No. U R A I A N
KODE KOEF.
SATUAN KET.
A. URAIAN PERALATAN
1. Jenis Peralatan
CONCRETE MIXER 0.3-0.6 M3 E06
2. Tenaga
Pw HP
3. Kapasitas
Cp Liter
4. Umur Ekonomis
A Tahun
5. Jam Kerja Dalam 1 Tahun
W Jam
6. Harga Setempat
B Rupiah
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat
= 10 x B C
Rupiah 2.
Faktor Angsuran Modal = i x 1 + iA
D -
1 + iA - 1 3.
Biaya Pasti per Jam : a. Biaya Pengembalian Modal =
B - C x D E
Rupiah W
b. Asuransi dan Lain-lain = 0.20 x C
F Rupiah
W
Biaya Pasti per Jam = E + F
G Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = 0.125-0.175 LtrHPJam x Pw x Ms
H Rupiah
2. Pelumas = 0.0035-0.006 LtrHPJam x Pw x Mp
I Rupiah
3. Workshop =
6,25 - 8,75 x B J
Rupiah W
4. Sparepart =
12,5 - 17,5 x B K
Rupiah W
5. Operator
= 1 Orang Jam x U1 L
Rupiah 6.
Pembantu Operator = 1 Orang Jam x U2
M Rupiah
Biaya Operasi per Jam =
H+I+J+K+L+M P
Rupiah
D. TOTAL BIAYA SEWA ALAT JAM = G + P
S Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga
i Tahun
2. Upah Operator
U1 Rp.Jam
3. Upah Pembantu Operator
U2 Rp.Jam
4. Bahan Bakar Bensin
Mb Liter
5. Bahan Bakar Solar
Ms Liter
6. Minyak Pelumas
Mp Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
PPN Biaya Pekerjaan
Note : = Bila bukan alat baru, diperhitungkan setelah mengalami depresiasi dengan declining methode.
ANALISA BIAYA SEWA ALAT PER JAM KERJA
No. U R A I A N
KODE KOEF.
SATUAN KET.
A. URAIAN PERALATAN
1. Jenis Peralatan
DUMP TRUCK 3-4 M3 E08
2. Tenaga
Pw HP
3. Kapasitas
Cp Ton
4. Umur Ekonomis
A Tahun
5. Jam Kerja Dalam 1 Tahun
W Jam
6. Harga Setempat
B Rupiah
7. Harga Ban
6,00 Bh
b1 Rupiah
B
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat
= 10 x B C
Rupiah 2.
Faktor Angsuran Modal = i x 1 + iA
D -
1 + iA - 1 3.
Biaya Pasti per Jam : a. Biaya Pengembalian Modal =
B - C x D E
Rupiah W
b. Asuransi dan Lain-lain = 0.20 x C
F Rupiah
W
Biaya Pasti per Jam = E + F
G Rupiah
C. BIAYA OPERASI PER JAM KERJA