SATUAN KERJA KHUSUS PELAKSANA KEGIATAN U

SATUAN KERJA KHUSUS
PELAKSANA KEGIATAN USAHA HULU MINYAK DAN GAS BUMI
(SKK Migas)

OVERVIEW KEGIATAN INDUSTRI HULU MIGAS

Gas

SATUAN KERJA KHUSUS
PELAKSANA KEGIATAN USAHA HULU MINYAK DAN GAS BUMI
(SKK Migas)

TAHAPAN PROYEK FASILITAS PRODUKSI

PROJECT :
- A temporary endeavor undertaken to create a unique product,
service, or result. (PMBOK)

- A temporary organization that is created for the purpose of
delivering one or more business product according to an agreed
Business Case. (PRINCE2)

- A finite endeavor - having specific start and completion dates undertaken to meet particular goals and objectives, usually to
brings about beneficial change or added value. (wikipedia)

THE THREE PROJECT INTERESTS

SKK Migas

KKKS

Kontraktor

Untuk mendukung proses pengambilan keputusan
secara sistematik dan terukur apakah kegiatan kegiatan
Proyek dapat dilanjutkan ke tahapan berikutnya, atau
harus dilakukan peninjauan ulang, atau Proyek
dinyatakan tidak layak untuk diteruskan

Feasibility Study

none


Conceptual
Study

Studi Konseptual
(Pra-POD)

Design
Engineering

FEED

Construction /
EPCI

Konstruksi
(EPCI)

Operation


Pemeliharaan
dan Modifikasi

Tahapan Proyek

Tahapan Proyek
Appraise

Select

Define

FEL-0

FEL-1

FEL-1

FEL-2


FEL-3

Identify

Appraise

Select

Optimize

Define

Phase-1

Phase-2

Identify & Assess Opportunity

Generate & Select
Alternative(s)


Appraisal Design

Pre-Project

Pra-POD

Execute

Operate

Execute

Operate

Phase-3

Phase-4

Phase-5


Develop Preferred Alternative

Execute

Operate & Evaluate

Basic Engineering

EPSC

FEED

Comm &
StartUp

Konstruksi

Operations


OPERASI

Key Criteria for Distinctive Investment Performance
Choose the Right Project

Develop the
Project Right

Deliver the Project Right

*
APPRAISE

SELECT

DEFINE

EXECUTE

OPERATE


Operational
Excellence
Risked Portfolio
Management

Excellence in Project
Management

Konseptual
Source: Eka Satria, bp, FKT 2005

FEED

Konstruksi

OPERASI

Influence vs Cost


Konseptual
Source: Eka Satria, bp, FKT 2005

FEED

Konstruksi

OPERASI

Eng Progress vs Cost Estimate

Copyright © 2009 IHS Inc. All Rights Reserved

6 (Six) Key Project Performance :
1.
2.
3.
4.
5.
6.


QUALITY
COST
SCOPE
TIME / SCHEDULE
RISK
BENEFITS

Plan of Development (POD)
Buku POD terdiri dari :
BAB 1
BAB 2
BAB 3
BAB 4
BAB 5
BAB 6
BAB 7
BAB 8
BAB 9
BAB 10

BAB 11
BAB 12
BAB 13
BAB 14

Executive Summary
Geological Findings and Reviews
Reservoir Descriptions
Reserve & Production Forecast
Drilling & Completion
Production Facilities
Field Development Scenario
Health Safety and Environment & Corporate Social Responsibility
Abandonment & Site Restoration Plan
Project Schedule & Organization
Local Content
Commercial
Conclusion
Attachments (Technical Supporting Data, Minutes of Meetings, Cost
Estimation, Spreadsheet Economic)

MARKET

Contoh: Studi PRE-POD
Pemilihan Konsep Skenario Pengembangan Lapangan yg Optimal

Overall Development
Scenario

Pre - FEED

Tahapan Studi Konseptual (Pre-POD atau Pre-FEED)
• Pre POD adalah kegiatan studi konseptual untuk menggali dan mempertimbangkan :






berbagai skenario pengurasan
lokasi dan metoda pengeboran sumur produksi
konfigurasi dan jenis Fasilitas Produksi, disesuaikan dengan perkiraan jumlah & jenis cadangan
Hasil analisa pasar
termasuk di dalam aktivitas Pre-POD adalah kegiatan survei seismic, studi GGR, pengeboran, dan
survei lokasi (geoteknik dan geofisika),

• Pre-FEED adalah kegiatan Proyek Fasilitas Produksi pada tahap studi konseptual
dimana dilakukan :
– proses identifikasi dan seleksi konsep, jenis, dan konfigurasi Fasilitas Produksi yang paling sesuai
– Pada tahap ini juga dilakukan kegiatan awal survei lokasi (geoteknikal dan geofisikal) untuk
mendapatkan gambaran umum karakteristik pada wilayah kerja yang akan dikembangkan.

• Kegiatan ini diutamakan untuk mendapatkan pilihan konsep pengembangan
lapangan yang akan tertuang di dalam dokumen Plan of Development (POD),
suatu dokumen tentang rencana jangka panjang pengembangan suatu lapangan.

