Lampiran 1. addendum II. ANALISA BIAYA ALAT

(1)

1. Jenis Peralatan CONCRETE MIXER 0.3-0.6 M3 E06

2. Tenaga Pw HP

3. Kapasitas Cp Liter

4. Umur Ekonomis A Tahun

5. Jam Kerja Dalam 1 Tahun W Jam

6. Harga Setempat B Rupiah

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x B C Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D

-(1 + i)^A' - 1 3. Biaya Pasti per Jam :

a. Biaya Pengembalian Modal = ( B' - C ) x D E Rupiah

W'

b. Asuransi dan Lain-lain = 0.20 x C F Rupiah

W'

Biaya Pasti per Jam = ( E + F ) G Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H Rupiah 2. Pelumas = (0.0035-0.006 Ltr/HP/Jam) x Pw x Mp I Rupiah

3. Workshop = (6,25 % - 8,75 %) x B' J Rupiah

W'

4. Sparepart = (12,5 % - 17,5 %) x B' K Rupiah W'

5. Operator = ( 1 Orang / Jam ) x U1 L Rupiah

6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i % / Tahun

2. Upah Operator U1 Rp./Jam

3. Upah Pembantu Operator U2 Rp./Jam


(2)

1. Jenis Peralatan DUMP TRUCK 3-4 M3 E08

2. Tenaga Pw HP

3. Kapasitas Cp Ton

4. Umur Ekonomis A Tahun

5. Jam Kerja Dalam 1 Tahun W Jam

6. Harga Setempat B Rupiah

7. Harga Ban 6,00 Bh b1 Rupiah

B'

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x B' C Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D

-(1 + i)^A' - 1 3. Biaya Pasti per Jam :

a. Biaya Pengembalian Modal = ( B' - C ) x D E Rupiah

W'

b. Asuransi dan Lain-lain = 0.20 x C F Rupiah

W'

Biaya Pasti per Jam = ( E + F ) G Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H Rupiah 2. Pelumas = (0.0035-0.006 Ltr/HP/Jam) x Pw x Mp I Rupiah

3. Workshop = (6,25 % - 8,75 %) x B' J Rupiah

W'

4. Sparepart = (12,5 % - 17,5 %) x B' K Rupiah W'

5. Biaya Ban = Jml Ban x Hrg Ban L Rupiah

900

6. Sopir = ( 1 Orang / Jam ) x U1 L Rupiah

7. Pembantu Sopir = ( 1 Orang / Jam ) x U2 M Rupiah


(3)

1. Jenis Peralatan EXCAVATOR 80-140 HP E10

2. Tenaga Pw HP

3. Kapasitas Cp M3

4. Umur Ekonomis A Tahun

5. Jam Kerja Dalam 1 Tahun W Jam

6. Harga Setempat B Rupiah

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x B C Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D

-(1 + i)^A' - 1 3. Biaya Pasti per Jam :

a. Biaya Pengembalian Modal = ( B' - C ) x D E Rupiah

W'

b. Asuransi dan Lain-lain = 0.20 x C F Rupiah

W'

Biaya Pasti per Jam = ( E + F ) G Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H Rupiah 2. Pelumas = (0.0035-0.006 Ltr/HP/Jam) x Pw x Mp I Rupiah

3. Workshop = (6,25 % - 8,75 %) x B' J Rupiah

W'

4. Sparepart = (12,5 % - 17,5 %) x B' K Rupiah W'

5. Operator = ( 1 Orang / Jam ) x U1 L Rupiah

6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i % / Tahun

2. Upah Operator U1 Rp./Jam

3. Upah Pembantu Operator U2 Rp./Jam


(4)

1. Jenis Peralatan MOTOR GRADER >100 HP E13

2. Tenaga Pw HP

3. Kapasitas Cp

4. Umur Ekonomis A Tahun

5. Jam Kerja Dalam 1 Tahun W Jam

6. Harga Setempat bs Rupiah

7. Harga Ban 6,00 Bh b1 Rupiah

B

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x B C Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D

-(1 + i)^A' - 1 3. Biaya Pasti per Jam :

a. Biaya Pengembalian Modal = ( B' - C ) x D E Rupiah

W'

b. Asuransi dan Lain-lain = 0.20 x C F Rupiah

W'

Biaya Pasti per Jam = ( E + F ) G Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H Rupiah 2. Pelumas = (0.0035-0.006 Ltr/HP/Jam) x Pw x Mp I Rupiah

