Perhitungan Volume Double Bottom Ruang Mesin Perencanaan Tangki Muat

GENERAL ARRANGEMENT MT “SAFINA SYUMADHANI” Tanker 3600 BRT TUGAS AKHIR PROGRAM STUDI D III TEKNIK PERKAPALAN PROGRAM DIPLOMA FAKULTAS TEKNIK UNIVERSITAS DIPONEGORO SEMARANG ANDHIKA ADI. S L0G006007 III - 16 9,75 FP 0,142 16,941 0,000 - - - -

3. Perhitungan Volume Double Bottom Ruang Mesin

a. Perhitungan volume double bottom pada Ruang Mesin, Frame 9 – Frame 40 dengan jarak 18,60 m No. Frame Luas FS Hasil 9 4,11 1 4,11 10 4,60 4 18,40 11 5,08 2 10,16 12 5,57 4 22,28 13 6,06 2 12,12 14 6,55 4 26,20 15 7,04 2 14,08 16 7,52 4 30,08 17 8,00 2 16,00 18 8,48 4 33,92 19 8,95 2 17,90 20 9,41 4 37,64 21 9,86 2 19,72 22 10,3 4 41,20 23 10,73 2 21,46 24 11,14 4 44,56 25 11,54 2 23,08 26 11,92 4 47,68 27 12,29 2 24,58 28 12,65 4 50,60 29 13,00 2 26,00 30 13,34 4 53,36 31 13,67 2 27,34 32 14,01 4 56,04 33 14,34 2 28,68 34 14,59 4 58,36 35 14,84 2 29,68 36 15,10 4 60,40 37 15,35 2 30,70 38 15,60 1,5 23,40 39 15,85 2 31,70 40 16,11 0,5 8,05 S 949,485 GENERAL ARRANGEMENT MT “SAFINA SYUMADHANI” Tanker 3600 BRT TUGAS AKHIR PROGRAM STUDI D III TEKNIK PERKAPALAN PROGRAM DIPLOMA FAKULTAS TEKNIK UNIVERSITAS DIPONEGORO SEMARANG ANDHIKA ADI. S L0G006007 III - 17 Volume Double Bottom pada Ruang Mesin = 13 x h x S = 13 x 0,6 x 949,485 = 189,897 m 3 b. Perhitungan Volume ruang mesin Perhitungan Volume Ruang Mesin, Terletak pada Frame 9 – Frame 40. No. Frame Luas FS Hasil 9 27,05 1 27,05 10 30,25 4 121,00 11 33,46 2 66,92 12 36,68 4 146,72 13 39,91 2 79,82 14 43,13 4 172,52 15 46,34 2 92,68 16 49,53 4 198,12 17 52,39 2 104,78 18 55,82 4 223,28 19 58,89 2 117,78 20 61,90 4 247,60 21 64,82 2 129,64 22 67,75 4 271,00 23 70,56 2 141,12 24 73,31 4 293,24 25 75,98 2 151,96 26 78,57 4 314,28 27 81,09 2 162,18 28 83,52 4 334,08 29 85,87 2 171,74 30 88,13 4 352,52 31 90,30 2 180,60 32 92,39 4 369,56 33 94,40 2 188,80 34 96,33 4 385,32 35 98,18 2 196,36 36 99,96 4 399,84 37 101,65 2 203,30 38 103,28 1,5 154,92 39 104,84 2 209,68 40 106,33 0,5 53,165 S 6261,575 GENERAL ARRANGEMENT MT “SAFINA SYUMADHANI” Tanker 3600 BRT TUGAS AKHIR PROGRAM STUDI D III TEKNIK PERKAPALAN PROGRAM DIPLOMA FAKULTAS TEKNIK UNIVERSITAS DIPONEGORO SEMARANG ANDHIKA ADI. S L0G006007 III - 18 Volume Ruang Mesin = 13 x h x S = 13 x 0,6 x 6261,575 = 1252,315 m 3

4. Perencanaan Tangki Muat

a. Perencanaan Double Skin. Menurut Peraturan BKI vol II th. 2006 sec. 24, 3.2, lebar Double Skin untuk kapal diatas 5000 DWT tidak boleh kurang dari : w = 0.5 + DWT 20000 m = 0.5 + 5142,632 20000 w = 0,757 m w min = 1,0 m diambil 1,0 m. b. Lebar Midship setelah Double Skin b’ b’ = B – 2 x w = 15,41 – 2 x 1,0 = 15,41– 2,0 b’ = 13,41 m. c. Luas Midship setelah double bottom dan double skin : Am = b’ x H – h x Cm = 13,41 x 7,9 – 1,0 x 0,98 Am = 90,678 m 3 d. Panjang Tanki Muat. Menurut Peraturan BKI vol. II th. 2006 sec. 24 Tabel 24.1, Panjang