PRE-FEED SAMPLE

41

Relative location to existing and new facilities
New Field / New KKKS

XYZ FIELD

KKKS-1

Plant-1 onshore – 72 Km
KKKS-2

Plant-2 FPU export line – 16 Km (future)
Plant-3 treatment plant – 70 Km
KKKS-3

XYZ FIELD

Plant-4 Terminal – 69 Km
Plant-5 offshore – 43 Km
Plant-6 offshore – 41 Km
Plant-7 – 39 Km
Plant-8 – 80 Km
 Water Depth: 400 - 500 m

Lapangan XYZ Gas Sample Composition

Lean gas
No H2S
Little CO2

Screening Methodology

44

Concept Screening Methodology
3 wells – 250 MMSCFD

Vertical type

Well type

None

Offshore
processing

Offshore
structure

Final
treatment
location

None -Subsea
tie-back

New
onshore
plant

Minim.Off.
Treatment

SWP

Existing
plant

Full Off.
Treat.

SWP

New
onshore
plant

Cluster type

Existing
plant

None

FPU

Minim.Off.
Treatment

None -Subsea
tie-back

New
offshore

New
onshore
plant

Full Off.
Treat.

SWP

TLP

Existing
Plant

SWP

New
onshore
plant

TLP

Existing
plant

FPU

New
offshore

Use of Existing Infrastructure

46

Project Location vs Existing Infrastructure
onshore
gas pipeline

Plant-1 complex

Plant-4 complex

4

4 4
25 km

70 km
+ 5 km
onshore

Custome
Export
Manifold

gas pipeline
70 km + 10 km
onshore

offshore

Plant-6 complex

Plant-7 complex

Plant-5 complex
Plant-8 complex
69 km
39 km

to Existing
41 km
80 km

43 km
Plant-2 complex
16 km
XYZ 3 wells - Gas production range [250 MMSCFD]

future

Offshore Existing Infrastructure

48

Total Site Visit - Objectives

PLANT-8

PLANT-6

80 Km




Mahakam North Area Facilities (Nubi
Complex)
Peciko Offshore Facilities
PLANT-5



Senipah Facilities



Sapi Facilities



PLANT-7

New Area near Senipah

39 Km

43 Km

41 Km

LAP XYZ

Main Findings from Evaluation Study
Plant-5 Offshore Facilities – NOT RECOMMENDED
• Study to tie-in future production from other KKKS (100 MMScfd) or existing (250 MMscfd)
fields into Plan-5 concluded that it is not recommended due to major back pressure with high
impact on current production.
• Seven wellhead unmanned platforms + 1 future currently operated at low pressure (12-15
bar) to try to maximize production.
• Production is sent to Plant-4 Terminal in multiphase via 4X24” pipelines.
• For these reasons, other KKKS and existing production will be sent directly on-shore to
Plant-4 via a dedicated sea-line.

Plant-6 Offshore Facilities – NOT RECOMMENDED
• Only 1X26” trunk line going to the on-shore compression facilities from existing off-shore
field.
• Possible backpressure and Production Losses
• Several wells and three compression stations operated by KKKS-3.
• Compression capacity fully booked for existing fields
• Use strongly discouraged by KKKS-3 as Facilities are in a swampy area (logistic issues,
pipeline laying difficulties and highly expensive civil works for any new facility).

Main Findings from Evaluation Study
Plant-7 Offshore Facilities – NOT RECOMMENDED





Oil field
Old facilities (1974) / Possible integrity issues
No Spare Capacity (design capacity 18 MMSCFD)
System Working at Low Pressure

Plant-8 Offshore Facilities – NOT RECOMMENDED
• Oil field
• No Spare Capacity (design capacity 200 MMSCFD)
• System Working at Low Pressure

Onshore Existing Infrastructure

Total Site Visit - Objectives

PLANT-8

PLANT-6
PLANT-1

70 Km + 10 km onshore
PLANT-4




Mahakam North Area Facilities (Nubi
Complex)
Peciko Offshore Facilities
PLANT-5



Senipah Facilities



Sapi Facilities



PLANT-7

New Area near Senipah

69 Km

LAP XYZ

Main Findings from Evaluation Study
Plant-1 Onshore Facilities – NOT RECOMMENDED
• No Spare Capacity (design capacity 150 MMSCFD)
• System Working at Low Pressure
Plant-4 Onshore Facilities :
Base on study of Plant-4 Terminal – Overview, Plant-4 - Process Area,
Plant-4 Terminal – Production Profile & Spare Capacities, Subsea tieback to Plant-4 Facilities is possible with the following limitation :
 Spare capacity will be available in 2016
 Spare capacity available only on HP System (870 Psig) otherwise
Compression will be needed
 Utilities System to be fully assessed (electrical power available, while water,
air instrument, control room, MCC building, civil works for new equipments to
be assessed)

However, a cost-benefit analysis is to be performed to fully assess this
option.

Project Location vs Existing Infrastructure Options

X

onshore

Plant-1 complex

gas pipeline

Gas capacity 150 mmscfd
Spare gas cap. 25 mmscfd

Plant-4 complex
HP Gas cap. 3 x 350 MMSCFD
Spare HP gas cap.
400 mmscfd from 2016

4 4
25 km

4

70 km
+ 5 km
onshore

Customer
Export
Manifold

gas pipeline
70 km + 10 km
onshore

X

Plant-7 complex
Gas capacity 18 mmscfd
No Spare gas capacity

Plant-5 complex
Wellhead Platforms
Trunkline cap 685
MMscfd (@HP) & 370
MMscfd (@MP)
Spare gas capacity
Major back pressure &
production losses

X

offshore

Plant-6 complex

X

Gas capacity 200 mmscfd
No spare gas cap
Potential Backpressure &
production losses

X

Plant-8 complex
Gas capacity 200 mmscfd
No spare gas cap.
Works in LP system

69 km
41 km
39 km
80 km

future

X

Plant-12 complex
40 km
XYZ 3 wells - Gas production range [250 MMSCFD]