3. Workshop = (6,25 % - 8,75 %) x B' J Rupiah

W'

4. Sparepart = (12,5 % - 17,5 %) x B' K Rupiah

5. Biaya Ban = Jml Ban x Hrg Ban L Rupiah

1200

6. Operator = ( 1 Orang / Jam ) x U1 M Rupiah

7. Pembantu Operator = ( 1 Orang / Jam ) x U2 N Rupiah


(5)

1. Jenis Peralatan WHEEL LOADER 1.0-1.6 M3 E15

2. Tenaga Pw HP

3. Kapasitas Cp M3

4. Umur Ekonomis A Tahun

5. Jam Kerja Dalam 1 Tahun W Jam

6. Harga Setempat B Rupiah

7. Harga Ban 4,00 Bh b1 Rupiah

B

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x B C Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D

-(1 + i)^A' - 1 3. Biaya Pasti per Jam :

a. Biaya Pengembalian Modal = ( B' - C ) x D E Rupiah

W'

b. Asuransi dan Lain-lain = 0.20 x C F Rupiah

W'

Biaya Pasti per Jam = ( E + F ) G Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H Rupiah 2. Pelumas = (0.0035-0.006 Ltr/HP/Jam) x Pw x Mp I Rupiah

3. Workshop = (6,25 % - 8,75 %) x B' J Rupiah

W'

4. Sparepart = (12,5 % - 17,5 %) x B' K Rupiah

5. Biaya Ban = Jml Ban x Hrg Ban L Rupiah

1200

6. Operator = ( 1 Orang / Jam ) x U1 L Rupiah

7. Pembantu Operator = ( 1 Orang / Jam ) x U2 M Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i % / Tahun

2. Upah Operator U1 Rp./Jam

3. Upah Pembantu Operator U2 Rp./Jam


(6)

1. Jenis Peralatan VIBRATORY ROLLER 5-8 T. E19

2. Tenaga Pw 60,0 HP

3. Kapasitas Cp 8,0 Ton

4. Umur Ekonomis A 5,0 Tahun

5. Jam Kerja Dalam 1 Tahun W 1.800,0 Jam

6. Harga Setempat B 543.229.500 Rupiah

7. Harga Ban 2,00 Bh b1 9.000.000 Rupiah

B' 534.229.500

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x B C 53.422.950 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0,26380 -(1 + i)^A' - 1

3. Biaya Pasti per Jam :

a. Biaya Pengembalian Modal = ( B' - C ) x D E 70.464,20 Rupiah W'

b. Asuransi dan Lain-lain = 0.20 x C F 5.935,88 Rupiah W'

Biaya Pasti per Jam = ( E + F ) G 76.400,08 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 0,00 Rupiah 2. Pelumas = (0.0035-0.006 Ltr/HP/Jam) x Pw x Mp I 0,00 Rupiah 3. Workshop = (6,25 % - 8,75 %) x B' J 22.634,56 Rupiah

W'

4. Sparepart = (12,5 % - 17,5 %) x B' K 37.724,27 Rupiah W'

5. Biaya Ban = Jml Ban x Hrg Ban L 7.500,00 Rupiah 1200

6. Operator = ( 1 Orang / Jam ) x U1 L 0,00 Rupiah

7. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 0,00 Rupiah


(7)

3. Kapasitas Cp -

4. Umur Ekonomis A 5,0 Tahun

5. Jam Kerja Dalam 1 Tahun W 1.500,0 Jam

6. Harga Setempat B 15.000.000 Rupiah

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x B C 1.500.000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0,26380 -(1 + i)^A' - 1

3. Biaya Pasti per Jam :

a. Biaya Pengembalian Modal = ( B' - C ) x D E 2.374,18 Rupiah W'

b. Asuransi dan Lain-lain = 0.20 x C F 200,00 Rupiah W'

Biaya Pasti per Jam = ( E + F ) G 2.574,18 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 0,00 Rupiah 2. Pelumas = (0.0035-0.006 Ltr/HP/Jam) x Pw x Mp I 0,00 Rupiah 3. Workshop = (6,25 % - 8,75 %) x B' J 750,00 Rupiah

W'

4. Sparepart = (12,5 % - 17,5 %) x B' K 1.250,00 Rupiah W'

5. Operator = ( 1 Orang / Jam ) x U1 L - Rupiah 6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 0,00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 2.000,00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 4.574,18 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 10,00 % / Tahun

