Penulangan Plat Lantai PLAT

commit to user Tugas Akhir Perencanaan Struktur dan Rencana Anggaran Biaya Gedung Kuliah 2 Lantai BAB 5 Plat Lantai 125 1,0 4,00 4,00 Lx Ly = = Mlx = 0,001.qu . Lx 2 . x = 0.001. 893,2. 4,0 2 .21 = 179,96 kg m Mly = 0,001.qu . Lx 2 . x = 0.001. 893,2. 4,0 2 .26 = 222,81 kg m Mtx = - 0,001.qu . Lx 2 . x = - 0.001 .893,2. 4,0 2 .55 = - 471,33 kg m Mty = - 0,001.qu . Lx 2 . x = - 0.001 . 893,2. 4,0 2 .60 = - 514,18 kg m

5.4. Penulangan Plat Lantai

Tabel 5.1. Perhitungan Plat Lantai Tipe Plat LyLx m Mlx kgm Mly kgm Mtx kgm Mty kgm A1 2,252,25 = 1,0 126,61 126,61 -307,48 -307,48 A2 4,002,25 = 1,8 230,61 99,48 -479,31 -352,70 A3 4,002,25 = 1,8 334,62 185,39 - -520,01 A4 4,002,25 = 1,8 180,87 58,78 -370,79 -257,74 A5 4,002,25 = 1,8 262,27 90,44 538,10 - B1 3,002,25 = 1,4 180,87 122,09 -402,44 -334,62 B2 3,003,00 = 1,0 168,81 168,81 -418,02 -418,02 B3 3,003,00 = 1,0 168,81 209,01 -442,13 -488,33 B4 4,002,00 = 2,0 196,50 75,03 -407,30 -278,68 B5 4,002,00 = 2,0 146,48 42,83 -296,54 -203,65 C1 4,004,00 = 1,0 528,77 443,03 -1200,46 - C2 4,004,00 = 1,0 300,12 300,12 -743,14 -743,14 D1 4,004,00 = 1,0 239,95 239,95 -582,73 -582,73 D2 4,004,00 = 1,0 179,96 222,81 -471,33 -514,18 Dari perhitungan momen diambil momen terbesar yaitu: Mlx = 528,77 kgm Mly = 443,03 kgm Mtx = Mty = - 1200,46 kgm commit to user Tugas Akhir Perencanaan Struktur dan Rencana Anggaran Biaya Gedung Kuliah 2 Lantai BAB 5 Plat Lantai 126 Data – data plat : Tebal plat h = 12 cm = 120 mm Diameter tulangan ∅ = 10 mm fy = 240 MPa f’c = 25 MPa b = 1000 mm p = 20 mm Tebal penutup d’ = p + ½ ∅ tul = 20 + 5 = 25 mm Tinggi Efektif d = h - d’ = 120 – 25 = 95 mm Tingi efektif Gambar 5.16 Perencanaan Tinggi Efektif dx = h – p - ½Ø = 120 – 20 – 5 = 95 mm dy = h – d’ – Ø - ½ Ø = 120 – 20 - 10 - ½ . 10 = 85 mm ρb = ⎟⎟⎠ ⎞ ⎜⎜⎝ ⎛ + fy fy fc 600 600 . . . 85 , β = ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ + 240 600 600 . 85 , . 240 25 . 85 , = 0,0538 h d y d x d commit to user Tugas Akhir Perencanaan Struktur dan Rencana Anggaran Biaya Gedung Kuliah 2 Lantai BAB 5 Plat Lantai 127 ρ max = 0,75 . ρb = 0,75 . 0,05376 = 0,0403 ρ min = 0,0025 5.5. Penulangan tumpuan arah x Mu = 1200,46 kgm = 12,0046.10 6 Nmm Mn = φ Mu = = 8 , 10 . 12,0046 6 15,0056.10 6 Nmm Rn = = 2 .dx b Mn = 2 6 95 . 1000 10 . 15,0056 1,663 Nmm 2 m = 294 , 11 25 . 85 , 240 . 85 , = = c f fy ρ perlu = ⎟⎟⎠ ⎞ ⎜⎜⎝ ⎛ − − fy Rn . m 2 1 1 . m 1 = . 294 , 11 1 ⎟⎟⎠ ⎞ ⎜⎜⎝ ⎛ − − 240 663 , 1 . 294 , 11 . 2 1 1 = 0,0072 ρ ρ max ρ ρ min , di pakai ρ perlu = 0,0072 As perlu = ρ perlu . b . dx = 0,0072 . 1000 . 95 = 686,38 mm 2 Digunakan tulangan ∅ 10 As = ¼ . π . 10 2 = 78,5 mm 2 S = perlu As b As. = 38 , 686 1000 . 5 , 78 = 114,368 ~ 120 mm commit to user Tugas Akhir Perencanaan Struktur dan Rencana Anggaran Biaya Gedung Kuliah 2 Lantai BAB 5 Plat Lantai 128 n = s b = 120 1000 = 8,33 ~ 9 As yang timbul = 9. ¼ . π . 10 2 = 706,5 mm 2 As perlu 686,38…..…ok Dipakai tulangan ∅ 10 – 120 mm

5.6. Penulangan tumpuan arah y