GENERAL ARRANGEMENT MT “SAFINA SYUMADHANI” Tanker 3600 BRT
TUGAS AKHIR
PROGRAM STUDI D III TEKNIK PERKAPALAN PROGRAM DIPLOMA FAKULTAS TEKNIK
UNIVERSITAS DIPONEGORO SEMARANG ANDHIKA ADI. S
L0G006007 III
- 29
= 9,6 x 13,41 x 6,9
= 888,2784 m
3
f. Volume Tangki Muat I Tanki muat I terletak pada frame 136–frame152 dengan jarak 9,6 m.
P = 9,6
L = 13,41
T = 6,9
Volume Tangki Muat I =
P x L x T =
9,6 x 13,41 x 6,9 =
888,2784 m
3
Volume Tangki Muat total = TM I + TM II + TM III + TM IV + TM V + TM VI
= 888,2784 + 888,2784 + 888,2784 + 888,2784 + 888,2784 + 888,2784 = 5329,6704 m
3
Koreksi Volume Muatan Volume Tanki Muat Rencana Volume Muatan Perhitungan Awal
5329,4704 m
3
5306,0091 m
3
= 100
x n
Perencanaa Volume
n Perhitunga
Volume n
Perencanaa Volume
-
=
100 5329,4704
0091 ,
5306 4704
, 5329
-
= 0,44 0,5 memenuhi
5. Perhitungan Volume Tanki-Tanki Lain
1. PerhitunganVolume Tanki Minyak Lumas Volume Tanki Minyak Lumas
Perhitungan tangki minyak pelumasan direncanakan terletak pada Kamar Mesin dengan panjang
Tanki Minyak Pelumas p
= 2,4 m l
= 1,8 m t
= 1,2 m
GENERAL ARRANGEMENT MT “SAFINA SYUMADHANI” Tanker 3600 BRT
TUGAS AKHIR
PROGRAM STUDI D III TEKNIK PERKAPALAN PROGRAM DIPLOMA FAKULTAS TEKNIK
UNIVERSITAS DIPONEGORO SEMARANG ANDHIKA ADI. S
L0G006007 III
- 30
Volume Tanki Minyak Lumas = p x l x t = 2,4 x 1,8 x 1,2
= 5,184 m
3.
Koreksi Perhitungan Tanki Minyak pelumas : Vol. Tanki Minyak pelumas Vol. Minyak pelumas yang dibutuhkan
5,184
m
3
3,638
m
3
à
memenuhi
2. Perhitungan Volume Ruang Pompa Frame
Luas FS
Hasil 40
106,330 1
106,330 41
107,771 4
431,084 42
109,155 2
218,310 43
110,453 4
441,812 44
111,634 0,5
55,817 45
112,684 2
225,468 46
113,605 0,5
56,803 S
1535,524 Volume
= k . h . S = 13 x 0,6 x 1535,524
= 307,1047 m
3
3. Perhitungan Volume air tawar Frame
Luas FS
Hasil 46
113,605 1
106,330 47
114,403 4
457,612 48
115,089 1
115,089 S
679,031 Volume
= k . h . S = 13 x 0,3 x 679,031
= 135,8062 m
3
4. Perhitungan Cofferdam I Buritan Frame
Luas FS
Hasil 48
115,089 1
115,089
GENERAL ARRANGEMENT MT “SAFINA SYUMADHANI” Tanker 3600 BRT
TUGAS AKHIR
PROGRAM STUDI D III TEKNIK PERKAPALAN PROGRAM DIPLOMA FAKULTAS TEKNIK
UNIVERSITAS DIPONEGORO SEMARANG ANDHIKA ADI. S
L0G006007 III
- 31
49 115,674
4 462,696
50 116,168
1 116,168
S 693,953
Volume = k . h . S
= 13 x 0,6 x 693,953 = 138,790 m
3
5. Perhitungan Tangki Bahan Bakar Frame
Luas FS
Hasil 50
116,168 1
116,168 51
116,586 4
466,344 52
116,944 1