16 km

Gas cap. 700 mmscfd
No spare gas cap
Available in Q3/2016

to Existing

Offshore Processing

56

Main findings from evaluation study

Option 1 : No Offshore Treatment
Subsea tie-back to shore : NOT RECOMMENDED

 Lower gas recovery caused by higher abandonment reservoir pressure
 Potential Flow assurance issues due to multiphase transport (i.e hydrate management, slug volumes,
etc.)
 Less reliability of the system
 System productivity dependent on less efficient well
 Expandability issues
 Dependance on other Operator existing facilities
 Technical Challenges due to long distance from shore (long control umbilical)

Main findings from evaluation study
Option 2 : Minimum Offshore Treatment : separation and compression
Option 3 : Full Offshore Treatment : separation, compression,
dehydration, condensate stabilization, hydrate inhibition
Minimum offshore process: NOT RECOMMENDED
 The minimum offshore treatment is not economically competitive with
respect to the full offshore treatment
 The minimum offshore treatment requires both offshore and onshore
processing facilities, thus increasing related operational and safety issues
(two processing facilities to be managed)
The full offshore treatment is preferred because it allows to
minimize potential flow assurance issues (i.e. hydrates, slugs,
corrosion, potential frequent pigging)

58

Offshore Structure

59

Offshore Platform Types
Larger lake- and sea-based offshore platforms and drilling rigs are some of the largest
moveable man-made structures in the world. There are several types of oil platforms
and rigs:

1, 2) conventional fixed platforms; 3) compliant tower; 4, 5) vertically moored tension leg
and mini-tension leg platform; 6) Spar ; 7,8) Semi-submersibles ; 9) Floating production,
storage, and offloading facility; 10) sub-sea completion and tie-back to host facility

Main findings from evaluation study
TLP: NOT RECOMMENDED

 Not cost effective due to a low number of surface wells reachable
from TLP
 Long time to market
 Low expansion capacity (mini-TLP)

Concepts still to be evaluated
Concept Dropped

5 wells – 300 MMSCFD

Vertical type

Well type

Offshore
processing

Minim.Off.
Treatment

None

Offshore
structure

None -Subsea
tie-back

Final
treatment
location

New
onshore
plant

Existing
Plant

SWP

Cluster type

Full Off.
Treat.

SWP

New
onshore
plant

None

FPU

Existing
plant

Minim.Off.
Treatment

None -Subsea
tie-back

New
offshore

New
onshore
plant

Full Off.
Treat.

SWP

TLP

Existing
Plant

SWP

New
onshore
plant

TLP

Existing
plant

FPU

New
offshore

Development Scenarios


Results of the pre-feasibility study and of the peer reviews recommended to
further evaluate in the concept selection phase the following main
development scenarios:
– Shallow Water Platform (in about 120 m water depth) with full offshore
treatment and export to an existing onshore pipeline
– FPU in about 300-500 m water depth with full offshore treatment and
export to an existing onshore pipeline

Options under evaluation: Shallow water platform (SWP)
To Customer

PLANT-4

70 km
Shallow Water
Platform (120m wd)

LEGEND

 Stand alone SWP
multiphase
Treated gas
Existing pipeline
Subsea development
Full treatment unit (FPU or Platform)
New onshore plant
Existing plant (onshore / offshore)

XYZ Field

 Gas pipeline to Existing pipeline
network

• Subsea Production System
(Wellhead, Flowline, Manifold,
Umbilical)
• Processing Facilities (Receiving &
Separation, Gas compression &
treatment, Condensate Treatment,
Gas & Condensate Transfer, Utility)

Subsea Layouts - SWP

Options under evaluation: Floating Production Unit (FPU)
To Customer

PLANT-4

70 km

FPU
(about 300 m WD)

LEGEND

 Stand alone FPU
multiphase
Treated gas
Existing pipeline
Subsea development
Full treatment unit (FPU or Platform)
New onshore plant
Existing plant (onshore / offshore)

 Gas pipeline to Existing pipeline
network

XYZ Field

• Subsea Production System
(Wellhead, Flowline, Manifold,
Umbilical)
• Processing Facilities (Receiving &
Separation, Gas compression &
treatment, Condensate Treatment,
Gas & Condensate Transfer, Utility)

Subsea Layouts - FPU

Development options preliminary comparison
Characteristic
Flowline system

SWP

FPU

Longer infield flowline system
Subsea layout less exposed to geohazards

•Larger deck area and load capacity permit
easier expansion;
•Allows storage of liquids

Expandability

HSE

•Risks for personnel working offshore for long
periods during hook up and commissioning
activities (moreover possible SIMOPs)

Requires heavy decommissioning activities

•Residual value
•Leasing scheme possible

Contractual scheme
Schedule

•SSIV system less effective (long distance from
FPU)
•Flexible risers less protected from ship impact
than SWP risers

•Complex riser base for export line due to
diameter limit on flexible riser (16” ID)

Subsea system
Decommissioning

•More complex riser system (need of dynamic
sections for risers and umbilicals)

In case of modular deck system, this requires
long hook up and commissioning activities

Operability/ piggability

•Pigging of export line requires support vessel
and subsea pig launcher because of complex
riser base

Constructability

•Possible availability of existing FPU for
reconversion

Pros

Cons

Shore Approach Options

PLANT-8

Total Site Visit - Objectives
PLANT-6

SHORE-1



Mahakam North Area Facilities (Nubi
Complex)
SHORE-2

PLANT-4



PLANT-7

Peciko Offshore Facilities
PLANT-5



Senipah Facilities



Sapi Facilities



New Area near Senipah

90 Km

70 Km
PLANT-2

XYZ FIELD

Shore-1 Approach – Preliminary Evaluation
PRO’S

 No necessity of land acquisition
 Low environmental impact (no need
to create a new ROW)
 Low populated area