tanki muat untuk kapal dengan Longitudinal Bulkhead pada centreline adalah : Lt = bi 4 B + 0,15 x Lpp Dimana : bi = jarak minimum dari sisi kapal sampai sisi luar tanki muat bi = B – b’ 2 = 15,41 – 13,41 2 bi = 1,0 m. Lt = 1,0 61,64 + 0,15 x 99,15 = 16,481 m. GENERAL ARRANGEMENT MT “SAFINA SYUMADHANI” Tanker 3600 BRT TUGAS AKHIR PROGRAM STUDI D III TEKNIK PERKAPALAN PROGRAM DIPLOMA FAKULTAS TEKNIK UNIVERSITAS DIPONEGORO SEMARANG ANDHIKA ADI. S L0G006007 III - 19 Lmax 0,2 Lpp = 0,2 x 99,15 = 19,83 m Lt = direncanakan 9,6 m Tangki muat yang di rencanakan ada 6 buah dengan panjang tiap tangki muat adalah : Tangki Muat I = 16 x Jarak Gading Melintang = 16 x 0,6 Jarak Gading = 9,6 m Tangki Muat II = 16 x Jarak Gading Melintang = 16 x 0,6 Jarak Gading = 9,6 m Tangki Muat III = 16 x Jarak Gading Melintang = 16 x 0,6 Jarak Gading = 9,6 m Tangki Muat IV = 16 x Jarak Gading Melintang = 16 x 0,6 Jarak Gading = 9,6 m Tangki Muat V = 16 x Jarak Gading Melintang = 16 x 0,6 Jarak Gading = 9,6 m Tangki Muat VI = 16 x Jarak Gading Melintang = 16 x 0,6 Jarak Gading = 9,6 m 4.1 Perhitungan volume tangki muat a. Tangki Muat VI terletak pada Frame 56 – Frame 72 Frame Luas FS Hasil 56 117,973 1 117,973 57 118,161 4 472,644 58 118,330 2 236,660 59 118,483 4 473,932 60 118,622 2 237,244 61 118,750 4 475,000 GENERAL ARRANGEMENT MT “SAFINA SYUMADHANI” Tanker 3600 BRT TUGAS AKHIR PROGRAM STUDI D III TEKNIK PERKAPALAN PROGRAM DIPLOMA FAKULTAS TEKNIK UNIVERSITAS DIPONEGORO SEMARANG ANDHIKA ADI. S L0G006007 III - 20 62 118,869 2 237,738 63 118,982 4 475,928 64 119,089 2 238,178 65 119,193 4 476,772 66 119,295 2 238,590 67 119,304 4 477,216 68 119,304 2 238,608 69 119,304 4 477,216 70 119,304 2 238,608 71 119,304 4 477,216 72 119,304 1 119,304 S 5708,827 Volume = k . h . S = 13 x 0,6 x 5708,827 m 3 = 1141,765 m 3 Tangki dasar ganda tangki muat VI pada Frame.56 – Frame. 72 Frame Luas FS Hasil 56 14,844 1 14,844 57 14,869 4 59,476 58 14,895 2 29,790 59 14,920 4 59,680 60 14,946 2 29,892 61 14,972 4 59,888 62 14,997 2 29,994 63 15,023 4 60,092 64 15,048 2 30,096 65 15,074 4 60,296 66 15,100 2 30,200 67 15,102 4 60,408 68 15,102 2 30,204 69 15,102 4 60,408 70 15,102 2 30,204 71 15,102 4 60,408 72 15,102 1 15,102 S 720,982 Volume = k . h . S = 13 x 0,6 x 720,982 m 3 = 144,1964 m 3 GENERAL ARRANGEMENT MT “SAFINA SYUMADHANI” Tanker 3600 BRT TUGAS AKHIR PROGRAM STUDI D III TEKNIK PERKAPALAN PROGRAM DIPLOMA FAKULTAS TEKNIK UNIVERSITAS DIPONEGORO SEMARANG ANDHIKA ADI. S L0G006007 III - 21 Vol. R. Muat VI Total = Vol. R. Muat – Vol. dasar ganda = 1141,765 - 144,1964 = 997,5686 m 3 b.Tangki Muat V terletak pada Frame 72 – Frame 88 Frame Luas FS Hasil 72 119,304 1 119,304 73 119,304 4 477,216 74 119,304 2 238,608 75 119,304 4 477,216 76 119,304 2 238,608 77 119,304 4 477,216 78 119,304 2 238,608 79 119,304 4 477,216 80 119,304 2 238,608 81 119,304 4 477,216 82 119,304 2 238,608 83 119,304 4 477,216 84 119,304 2 238,608 85 119,304 4 477,216 86 119,304 2 238,608 87 119,304 4 477,216 88 119,304 1 119,304 S 5726,592 Volume = k . h . S = 13 x 0,6 x 5726,592 m 3 = 1145,318 m 3 Tangki dasar ganda tangki muat V pada Frame.72 – Frame. 