Water and Sanitation Program
Page | 11
in the process of developing a national communication platform for data, voice and video services to all district capitals.
The Government also recognises the importance of the need to provide community housing and other support facilities at locations across the country.
4.2. SUMMARY OF THE 2015 IF BUDGET BY PROGRAM 4.2.1. Agriculture Program
The Agriculture Sector is a cornerstone for the economic development of Timor-Leste. The total budget allocated to this sector in 2014, post-virement, totals 10.4 million for six ongoing
projects in 2014. Of these, the Canal Protection Works at Casameta Irrigation Scheme was completed in 2013 and only the payment of retention money 110,000 remains to be paid.
Execution of this payment is waiting recommendation of the project owner and ADN. Phase 1 of Rehabilitation of the Raibere, Oebaba and Carau Ulun Irrigation Schemes are
on-going and that at Larisula will likely commence before the end of 2014 and continue to phase 2. The Detailed Engineering Design DED for Ten Irrigation Schemes had
commenced in 2013 but the contract was terminated in 2014 because of unsatisfactory performance by the consultant, but will re-commence when negotiations with the second placed
bidder have been successfully completed. Initial funding for six other projects was deferred from 2014 to 201516. Of these, it is expected
that the Detailed Engineering Designs DED for Construction of Fishery Harbour at Metinaro will be completed such that works could commence next year. However, given the
lead-time for DED review and procurement, this is unlikely and no funds have been allocated for the project in 2015. For a further four projects, Rehabilitation Works of Irrigation
Schemes at Maukola, Beikala, Galata and Dardau, DEDs have yet to be commissioned by the Ministry of Agriculture and Fisheries and therefore works cannot commence in 2015.
Similarly, the sixth deferred project, Feasibility Studies and Construction of Ten New Dam Sites, will also not be ready for commencement in 2015.
New projects for 2015 are implementations of the second phases of Rehabilitation of the Raibere, Oebaba and Cara Ulun Irrigation Schemes. These will be implemented using the
same contractors that are implementing the first phases to minimise delays and costs. A total budget of 4.0 million has been allocated to these projects.
Thus the IF total required in 2015 for the Agriculture Program is 7.2 million.