CON’S

 Longer sea-line route
 Possible off-shore crossings

Shore Approach Shore-2 – Preliminary Evaluation
PRO’S

CON’S

 Easy connection directly to 42”
pipeline
 No necessity to interface with other
operators for the shore approach
works
 Relatively low populated area
 Short sea-line route

 Necessity of land acquisition
 Longer on-shore line route
 Higher environmental impact (need
to create a new ROW)
 Necessity of off-shore crossing
existing lines
 Possible local community issues

Deep vs Shallow Water
Offshore vs Onshore Process

Wet vs Dry Tree

Contoh Studi Konseptual

12/10/2013

Contoh Studi Pre-FEED:
Pemilihan Skenario Pemilihan ROW Pipa yg Optimal
PT. Siak
Seraya

PT. Surya Dumai
Industri

Recreation
Forest

PT. Surya Dumai
Agrindo

Limited Production Forest

Community
Forest

Community
Forest

PT. Arara Abadi

PT. Arara
Abadi

Limited Production Forest
PT. Titian Tata Pelita

PT. Darma Wungu
Guna
SAKAI
VILLAGE

PT. Darmali
Jaya
Lestari
PT. Tumpuan

PT.
Murini
Wood
Indah
Industry

PT. Rimba
Rokan
Limited
Lestari
Production
Forest

Contoh Studi Konseptual
(kontrak dengan Engineering Company )
The result of Pre-FEED work and G&G Survey will be used as basis
for FEED work i.e. :
1.0

2.0
3.0
4.0
5.0
6.0

Concept Studies
1.1 Pipeline Design Documents
1.2 Top Side Facilities Engineering Document
1.3 Corrosion and Material Studies
1.4 Hydraulic Studies
1.5 Miscellaneous
Geophysical Survey (Platform Location and Pipeline Route)
Geotechnical Survey (Platform Location and Pipeline Route)
Third Party Reports
Metocean Data
AMDAL Studies

Contoh Studi Konseptual
(kontrak dengan Engineering Company )
Organization Chart

Contoh Studi Konseptual
(kontrak dengan Engineering Company )
Manpower Loading

FEED

Tahapan Rekayasa Desain (FEED)


Kegiatan pada tahap rekayasa desain (biasa disebut FEED; Front End Engineering
Design) adalah kegiatan rekayasa (definition engineering) terhadap Fasilitas
Produksi untuk suatu Proyek tertentu yang disesuaikan dengan rencana jangka
panjang yang tertuang pada dokumen POD :
− Fit for purpose design dengan mempertimbangkan Safety, Life Cycle Cost,
Reliability, Availability dan Maintainability
− Estimasi biaya Konstruksi Proyek
− Estimasi jadwal pelaksanaan Konstruksi Proyek
− Strategi Pengadaan, LLI (Long Lead Items), targer TKDN (Tingkat Kandungan
Dalam Negeri)
− Dokumen Lelang kontraktor Pelaksana EPC
− Update Risk Register, potensi resiko pelaksanaan EPCI dan rencana
antisipasinya



Kegiatan survei lokasi (geoteknik dan geofisika) yang lebih spesifik dapat dilakukan
secara paralel dengan proses evaluasi POD, dimana data yang dihasilkan
merupakan faktor penting untuk pelaksanaan rekayasa desain.

Contoh Studi FEED
(kontrak dengan Engineering Company )
“tage : P e-FEED Opti izatio “tudies a d o espo di g
development of Project Basis of Design; Scope Groups includes (scope
further detailed in CTRs) :






Facilities Optimization (Mainly Process Studies)
Facilities Operability Study
Pipeline Flow Assurance (Mainly Process Studies)
HAZID and Development of Overall Risk Register (Project
Risk/HSE/Process Safety)
• Operations Philosophy, Operations Reference Plan for field life
(shutdown, maintenance, inspections, etc)
• Preparation of Project Basis of Design

Contoh Studi FEED
(kontrak dengan Engineering Company )
“tage : The pu pose this do u e t is to o tai a detailed p oposal fo the P eFEED Opti izatio “tudies a d FEED/Basi E gi ee i g fo the platfo s a d
pipeline.
The deliverables from this contract will form the basis for the EPC/EPCI bid
package. FEED/Basic Engineering scope which includes :
• Multidiscipline; Process, Process Safety, Piping/PDMS, Structural/Architecture, Electrical,
Instrumentation, Telecom, Corrosion, Mechanical/Rotating, Procurement, PMT and Cost
Estimation.
• Assist in preparation of EPCI Tender Documents
• Preparation of RFQ for LLI, vendor review (max. 5 bids each). COMPANY intends to
procure the Long Lead Items. Orders will be novated to the EPCI CONTRACTOR
• Liaise with 3rd party design agency who will verify FEED Package
• Constructability Engineering
• Cost Estimate (+/- (10 – 15) %)
• Preparation of EPCI Schedule – Level 2
• Safety Design Reviews
• Provide RFQ for specific materials. Contractor shall consider future expansion with
potential to bring in gas from adjacent field

Contoh Studi FEED
(kontrak dengan Engineering Company )
FEED ENGINEERING DESIGN WORK FLOW
The key deliverables and activities throughout the lifecycle of a
typical / generic FEED project is broken divided into 6 (six) phase :

1.
2.
3.
4.
5.
6.