116,944 S
699,456 Volume
= k . h . S = 13 x 0,6 x 699,456 = 139,891 m
3
Volume Tangki Bahan Bakar = 199,672 m
3
6. Perhitungan Volume Slop Tank Frame
Luas FS
Hasil 52
116,944 1
116,944 53
117,254 4
469,016 54
117,524 1,5
176,286 55
117,762 2
235,524 56
117,973 0,5
58,987 S
1056,757 Volume
= k . h . S = 13 x 0,6 x 1056,757
= 211,3513 m
3
Koreksi volume Slop Tank ± 3 dari volume Tangki Muat =
100 x
Muat Tangki
Volume Tank
Slop Volume
=
100 0252
, 5597
3513 ,
211 x
= 3,77 memenuhi
GENERAL ARRANGEMENT MT “SAFINA SYUMADHANI” Tanker 3600 BRT
TUGAS AKHIR
PROGRAM STUDI D III TEKNIK PERKAPALAN PROGRAM DIPLOMA FAKULTAS TEKNIK
UNIVERSITAS DIPONEGORO SEMARANG ANDHIKA ADI. S
L0G006007 III
- 32
7. Perhitungan Cofferdam II Haluan Frame
Luas FS
Hasil 152
54,324 1
54,324 153
50,353 4
201,412 154
46,369 1
46,369 S
302,105 Volume
= k . h . S = 13 x 0,6 x 302,105
= 60,421 m
3
8. Perhitungan Tangki Ballas Ceruk Buritan Frame
Luas FS
Hasil 1
2,849 1
2,849 2
5,712 4
22,848 3
8,605 2
17,210 4
11,544 4
46,176 5
14,545 2
29,090 6
17,607 4
70,428 7
20,720 2
41,440 8
23,872 4
95,488 9
27,050 1
27,050 S
352,579 Volume
= k . h . S = 13 x 0,6 x 352,579
= 70,5158 m
3
9. Volume Tangki Ballas Ceruk Haluan I Frame
Luas FS
Hasil 154
46,369 1
46,369 155
42,359 4
169,436 156
38,300 2
76,600 157
34,512 4
138,048 158
30,644 2
61,288 159
26,721 4
106,884 160
22,787 2
45,574 161
18,887 4
75,548 162
14,990 2
29,980 163
11,176 4
44,704 164
7,419 2
14,838
GENERAL ARRANGEMENT MT “SAFINA SYUMADHANI” Tanker 3600 BRT
TUGAS AKHIR
PROGRAM STUDI D III TEKNIK PERKAPALAN PROGRAM DIPLOMA FAKULTAS TEKNIK
UNIVERSITAS DIPONEGORO SEMARANG ANDHIKA ADI. S
L0G006007 III
- 33
165 3,701
4 14,804
FP 0,000
1 0,000
S 824,073
Volume’ = k . h . S
= 13 x 0,6 x 824,073 = 164,8146 m
3
Total Volume Tanki Ballas : = V.T.Ballas Ceruk Haluan + V.T.Ballas Ceruk Buritan
= 164,8146 + 70,5158 = 235,3304 m
3
Volume Double Bottom = Double Bottom I + Double Bottom II + Double Bottom III +
Double Bottom IV + Double Bottom V + Double Bottom VI = 96,8054 + 135,5534 + 144,5632 + 144,966 + 144,9792 +
144,1964 = 811,0636 m
3
Volume Tanki Ballast Total = Vol.Ceruk Haluan Buritan + Vol.Doub.Bottom R. Muat
= 235,3304 + 811,0636 = 1046,394 m
3
Berat jenis air laut = 1,025 ton m
3
Berat air ballast = 1046,394 x 1,025
= 1072,554 ton
Koreksi berat air terhadap displacement kapal 10 – 17 =
100 x
nt Displaceme
ballast air
Berat
=
100 677
, 8197
554 ,
1072 x
= 13,08 memenuhi