88 Frame Luas FS Hasil 72 15,102 1 15,102 73 15,102 4 60,408 74 15,102 2 30,204 75 15,102 4 60,408 76 15,102 2 30,204 77 15,102 4 60,408 78 15,102 2 30,204 79 15,102 4 60,408 80 15,102 2 30,204 81 15,102 4 60,408 82 15,102 2 30,204 GENERAL ARRANGEMENT MT “SAFINA SYUMADHANI” Tanker 3600 BRT TUGAS AKHIR PROGRAM STUDI D III TEKNIK PERKAPALAN PROGRAM DIPLOMA FAKULTAS TEKNIK UNIVERSITAS DIPONEGORO SEMARANG ANDHIKA ADI. S L0G006007 III - 22 83 15,102 4 60,408 84 15,102 2 30,204 85 15,102 4 60,408 86 15,102 2 30,204 87 15,102 4 60,408 88 15,102 1 15,102 S 724,896 Volume = k . h . S = 13 x 0,6 x 724,896 m 3 = 144,9792 m 3 Vol. R. Muat V Total = Vol. R. Muat – Vol. dasar ganda = 1145,318 - 144,9792 = 1000,3388 m 3 c. Tangki Muat IV terletak pada Frame 88– Frame 104 Frame Luas FS Hasil 88 119,304 1 119,304 89 119,304 4 477,216 90 119,304 2 238,608 91 119,304 4 477,216 92 119,304 2 238,608 93 119,304 4 477,216 94 119,304 2 238,608 95 119,304 4 477,216 96 119,304 2 238,608 97 119,304 4 477,216 98 119,304 2 238,608 99 119,304 4 477,216 100 119,292 2 238,584 101 119,277 4 477,108 102 119,263 2 238,526 103 119,248 4 476,992 104 119,234 1 119,234 S 5726,084 Volume = k . h . S = 13 x 0,6 x 5726,084 m 3 = 1145,217 m 3 GENERAL ARRANGEMENT MT “SAFINA SYUMADHANI” Tanker 3600 BRT TUGAS AKHIR PROGRAM STUDI D III TEKNIK PERKAPALAN PROGRAM DIPLOMA FAKULTAS TEKNIK UNIVERSITAS DIPONEGORO SEMARANG ANDHIKA ADI. S L0G006007 III - 23 Tangki dasar ganda tangki muat IV pada Frame.88 –Frame. 104 Frame Luas FS Hasil 88 15,102 1 15,102 89 15,102 4 60,408 90 15,102 2 30,204 91 15,102 4 60,408 92 15,102 2 30,204 93 15,102 4 60,408 94 15,102 2 30,204 95 15,102 4 60,408 96 15,102 2 30,204 97 15,102 4 60,408 98 15,102 2 30,204 99 15,102 4 40,408 100 15,100 2 30,200 101 15,099 4 60,396 102 15,097 2 30,194 103 15,095 4 60,380 104 15,093 1 15,093 S 724,833 Volume = k . h . S = 13 x 0,6 x 724,833 m 3 = 144,966 m 3 Vol. R. Muat IV Total = Vol. R. Muat – Vol. dasar ganda = 1145,217 - 144,966 = 1000,251 m 3 d.Tangki Muat III terletak pada Frame. 104– Frame 120 Frame Luas FS Hasil 104 119,234 1 119,234 105 119,220 4 476,880 106 119,205 2 238,410 107 119,191 4 476,764 108 119,176 2 238,352 109 119,162 4 476,648 110 119,148 2 238,296 111 119,133 4 476,532 112 119,119 2 238,238 GENERAL ARRANGEMENT MT “SAFINA SYUMADHANI” Tanker 3600 BRT TUGAS AKHIR PROGRAM STUDI D III TEKNIK PERKAPALAN PROGRAM DIPLOMA FAKULTAS TEKNIK UNIVERSITAS DIPONEGORO SEMARANG ANDHIKA ADI. S L0G006007 III - 24 113 119,105 4 476,420 114 119,090 2 238,180 115 119,076 4 476,304 116 118,966 2 237,932 117 118,656 4 474,624 118 118,326 2 236,652 119 