 Prepare a verification report
* Validation and Verification
guidelines
* Verification report form

2. Submit report to
project participants
3. Next step: request for credit issuance to Secretariat

Secretariat

The TPE des i es all do u e tatio suppo ti g ve ifi atio a d akes su h do u e tatio
availa le to the Joi t Co
ittee upo e uest. (JCM Guideli es fo Ve ifi atio a d Validatio Pa a
128)
• All of data obtained by TPE which support verification process may be shared to Joint Committee

12

JCM Project in Practice: Credit issuance
Start of project (i.e
design, procurement,
etc)

Technology
Implementation &
Registration

Verification by
TPE

Credit
issuance

Submission & validation of PDD

• Request issuance of credits

O the asis of a e uest fo otifi atio to ea h side fo issua e of edits su itted y
project participants, the Joint Committee notifies both sides to issue the credits which
were verified by the third-party entities. (JCM Rule of Implementation Para 10)

Project Participants
Request for notification for issuance
 Determine allocation
of credits
Notify the receipt of Secretariat
 Complete a credit
the request  Completeness check
issuance request
[7 days] (secretariat)
form
* Credit issuance request
Joint Committee
form
Notify the result
 Decision on
notification of
amount of credits to
be issued
Notify the issuance

Notify the amount of credits
to be issued

Government
 Issuance of credits 13

Validation and verification with TPE
• TPE are selected by the project participants to validate and/or
verify their PDD and/or emission reductions.
• Requirements/Eligibility:
– Candidate entities are either:
(a) Accredited under ISO 14065; or
(b) Designated Operational Entities (DOEs) under the UNFCCC
CDM
– Candidate entities have sufficient knowledge of the JCM
between the Republic of Indonesia and Japan by reading and
knowing all applicable rules and guidelines of the JCM.

• Eligible entities can apply as TPE for JCM in each host country
separately
– Candidate entity submit application form and related document stated
in Guideline for TPE to JCM Secretariat of Japan and Indonesia
([email protected] and [email protected] )
14

List of TPE in Indonesia
TPE
Lloyd’s Register Quality
Assurance Limited (LRQA)
Japan Quality Assurance
Organization (JQA)
Japan Management
Association (JMA)
TÜV SÜD South Asia Private
Limited (TÜV SÜD)
Deloitte Tohmatsu Evaluation
and Certification Organization
Co., Ltd.
TÜV Rheinland (China) Ltd.

EPIC Sustainability Services
Private Limited (India)

Accreditation
JCM Sectoral Scope
CDM
(for Validation and Verification) ISO 14065
DOE
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12,
Yes
Yes
13
1, 3, 4, 5, 9, 10, 13, 14

Yes

Yes

1, 2, 3, 4, 6, 8, 9, 14

Yes

Yes

1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12,
13, 14, 15

No

Yes

1, 2, 3, 4, 5, 8, 10, 12, 13, 15

No

Yes

No

Yes

No

Yes

1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12,
13, 14, 15
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11,
13, 14, 15

KBS Certification Services Pvt.
Ltd. (India)

1, 3, 4 ,5, 6, 7, 9, 10, 11, 13, 15

No

Yes

PT Mutu Agung Lestari

1, 2, 3, 14, 15
Provisionally designated: 4, 13

Yes

No

ERM Certification and
Verification Services Ltd

1, 2, 3, 4, 5, 8, 9, 10, 13, 15

No

Yes

Sectoral Scope
1. Energy Industries
(renewable/non-renewable
sources);
2. Energy Distribution;
3. Energy Demand;
4. Manufacture Industries;
5. Chemical Industries;
6. Construction;
7. Transport;
8. Mining/Mineral Production;
9. Metal Production;
10. Fugitive emissions from fuel
(solid, oil and gas);
11. Fugitive emissions from
production and consumption of
halocarbons and sulfur
hexafluoride;
12. Solvent Use
13. Waste handling and disposal
14. Reducing emissions from
Deforestation and Forest
Degradation in developing
countries; and the role of
conservation, sustainable
management of forest and
forest carbon stocks in
developing countries (REDDplus),
15
15. Agriculture.

Thank you! Terima kasih!