Scope Definition and Engineering Execution Strategy
Commencement of FEED Design
Initial FEED Development and Hazard Identification
Initial Design Review and Audit
FEED Design Approval
Final Reviews and FEED Report Compilation

Phase 1 : Scope Definition and Engineering Execution Strategy
Preparation for commencement of detail engineering. To evaluate FEED deliverables to ensure
engineering is sufficiently mature for detail design to progress in a controlled and minimal change
environment. To confirm Engineering Execution Plan.

No.

Activities / Deliverables

Description

1

Engineering Execution Plan & Engineering
Organization Chart

Create Engineering Execution Plan complete with key supporting documents /information.

2

Preparation / Validation of Conceptual Study
Report / BoD

Confirm maturity of Conceptual Design report, identify any areas of concern and ensure these are
captured on the Technical Risk Register.

3

Project Baseline Standard

Establish which codes, standards and specifications are to be utilized, e.g. Corporate, project, client, and
confirm procedure. Include in Engineering Execution Plan and/or Discipline Job Design Specifications.

4

Engineering Audit Schedule

Create formal schedule to identify when technical integrity audits, design reviews, HAZID, HAZOP, etc are
to be carried out. Align to Level 3 Engineering Plan and include in Engineering Execution Plan.

5

Technical Risk Register

Create formal Technical Risk Register identifying all possible risks associated with the engineering design.

6

Integrated Engineering Systems

Agree engineering design tools to be used and confirm that system, hardware, software and support is
available, include PDMS, survey methods, dimensional control, techniques, etc.

7

QRA (Quantitative Risk Assessment) & FRA
(Fire Risk Assessment) Strategy

Establish status of QRA, FRA, and Emergency Escape & Rescue Assessment (EERA) information and
confirm methodology for timely delivery into engineering design process.

8

Discipline Job Design Specification

Define the key project specific design parameters and operational constraints that are applicable to the
appropriate discipline for the detailed design of the project. To identify key individuals, roles and
responsibilities, design tools, key codes and standards, etc.

9

Level 3 Engineering Plan

Agree work breakdown structure, develop CTRs and create level 3 integrated engineering plan covering
all disciplines. To be included in Engineering Execution Plan.

10

Confirm CE Compliance Strategy

Review and confirm strategy for CE Compliance. Ensure discipline Lead Engineers are aware of their
responsibilities and appropriate resources / measures are in place.

11

Prepare Interface Register

Develop interface register to ensure all interfaces are identified and managed.

Phase 2 : Commencement of FEED Design
To formally kick off the Engineering Design Process in accordance with the project execution plan and
ensure that key engineering strategies / philosophies are in place.

No.

Activities / Deliverables

Description

1

Safety Critical Systems / Elements and
Performance Standards

Confirm safety critical systems / elements and set appropriate performance standards,
i.e. functionality, reliability and survivability.

2

Document Distribution Matrix

Create formal documents distribution matrix to ensure all disciplines & departments
receive all necessary design information in a timely manner.

3

Structure Integrity Interface

Ensure structural integrity interfaces are identified & visible to project, e.g. Technical
Authorities, Independent Verification Bodies, etc.

4

Material Selection Report

Report defining the requirements and specifications of necessary material.

5

Hazard Management Plan

Create Hazard Management Plan identifying all key hazards, technical safety activities
and the approach to managing Major Accident Hazards in the design.

6

Piping Specifications

Develop / confirm baseline piping specifications.

7

PDMS Catalogues

Ensure PDMS catalogues are populated and available for all affected discipline.

8

CMSS Philosophy

The purpose of this task is to define and prepare the assurance activities to be
undertaken aligned with the project categorization.

Phase 3 : Initial Design Development and Hazard Identification
To develop initial design deliverables to Inter Discipline Review (IDC) stage and identify key hazard

No.

Activities /
Deliverables

Key
Discipline

Description

1

HAZID

Perform hazard identification studies, as identified on Engineering Audit Schedule /
Technical Safety Events Schedule.

Technical
Safety

2

Environmental
Impact Identification

Formal assessment of environmental aspects associated with a modification or a
change, and to propose prevention or mitigating measures.

Technical
Safety

3

PFD IDC

Issue P o ess Flo Diag a s PFD s o fo

4

Shutdown &
Blowdown
Philosophy

Explains the measures to shutdown safely and control blowdown and how this will be
achieved.

Process

5

P&ID s IDC

Issue Piping & Instrumentation Diag a
(IDC).

Process

6

Plot Plans / Layouts
IDC

Issue equipment Plot Plans / Layouts on formal Inter-Discipline Review (IDC).

7

HIPPS Review

Initial review to establish requirements for a High Integrity Pressure Protection
System

8

Dropped Object
Study

Identify and assess the potential risks to drilling, production, process equipment, and
manned areas from dropped or swinging objects. Where the consequence of a
dropped object is considered significant, to propose prevention/mitigating measures.

9

Mechanical Handling
Strategy

Develop Mechanical Handling Strategy including general approach / constraints,
platform crane limits, installation philosophy, operation and maintenance, etc.

al I te -Discipline Review (IDC).

P&ID s o fo

al Inter-Discipline Review

Process

Piping &
Layouts
Instruments
Technical
Safety
Mechanical
and Structural

Phase 3 : Initial Design Development and Hazard Identification
(continued)
No.

Activities /
Deliverables

Description

Key
Discipline

10

Particular Material
Appraisal (PMA)

Where required, i.e. he e Co po ate PMA s a e ot suita le, de elop e PMA s.