118,011 4 472,044 120 117,665 1 117,665 S 5709,175 Volume = k . h . S = 13 x 0,6 x 5709,175 m 3 = 1141,835 m 3 Tangki dasar ganda tangki muat III pada Frame.104-Frame.120 Frame Luas FS Hasil 104 15,093 1 15,093 105 15,091 4 60,364 106 15,090 2 30,180 107 15,088 4 60,352 108 15,086 2 30,172 109 15,084 4 60,336 110 15,082 2 30,164 111 15,080 4 60,320 112 15,079 2 30,158 113 15,077 4 60,308 114 15,075 2 30,150 115 15,073 4 60,292 116 15,061 2 30,122 117 15,027 4 60,108 118 14,990 2 29,980 119 14,952 4 59,808 120 14,909 1 14,909 S 722,816 Volume = k . h . S = 13 x 0,6 x 722,816 m 3 = 144,5632 m 3 Vol. R. Muat III Total = Vol. R. Muat – Vol. dasar ganda = 1141,835 - 144,5632 = 997,2718 m 3 GENERAL ARRANGEMENT MT “SAFINA SYUMADHANI” Tanker 3600 BRT TUGAS AKHIR PROGRAM STUDI D III TEKNIK PERKAPALAN PROGRAM DIPLOMA FAKULTAS TEKNIK UNIVERSITAS DIPONEGORO SEMARANG ANDHIKA ADI. S L0G006007 III - 25 e. Tangki Muat II terletak pada Frame. 120– Frame 136 Frame Luas FS Hasil 120 117,665 1 117,665 121 117,295 4 469,180 122 116,891 2 233,782 123 116,441 4 465,764 124 115,929 2 231,858 125 115,333 4 461,332 126 114,636 2 229,272 127 113,825 4 455,300 128 112,884 2 225,768 129 111,801 4 447,204 130 110,574 2 221,148 131 109,220 4 436,880 132 107,782 2 215,564 133 105,851 4 423,404 134 103,798 2 207,596 135 101,731 4 406,924 136 99,644 1 99,644 S 5348,285 Volume = k . h . S = 13 x 0,6 x 5348,285 m 3 = 1069,657 m 3 Tangki dasar ganda tangki muat II pada Frame.129 –Frame.145 Frame Luas FS Hasil 120 14,909 1 14,909 121 14,861 4 59,444 122 14,807 2 29,614 123 14,745 4 58,980 124 14,674 2 29,348 125 14,594 4 58,376 126 14,502 2 29,004 127 14,398 4 57,592 128 14,280 2 28,560 129 14,148 4 56,592 130 13,999 2 27,998 131 13,833 4 55,332 132 13,646 2 27,292 133 13,439 4 53,756 134 13,210 2 26,420 GENERAL ARRANGEMENT MT “SAFINA SYUMADHANI” Tanker 3600 BRT TUGAS AKHIR PROGRAM STUDI D III TEKNIK PERKAPALAN PROGRAM DIPLOMA FAKULTAS TEKNIK UNIVERSITAS DIPONEGORO SEMARANG ANDHIKA ADI. S L0G006007 III - 26 135 12,963 4 51,852 136 12,698 1 12,698 S 677,767 Volume = k . h . S = 13 x 0,6 x 677,767 m 3 = 135,5534 m 3 Vol. R. Muat II Total = Vol. R. Muat – Vol. dasar ganda = 1069,657 – 135,5534 = 934,1036 m 3 f. Tangki Muat I terletak pada Frame. 136 – Frame 152 Frame Luas FS Hasil 136 99,644 1 99,644 137 97,528 4 390,112 138 95,374 2 190,748 139 93,170 4 372,680 140 90,904 2 181,808 141 88,559 4 354,236 142 86,122 2 172,244 143 83,585 4 334,340 144 80,938 2 161,876 145 78,171 4 312,684 146 75,270 2 150,540 147 72,222 4 288,888 148 69,007 2 138,014 149 65,605 4 262,420 150 62,005 2 124,010 151 58,229 4 232,916 152 54,324 1 54,324 S 3821,484 Volume = k . h . S = 13 x 0,6 x 3821,484 m 3 = 764,2968m 3 Tangki dasar ganda tangki muat I pada Frame. 