Lampiran 4
FORMULIR STANDAR UNTUK PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP KAB KODYA :
ITEM PEMBAYARAN NO. : 7.1
3 PERKIRAAN VOL. PEK.
71.30 JENIS PEKERJAAN
: Beton K-350 TOTAL HARGA Rp.
33,042,007.14 SATUAN PEMBAYARAN
: M3 THD. BIAYA PROYEK
0.79
PERKIRAAN HARGA
JUMLAH NO. KOMPONEN SATUAN
KUANTITAS SATUAN
HARGA Rp.
Rp A.
TENAGA
1. Pekerja L01
jam 5.3012 1,800.00
9,542.17 2. Tukang
L02 jam
1.7671 2,500.00 4,417.67
3. Mandor L03
jam 0.4418 2,750.00
1,214.86 JUMLAH HARGA
TENAGA 15,174.70
B. BAHAN
1. Semen M12
Kg 384.3750
575.00 221,015.63
2. Pasir M01 M3
0.4271 33,800.00 14,435.42
3. Agregat Kasar
M03 M3
0.6406 57,676.45
36,948.97 4.
Kayu Perancah
M19 M3 0.1500
650,000.00 97,500.00
5. Paku M18
Kg 1.5000 4,000.00
6,000.00 JUMLAH HARGA
BAHAN 375,900.02
C. PERALATAN
1. Conc. Mixer
E06 jam
0.4418 12,290.01
5,429.32 2.
Water Tanker E23
jam 0.0521
29,327.95 1,527.96
3. Con. Vibrator
E20 jam
0.4418 7,304.22
3,226.76 4.
Con, Pump E28
jam 0.4418
43,991.98 19,434.21
5. Alat Bantu
Ls 1.0000
600.00 600.00
JUMLAH HARGA PERALATAN 30,218.25
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN A + B + C
421,292.97 E.
OVERHEAD PROFIT 10.0 x D
42,129.30 F.
HARGA SATUAN PEKERJAAN D + E 463,422.26
Universitas Kristen Maranatha
Lampiran 5
FORMULIR STANDAR UNTUK PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP KAB KODYA :
ITEM PEMBAYARAN NO. : 7.1
5 PERKIRAAN VOL. PEK.
71.50 JENIS PEKERJAAN
: Beton K-250 TOTAL HARGA Rp.
27,602,370.51 SATUAN PEMBAYARAN
: M3 THD. BIAYA PROYEK
0.66
PERKIRAAN HARGA
JUMLAH NO. KOMPONEN SATUAN
KUANTITAS SATUAN
HARGA Rp.
Rp A.
TENAGA
1. Pekerja Biasa
L01 jam
5.3012 1,800.00
9,542.17 2. Tukang
L02 jam
1.7671 2,500.00 4,417.67
3. Mandor L03
jam 0.4418 2,750.00
1,214.86 JUMLAH HARGA
TENAGA 15,174.70
B. BAHAN
1. Semen M12
Kg 354.8077
575.00 204,014.42
2. Pasir M01 M3
0.4435 33,800.00 14,990.63
3. Agregat Kasar
M03 M3
0.6406 57,676.45
36,948.97 4.
Kayu Perancah
M19 M3 0.1000
650,000.00 65,000.00
5. Paku M18
Kg 1.0000 4,000.00
4,000.00 JUMLAH HARGA
BAHAN 324,954.02
C. PERALATAN
1. Conc. Mixer
E06 jam
0.4418 12,290.01
5,429.32 2.
Water Tanker E23
jam 0.0534
29,327.95 1,567.14
3. Con. Vibrator
E20 jam
0.4418 7,304.22
3,226.76 4. Alat
Bantu Ls
1.0000 600.00
600.00
JUMLAH HARGA PERALATAN 10,823.22
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN A + B + C
350,951.94 E.
OVERHEAD PROFIT 10.0 x D
35,095.19 F.
HARGA SATUAN PEKERJAAN D + E 386,047.14
Universitas Kristen Maranatha
Lampiran 6
FORMULIR STANDAR UNTUK PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP KAB KODYA :
ITEM PEMBAYARAN NO. : 7.1
6 PERKIRAAN VOL. PEK.
71.60 JENIS PEKERJAAN
: Beton K-175 TOTAL HARGA Rp.
24,723,011.74 SATUAN PEMBAYARAN
: M3 THD. BIAYA PROYEK
0.59
PERKIRAAN HARGA
JUMLAH NO. KOMPONEN SATUAN
KUANTITAS SATUAN
HARGA Rp.
Rp A.
TENAGA
1. Pekerja L01
jam 5.3012 1,800.00
9,542.17 2. Tukang
L02 jam
1.7671 2,500.00 4,417.67
3. Mandor L03
jam 0.4418 2,750.00
1,214.86 JUMLAH HARGA TENAGA
15,174.70 B.
BAHAN
1. Semen M12
Kg 318.1034
575.00 182,909.48
2. Pasir M01 M3
0.3976 33,800.00 13,439.87
3. Agregat Kasar
M03 M3
0.7069 57,676.45
40,771.28 4.
Kayu Perancah
M19 M3 0.0750
650,000.00 48,750.00
5. Paku M18
Kg 0.5000 4,000.00
2,000.00 JUMLAH HARGA BAHAN
287,870.64 C.
PERALATAN
1. Conc. Mixer
E06 jam
0.4418 12,290.01
5,429.32 2.
Water Tanker E23
jam 0.0546
29,327.95 1,601.72
3. Con. Vibrator
E20 jam
0.4418 7,304.22
3,226.76 4. Alat
Bantu Ls
1.0000 600.00
600.00
JUMLAH HARGA PERALATAN 10,857.81
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN A + B + C