11

Cause & Effects IDC

Issue Cause & Effects for formal Inter-Discipline Review (IDC).

12

Hazardous Area Layouts
IDC

Issue Hazardous Area Layouts for formal Inter-Discipline Review (IDC).

Technical Safety

13

Fire Risk Assessment
(FRA)

Determine Fire & Explosion scenarios and identifies requirements for prevention, control and
mitigation measures.

Technical Safety

14

Blast Design Philosophy

Develop philosophy that assesses potential explosion hazards and identifies appropriate blast loadings
to be applied to the engineering design process, e.g. Vessels, pipe supports, structural steel, etc.

Technical Safety

15

TR Impairment Study

Assessment of the vulnerability of a Temporary Refuge and demonstration of its capability to sustain
life for a specified duration when under attack by fire, explosion and toxic gases.

Technical Safety

16

Equipment List & Data
Sheets

Create master project equipment list identifying all major items of tagged equipment, e.g. vessels,
pumps, motors, generators, hydrocyclones, chemical injection packages, electrical switichgear, control
panels, etc.

17

Emergency Escape &
Rescue Assessment
(EERA)

To identify requirements for emergency escape & rescue, e.g. lifeboats, escape routes, plant layout,
etc.

18

PFP / AFP Philosophy

Develop philosophy that identifies requirements for Passive Fire Protection (PFP) and/or Active Fire
Protection (AFP)

Technical Safety

19

Power System Analysis

Check power system capacities for increase power requirements for new equipment (Brownfiled).

Electrical

20

Preliminary Weight
Report

Prepare preliminary Weight Report

Structural

PED Focal Point
Process and
Instruments

Mechanical

Technical Safety

Phase 4 : Initial Design Review and Audit
To confirm that the initial design development is robust

No.

Activities /
Deliverables

Key
Discipline

Description

1

Hazardous Area
Review

Formal Engineering discipline review of hazardous area layouts to confirm
requirements for the correct selection and location of equipment.

Technical Safety

2

P&ID Review

Fo

Process, Piping,
Technical Safety,
Instruments

3

Plot Plan / Layout /
3-D Model Review

Formal Engineering review of Plot plans / Layouts. The review shall ensure that the
layout design complies with the required technical, safety, operability and
maintainability standards. Makes sure the layout is cost effective, ensures the
constructability of the work and agrees the layout basis on which the detailed design
can proceed.

Piping and
Layouts,
Structural,
Mechanical,
Electrical,
Technical Safety,
Process

4

Cause & Effect
review

Formal review of Cause & Effects diagrams to confirm design basis and alignment
with Hazard Management Plan.

Instruments,
Process,
Technical Safety

5

Technical Audit

Obtain confirmation, by sampling of project documentation, that the engineering of
the project is to the required standard and the free from errors.

al E gi ee i g dis ipli e e ie of P&ID s to o fi

desig

asis.

Independent

Phase 5 : FEED Design Approval
To F eeze the P o ess desig , a d de elop depe de t desig & p o u e e t a ti ities

No.

Activities /
Deliverables

Description

Key
Discipline

1

Final Design review

Demonstration that all of the design and review activities relevant to achieving design integrity have
been performed.

Technical Safety

2

PUWER Assessments

Conduct initial PUWER (Provision and Use of Work Equipment Regulations) assessment typically by
review of PDMS model and/or vendor / equipment supplier information received to date.

Technical Safety,
Mechanical

3

HAZOP

Hazard and Operability Studies, a systemic multi-discipline study based on the applications of
guidewords to identify causes of potential hazards and operability constraints in a facility.

Process, Technical
Safety

4

Best Available
Techniques (BAT)
Report

The Final report which analyses the major environmental issues that have been considered as part of
the process to select the final option from the various alternatives considered. Thus preventing, or
eliminating, or where the alternatives are not practicable, to then limit or reduce environmental
impacts associated with the selected option.

Technical Safety

Affected
disciplines +
Construction /
Implementation
Group

5

Constructability
Review

Conduct formal Constructability Reviews to ensure safe and efficient installation of plant & equipment.

6

P&ID AFD

Issue Approved For Design (AFD) Process and Instrumentation Diagrams.

7

Cause & Effects AFD

Issue Approved For Design (AFD) Cause & Effects

8

Process Data Sheets
AFD

Issue Approved For Design (AFD) Process Data Sheets

Process

9

HP / LP Interface
Listing

Identify all HP / LP Interface on formal register and ensure that all have been addressed satisfactorily
via HAZOP and/or individual reviews.

Process

10

HOLDs Register

Develop register to record & manage post AFD design HOLDs

Process
Instruments

Engineering
Manager

Phase 5 : FEED Design Approval (continued)
Description

Key
Discipline

SIL Assessment

Conduct assessment to determine target Safety Integrity Level (SIL). Note : Where the
target SIL is 3, then it is likely that a High Integrity Pressure Protection Systems
(HIPPS) will be required. If the value is found to be 1 or 2, then a HIPPS will not be
required.

Instruments

12

HIPPS Study

Conduct study to formally identify the performance requirements of the High
Integrity Pressure Protection Systems (HIPPS) and demonstrate that it is robust.
Should include dynamic study for a range of transient conditions.

13

Qualitative Risk
Assessment (QRA)

Multi-disciplinary study of hazards, the likelihood of their occurrence and potential
consequences in terms of harm to people and the environment.

14

HIPPS Reliability
Study

Conduct study to formally demonstrate that the High Integrity Pressure Protection
Systems (HIPPS) complies with the reliability & availability criteria for the Project, e.g.
as stipulated in the performance standard.