2. Upah Operator / Sopir U1 - Rp./Jam

3. Upah Pembantu Operator / Pmb.Sopir U2 0,00 Rp./Jam

4. Bahan Bakar Bensin Mb 0,00 Liter

5. Bahan Bakar Solar Ms 0,00 Liter

6. Minyak Pelumas Mp 0,00 Liter

7. PPN diperhitungkan pada lembar Rekapitulasi PPN 10,00 % Biaya Pekerjaan


(8)

1. Jenis Peralatan WATER TANKER 3000-4500 L. E23

2. Tenaga Pw 115,0 HP

3. Kapasitas Cp 4.000,0 Liter

4. Umur Ekonomis A 5,0 Tahun

5. Jam Kerja Dalam 1 Tahun W 1.800,0 Jam

6. Harga Setempat B 255.000.000 Rupiah

7. Harga Ban 6,00 Bh b1 4.800.000 Rupiah

B' 250.200.000

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x B C 25.020.000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0,26380 -(1 + i)^A' - 1

3. Biaya Pasti per Jam :

a. Biaya Pengembalian Modal = ( B' - C ) x D E 33.001,06 Rupiah W'

b. Asuransi dan Lain-lain = 0.20 x C F 2.780,00 Rupiah W'

Biaya Pasti per Jam = ( E + F ) G 35.781,06 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 0,00 Rupiah 2. Pelumas = (0.0035-0.006 Ltr/HP/Jam) x Pw x Mp I 0,00 Rupiah 3. Workshop = (6,25 % - 8,75 %) x B' J 10.625,00 Rupiah

W'

4. Sparepart = (12,5 % - 17,5 %) x B' K 17.708,33 Rupiah 5. Biaya Ban = Jml Ban x Hrg Ban L 4.000,00 Rupiah

1200

6. Sopir = ( 1 Orang / Jam ) x U1 L 0,00 Rupiah

7. Pembantu Sopir = ( 1 Orang / Jam ) x U2 M 0,00 Rupiah


(9)

3. Kapasitas Cp -

4. Umur Ekonomis A 5,0 Tahun

5. Jam Kerja Dalam 1 Tahun W 1.500,0 Jam

6. Harga Setempat B 168.750.000 Rupiah

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x B C 16.875.000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0,26380 -(1 + i)^A' - 1

3. Biaya Pasti per Jam :

a. Biaya Pengembalian Modal = ( B' - C ) x D E 26.709,49 Rupiah W'

b. Asuransi dan Lain-lain = 0.20 x C F 2.250,00 Rupiah W'

Biaya Pasti per Jam = ( E + F ) G 28.959,49 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 0,00 Rupiah (Excavator) 2. Pelumas = (0.0035-0.006 Ltr/HP/Jam) x Pw x Mp I 0,00 Rupiah

3. Workshop = (6,25 % - 8,75 %) x B' J 8.437,50 Rupiah W'

4. Sparepart = (12,5 % - 17,5 %) x B' K 14.062,50 Rupiah W'

5. Operator = ( 1 Orang / Jam ) x U1 L - Rupiah 6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M - Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 22.500,00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 51.459,49 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 10,00 %/Tahun

2. Upah Operator U1 0,00 Rp./Jam

3. Upah Pembantu Operator U2 0,00 Rp./Jam

4. Bahan Bakar Bensin Mb 0,00 Liter

5. Bahan Bakar Solar Ms 0,00 Liter

6. Minyak Pelumas Mp 0,00 Liter

7. PPN diperhitungkan pada lembar Rekapitulasi PPN 10,00 % Biaya Pekerjaan


(1)

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN

1. Jenis Peralatan MOTOR GRADER >100 HP E13

2. Tenaga Pw HP

3. Kapasitas Cp

4. Umur Ekonomis A Tahun

5. Jam Kerja Dalam 1 Tahun W Jam

6. Harga Setempat bs Rupiah

7. Harga Ban 6,00 Bh b1 Rupiah

B

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x B C Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D

-(1 + i)^A' - 1 3. Biaya Pasti per Jam :

a. Biaya Pengembalian Modal = ( B' - C ) x D E Rupiah

W'

b. Asuransi dan Lain-lain = 0.20 x C F Rupiah

W'

Biaya Pasti per Jam = ( E + F ) G Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H Rupiah 2. Pelumas = (0.0035-0.006 Ltr/HP/Jam) x Pw x Mp I Rupiah

3. Workshop = (6,25 % - 8,75 %) x B' J Rupiah

W'