136– Frame.152 Frame Luas FS Hasil 136 12,698 1 12,698 137 12,419 4 49,676 GENERAL ARRANGEMENT MT “SAFINA SYUMADHANI” Tanker 3600 BRT TUGAS AKHIR PROGRAM STUDI D III TEKNIK PERKAPALAN PROGRAM DIPLOMA FAKULTAS TEKNIK UNIVERSITAS DIPONEGORO SEMARANG ANDHIKA ADI. S L0G006007 III - 27 138 12,127 2 24,254 139 11,825 4 47,300 140 11,516 2 23,032 141 11,202 4 44,808 142 10,884 2 21,768 143 10,558 4 42,232 144 10,224 2 20,448 145 9,877 4 39,508 146 9,515 2 19,030 147 9,135 4 36,540 148 8,733 2 17,466 149 8,305 4 33,220 150 7,848 2 15,696 151 7,369 4 29,476 152 6,875 1 6,875 S 484,027 Volume = k . h . S = 13 x 0,6 x 484,027m 3 = 96,8054 m 3 Vol. R. Muat I Total = Vol. R. Muat – Vol. dasar ganda = 764,2968– 96,8054 = 667,4914 m 3 Ø Volume Tangki Muat Total Sebelum Double Skin : = Vol R.M VI Tot + Vol R.M Tot V + Vol R.M Tot IV + Vol R.M Tot III + Vol R.M Tot II + Vol R.M Tot I = 997,5686 + 1000,3388 + 1000,251 + 997,2718 + 934,1036 + 667,4914 = 5597,0252 m 3 4.2 Perhitungan Volume Tanki Muat yang dibutuhkan dan Volume Double Skin a. Volume Tangki Muat VI Tanki muat VI terletak pada frame 56 – frame 72 dengan jarak 9,6 m. P = 9,6 L = 13,41 T = 6,9 Volume tanki muat VI = P x L x T GENERAL ARRANGEMENT MT “SAFINA SYUMADHANI” Tanker 3600 BRT TUGAS AKHIR PROGRAM STUDI D III TEKNIK PERKAPALAN PROGRAM DIPLOMA FAKULTAS TEKNIK UNIVERSITAS DIPONEGORO SEMARANG ANDHIKA ADI. S L0G006007 III - 28 = 9,6 x 13,41 x 6,9 = 888,2784 m 3 b. Volume Tangki Muat V Tanki muat V terletak pada frame 72 – frame 88 dengan jarak 9,6 m. P = 9,6 L = 13,41 T = 6,9 Volume Tangki Muat V = P x L x T = 9,6 x 13,41 x 6,9 = 888,2784 m 3 c. Volume Tangki Muat IV Tanki muat IV terletak pada frame 88 –frame 104 dengan jarak 9,6 m. P = 9,6 L = 13,41 T = 6,9 Volume Tangki Muat IV = P x L x T = 9,6 x 13,41 x 6.9 = 888,2784 m 3 d. Volume Tangki Muat III Tanki muat III terletak pada frame 104–frame120 dengan jarak 9,6 m. P = 9,6 L = 13,41 T = 6,9 Volume Tangki Muat III = P x L x T = 9,6 x 13,41 x 6,9 = 888,2784 m 3 e. Volume Tangki Muat II Tanki muat II terletak pada frame 120–frame136 dengan jarak 9,6 m. P = 9,6 L = 13,41 T = 6,9 Volume Tangki Muat II = P x L x T GENERAL ARRANGEMENT MT “SAFINA SYUMADHANI” Tanker 3600 BRT TUGAS AKHIR PROGRAM STUDI D III TEKNIK PERKAPALAN PROGRAM DIPLOMA FAKULTAS TEKNIK UNIVERSITAS DIPONEGORO SEMARANG ANDHIKA ADI. S L0G006007 III - 29 = 9,6 x 13,41 x 6,9 = 888,2784 m 3 f. Volume Tangki Muat I Tanki muat I terletak pada frame 136–frame152 dengan jarak 9,6 m. P = 9,6 L = 13,41 T = 6,9 Volume Tangki Muat I = P x L x T = 9,6 x 13,41 x 6,9 = 888,2784 m 3 Volume Tangki Muat total = TM I + TM II + TM III + TM IV + TM V + TM VI = 888,2784 + 888,2784 + 888,2784 + 888,2784 + 888,2784 + 888,2784 = 5329,6704 m 3 Koreksi Volume Muatan Volume Tanki Muat Rencana Volume Muatan Perhitungan Awal 5329,4704 m 3 5306,0091 m 3 = 100 x n Perencanaa Volume n Perhitunga Volume n Perencanaa Volume - = 100 5329,4704 0091 , 5306 4704 , 5329 - = 0,44 0,5 memenuhi

5. Perhitungan Volume Tanki-Tanki Lain