Instruments

15

Flow Assurance

Conduct flow assurance studies to demonstrate the process design under a range of
flow condition, i.e. start-up to 100%

Process

16

EDAS (Engineering
Delivery Assurance
System) Stage Gate
Reviews

Demonstrate adherence to the EDAS Task Performance Criteria appropriate for
Project Category

Engineering
Manager

17

Technical Peer
Review

Demonstrate adherence to the EDAS Task Performance Criteria appropriate for the
Project Category and to ensure that engineering personnel are aware of EDAS
requirements and adequately explain how those requirements are being fulfilled.

Engineering
Manager

No.
11

Activities /
Deliverables

Process
Technical
Safety

Phase 6 : Final Reviews and FEED Report Compilation
To ensure all final design deliverables are completed and that client and statutory obligations are
satisfactorily resolved.

No.
1

Activities /
Deliverables
FEED Report

Description
Collate all disciplines inputs and finalize study report

Contoh FEED Deliverable

Key
Discipline
Project
Management

Contoh Studi FEED
(kontrak dengan Engineering Company )
Manpower Loading

Contoh Studi FEED
Organization Chart FEED Project

Contoh Studi FEED

Multidiscipline Engineering

Contoh Studi FEED

Code & Standard

Contoh Studi FEED
Code & Standard

Contoh Studi FEED
Code & Standard

Contoh Studi FEED

Software yang digunakan

Contoh Studi FEED (kontrak dengan Engineering Company )
3D Model

Contracting Strategy - Sample

Contracting Strategy – Sample
XYZ DEVELOPMENT PROJECTS
Jackets

Topsides

Management, Project Definition,
Contract Preparation

COMPANY

PT. SURVEY CONTRACTOR

Survey

PT. ENGINEERING CONTRACTOR)

Basic Engineering

PO 001
STRUCTURAL STEEL

Detail Engineering

Procurement / Supply

EPC2

EPC1

EPC3

PO 002
VALVES

Construction

PO 003
PRESSURE VESSEL - SS

Pre-Commissioning

PO 004
PRESSURE VESSEL - CS

Tie-ins & Modification to existing
platform

Transportation & Installation

Pipelines

EPC4

Hook Up

Commissioning

Start-Up

COMPANY COMMISSIONING TEAM / CONTRACTORS & Supplier Assistance

COMPANY START-UP TEAM

PO - Scope of Work
PO 001 – Structural Steel

PO 002 - Valves

Supply of:
 Tubular cans with various diameters from 26” to 68.5” with
various thicknesses from 1.0” to 2.0”
 Rolled and welded tubular with various diameters from 10.750” to
66” with various thicknesses from 0.375” to 1.0”
 Plates with various thicknesses from 12 mm to 50 mm
 Rolled structural shapes

Supply of:
 Manual Ball VALVES, Butterfly VALVES, Globe VALVES and
Check VALVES from 6” up to 20” size, Rating 150#, 600# and 900#
 Actuated VALVES from 6” up to 20” size, Rating 150#, 600# and
900#

Design codes ASME, Body material: Duplex Stainless Steel UNS
S31803 and Carbon steel.

Material designation:
 For tubular cans: API 2H
 Rolled and welded tubular: API 5L
 Plates: A36
 Rolled structural shapes: API 2B

PO 003 – Press. Vessel SS
Supply of:
 One (1) Test Separator, Carbon Steel material with Stainless Steel
Clad, fitted with internals
 Three (3) Vent KO Drums, Stainless Steel material, fitted with
internals

PO 004 – Press. Vessel CS
Supply of:
 Three (3) Close Drain Drums, Carbon Steel material, internally
coated, cathodic protection installed inside
 Three (3) Open Drain Drums, Carbon Steel material, internally
coated, cathodic protection installed inside

EPC – Scope of Work
EPC1 - Jackets
2(two) tripod WHP and 1 (one)
four legs CPP jackets and
appurtenance.
Each tripod jacket weight approx.
800 Metric tons and four legs
jacket weight approx. 1250
Metric tons.
 Detailed engineering, site
survey and interface
management.
 Main structural steel free
issued by COMPANY.
 Procurement of all the
remaining steel, anodes, piles,
conductor pipes.
 Construction of the two (2)
tripod jackets and one (1) four
leg jacket.
 Load out and sea fastening of
the three (3) jackets and
associated piles and
conductor pipes

EPC2 - Topsides
2 (two) integrated topsides for WHP and 1 (one)
CPP
WHP Topsides each weighs approx. 750 Metric
tons and CPP topside weight approx.. 1350
Metric tons plus modifications to existing
platforms facilities.
 Detailed engineering, site survey and
interface management.
 Main structural steel free issued by
COMPANY.
 Ma ual a d a tuated al es a o e 6 f ee
issued by COMPANY.
 Procurement and supply of the main
components of the topsides and the entire
equipment for the telecommunication
system.
 Construction and pre-commissioning of the
three (3) topsides and of the entire
telecommunication system.
 Load out and sea fastening of the three (3)
topsides
 Mobilization of Marine Spread(s) for hook up
 HOOK up following installation of topsides by
EPC4.
 Assistance to COMPANY during
commissioning and start-up.
 Tie-ins and modifications works to the
existing platforms facilities, including
telemetry, control, safety systems and by
pass line.

EPC3 - Pipelines
Pipelines:
6 pipeli e app o . 6k
- 1 x 16 pipeli e (approx. 8km)
pipeline (approx. 4km)

EPC4 - Transportation and Installation
Transportation and installation of 2 (two)
integrated topsides for WHP and 1 (one)
CPP.
Water depth ranging from 50m to 75m.