4. Sparepart = (12,5 % - 17,5 %) x B' K Rupiah

5. Biaya Ban = Jml Ban x Hrg Ban L Rupiah

1200

6. Operator = ( 1 Orang / Jam ) x U1 M Rupiah

7. Pembantu Operator = ( 1 Orang / Jam ) x U2 N Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M+N) O Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + O ) S Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i % / Tahun

2. Upah Operator U1 Rp./Jam

3. Upah Pembantu Operator U2 Rp./Jam

4. Bahan Bakar Bensin Mb Liter

5. Bahan Bakar Solar Ms Liter


(2)

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN

1. Jenis Peralatan WHEEL LOADER 1.0-1.6 M3 E15

2. Tenaga Pw HP

3. Kapasitas Cp M3

4. Umur Ekonomis A Tahun

5. Jam Kerja Dalam 1 Tahun W Jam

6. Harga Setempat B Rupiah

7. Harga Ban 4,00 Bh b1 Rupiah

B

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x B C Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D

-(1 + i)^A' - 1 3. Biaya Pasti per Jam :

a. Biaya Pengembalian Modal = ( B' - C ) x D E Rupiah

W'

b. Asuransi dan Lain-lain = 0.20 x C F Rupiah

W'

Biaya Pasti per Jam = ( E + F ) G Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H Rupiah 2. Pelumas = (0.0035-0.006 Ltr/HP/Jam) x Pw x Mp I Rupiah

3. Workshop = (6,25 % - 8,75 %) x B' J Rupiah

W'

4. Sparepart = (12,5 % - 17,5 %) x B' K Rupiah

5. Biaya Ban = Jml Ban x Hrg Ban L Rupiah

1200

6. Operator = ( 1 Orang / Jam ) x U1 L Rupiah

7. Pembantu Operator = ( 1 Orang / Jam ) x U2 M Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i % / Tahun

2. Upah Operator U1 Rp./Jam

3. Upah Pembantu Operator U2 Rp./Jam


(3)

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN

1. Jenis Peralatan VIBRATORY ROLLER 5-8 T. E19

2. Tenaga Pw 60,0 HP

3. Kapasitas Cp 8,0 Ton

4. Umur Ekonomis A 5,0 Tahun

5. Jam Kerja Dalam 1 Tahun W 1.800,0 Jam

6. Harga Setempat B 543.229.500 Rupiah

7. Harga Ban 2,00 Bh b1 9.000.000 Rupiah

B' 534.229.500

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x B C 53.422.950 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0,26380 -(1 + i)^A' - 1

3. Biaya Pasti per Jam :

a. Biaya Pengembalian Modal = ( B' - C ) x D E 70.464,20 Rupiah W'

b. Asuransi dan Lain-lain = 0.20 x C F 5.935,88 Rupiah W'

Biaya Pasti per Jam = ( E + F ) G 76.400,08 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 0,00 Rupiah 2. Pelumas = (0.0035-0.006 Ltr/HP/Jam) x Pw x Mp I 0,00 Rupiah 3. Workshop = (6,25 % - 8,75 %) x B' J 22.634,56 Rupiah

W'

4. Sparepart = (12,5 % - 17,5 %) x B' K 37.724,27 Rupiah W'

5. Biaya Ban = Jml Ban x Hrg Ban L 7.500,00 Rupiah 1200

6. Operator = ( 1 Orang / Jam ) x U1 L 0,00 Rupiah

7. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 0,00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 67.858,83 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 144.258,91 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 10,00 % / Tahun

2. Upah Operator U1 0,00 Rp./Jam

3. Upah Pembantu Operator U2 0,00 Rp./Jam

4. Bahan Bakar Bensin Mb 0,00 Liter


(4)

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN

1. Jenis Peralatan CONCRETE VIBRATOR E20

2. Tenaga Pw 3,0 HP

3. Kapasitas Cp -

4. Umur Ekonomis A 5,0 Tahun

5. Jam Kerja Dalam 1 Tahun W 1.500,0 Jam

6. Harga Setempat B 15.000.000 Rupiah

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x B C 1.500.000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0,26380 -(1 + i)^A' - 1

3. Biaya Pasti per Jam :

a. Biaya Pengembalian Modal = ( B' - C ) x D E 2.374,18 Rupiah W'

b. Asuransi dan Lain-lain = 0.20 x C F 200,00 Rupiah W'

Biaya Pasti per Jam = ( E + F ) G 2.574,18 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 0,00 Rupiah 2. Pelumas = (0.0035-0.006 Ltr/HP/Jam) x Pw x Mp I 0,00 Rupiah 3. Workshop = (6,25 % - 8,75 %) x B' J 750,00 Rupiah

W'

4. Sparepart = (12,5 % - 17,5 %) x B' K 1.250,00 Rupiah W'

5. Operator = ( 1 Orang / Jam ) x U1 L - Rupiah 6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 0,00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 2.000,00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 4.574,18 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 10,00 % / Tahun

2. Upah Operator / Sopir U1 - Rp./Jam

3. Upah Pembantu Operator / Pmb.Sopir U2 0,00 Rp./Jam

4. Bahan Bakar Bensin Mb 0,00 Liter

5. Bahan Bakar Solar Ms 0,00 Liter

6. Minyak Pelumas Mp 0,00 Liter

7. PPN diperhitungkan pada lembar Rekapitulasi PPN 10,00 % Biaya Pekerjaan


(5)

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN

1. Jenis Peralatan WATER TANKER 3000-4500 L. E23

2. Tenaga Pw 115,0 HP

3. Kapasitas Cp 4.000,0 Liter

4. Umur Ekonomis A 5,0 Tahun

5. Jam Kerja Dalam 1 Tahun W 1.800,0 Jam

6. Harga Setempat B 255.000.000 Rupiah

7. Harga Ban 6,00 Bh b1 4.800.000 Rupiah

B' 250.200.000

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x B C 25.020.000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0,26380 -(1 + i)^A' - 1

3. Biaya Pasti per Jam :

a. Biaya Pengembalian Modal = ( B' - C ) x D E 33.001,06 Rupiah W'

b. Asuransi dan Lain-lain = 0.20 x C F 2.780,00 Rupiah W'

Biaya Pasti per Jam = ( E + F ) G 35.781,06 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 0,00 Rupiah 2. Pelumas = (0.0035-0.006 Ltr/HP/Jam) x Pw x Mp I 0,00 Rupiah 3. Workshop = (6,25 % - 8,75 %) x B' J 10.625,00 Rupiah

W'

4. Sparepart = (12,5 % - 17,5 %) x B' K 17.708,33 Rupiah 5. Biaya Ban = Jml Ban x Hrg Ban L 4.000,00 Rupiah

1200

6. Sopir = ( 1 Orang / Jam ) x U1 L 0,00 Rupiah

7. Pembantu Sopir = ( 1 Orang / Jam ) x U2 M 0,00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 32.333,33 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 68.114,40 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 10,00 % / Tahun

2. Upah Operator Water Tank U1 0,00 Rp./Jam

3. Upah Pembantu Operator Water Tank U2 0,00 Rp./Jam

4. Bahan Bakar Bensin Mb 0,00 Liter

5. Bahan Bakar Solar Ms 0,00 Liter


(6)

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN

1. Jenis Peralatan BREAKER E26

2. Tenaga Pw 20,0 HP

3. Kapasitas Cp -

4. Umur Ekonomis A 5,0 Tahun

5. Jam Kerja Dalam 1 Tahun W 1.500,0 Jam

6. Harga Setempat B 168.750.000 Rupiah

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x B C 16.875.000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0,26380 -(1 + i)^A' - 1

3. Biaya Pasti per Jam :

a. Biaya Pengembalian Modal = ( B' - C ) x D E 26.709,49 Rupiah W'

b. Asuransi dan Lain-lain = 0.20 x C F 2.250,00 Rupiah W'

Biaya Pasti per Jam = ( E + F ) G 28.959,49 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 0,00 Rupiah (Excavator) 2. Pelumas = (0.0035-0.006 Ltr/HP/Jam) x Pw x Mp I 0,00 Rupiah

3. Workshop = (6,25 % - 8,75 %) x B' J 8.437,50 Rupiah W'

4. Sparepart = (12,5 % - 17,5 %) x B' K 14.062,50 Rupiah W'

5. Operator = ( 1 Orang / Jam ) x U1 L - Rupiah 6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M - Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 22.500,00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 51.459,49 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 10,00 %/Tahun

2. Upah Operator U1 0,00 Rp./Jam

3. Upah Pembantu Operator U2 0,00 Rp./Jam

4. Bahan Bakar Bensin Mb 0,00 Liter

5. Bahan Bakar Solar Ms 0,00 Liter

6. Minyak Pelumas Mp 0,00 Liter

7. PPN diperhitungkan pada lembar Rekapitulasi PPN 10,00 % Biaya Pekerjaan