 Detailed engineering, site
survey and interface
management.
 Procurement of all materials
including line pipes, anodes,
and coating materials.
 Coating and transportation of
line pipe.
 Mobilization/demobilization of
marine spread(s).
 I stallatio of 6 a d
pipeline.
 Diving works for all subsea
installations and connections.
 Pre-commissioning of the
entire pipeline network.

 Detailed engineering and interface
management.
 Mobilization/demobilization of marine
spread(s).
 Transportation of the jackets,
topsides, vent booms and telecom
masts and appurtenance to the
offshore location.
 Installation of the jackets, topsides,
vent booms, and telecom masts and
appurtenance.

EPC Potential Bidder
Potential Bidder for Jackets and Topsides:









McDermot (Batam Yard)
SMOE (Batam Yard)
Nisconi (Batam Yard)
Saipem (Karimun Yard)
Gunanusa (West Java Yard)
Bakrie Construction (West Java Yard)
Meindo (Handil Yard)
Etc.

Potential Bidder for Transportation and Installation:
No.

Barge Name

Scope

Owner

1

Sapura 3000

All scope

Sapura Acergy

2

DB 27

All scope

Mc Dermott

3

DB 30

All scope

Mc Dermott

4

Castoro 8

All scope

Saipem

5

PJW 3000

All scope

Swiber

6

LTS 3000

All scope

TL Offshore

7

Kuroshio One

All scope

Nisconi

8

Lanjiang

All scope

COOEC

9

Etc …

Tender Schedule
Start
Prequalification

Contract
Award

Contract

2 Feb ‘11

7 Mar ‘11

36 weeks

25 Jan ‘11

2 Feb ‘11

7 Mar ‘11

36 weeks

25 Oct ‘10

25 Jan ‘11

31 Jan ‘11

3 Mar ‘11

60 weeks

25 Oct ‘10

25 Jan ‘11

31 Jan ‘11

3 Mar ‘11

60 weeks

Contract
Award

Contract

3 May ‘11

10 Jun ‘11

20 months

25 Apr ‘11

3 May ‘11

9 Jun ‘11

24 months

22 Dec ‘10

15 Apr ‘11

25 Apr ‘11

1 Jun ‘11

24 mon ths

23 Dec ‘11

15 Apr ‘11

25 Apr ‘11

1 Jun ‘11

22 months

Issue CFT to

Stage 1

Stage 2

Issue RTA

Qualified Tenderers

Tender Opening

Tender Opening

to BPMIGAS

PO

Issue Media
Announcement

PO 001

21 Sep ‘10

28 Sep ‘10

7 Oct ‘10

29 Oct ‘10

25 Jan ‘11

PO 002

21 Sep ‘10

28 Sep ‘10

7 Oct ‘10

25 Oct ‘10

PO 003

21 Sep ‘10

28 Sep ‘10

7 Oct ‘10

PO 004

21 Sep ‘10

28 Sep ‘10

7 Oct ‘10

EPSC

Issue Media
Announcement

Start
Prequalification

EPC1

28 Sep ‘10

15 Oct ‘10

4 Nov ‘10

14 Dec ‘10

25 Apr ‘11

EPC2

28 Sep ‘10

15 Oct ‘10

4 Nov ‘10

13 Dec ‘10

EPC3

28 Sep ‘10

15 Oct ‘10

4 Nov ‘10

EPC4

28 Sep ‘10

15 Oct ‘10

4 Nov ‘10

Issue CFT to
Qualified Tenderers

Stage 1

Stage 2

Issue RTA

Tender Opening

Tender Opening

to BPMIGAS

Duration

Duration

EPCI
(Engineering, Procurement,
Construction, Installation)

• Kegiatan pada tahap Konstruksi adalah kegiatan pembangunan
Konstruksi fisik dari Fasilitas Produksi.
• Tahapan ini bisa dilaksanakan secara terintegrasi (biasa disebut EPC –
engineering, procurement, construction), atau dengan beberapa
Kontrak Pelaksana.
• Tahap ini diakhiri dengan kegiatan pengujian, Commissioning, dan
Start-up untuk kemudian diserahterimakan dari penanggung jawab tim
Proyek kepada penangung jawab tim operasi Kontraktor KKS.

Contractor General Obligation
The Contractor shall design, execute and complete the works in
accordance with the contract and shall remedy any defect in works. When
completed, the works shall be fit for purposes for which the works are
intended as defined in or reasonably to be inferred from the contract
The Co t a to shall p o ide the pla t, ate ials a d Co t a to s
do u e ts spe ified i the o t a a d all Co t a to s pe so el, goods,
consumables and other thing and services, whether of a temporary or
permanent nature, required in and for this design, execution completion
and remedying of defect of damage

The Works shall include any work which is necessary to satisfy the
requirements of Good Engineering and Construction Practices and the
Specification

All other work which (although not mentioned in the contract) is
necessary for stability or for the completion, or safe and proper operation
of the works
The Contractor shall be responsible for the adequacy, stability and safety
of all offsoe site operations of all methods of construction and all the
works
The Contractor shall, whenever required by the company, submit details
of the arrangements and methods which the contractor proposes to
adopt for the execution of the works. No significant alteration to these
arrangement and methods shall be made without this having previously
been notified to and approved by the company (acting reasonably)

ISI KONTRAK EPCI - contoh
DAFTAR ISI
Dokumen Tandatangan Kontrak
1.0 Kontrak
2.0 Pekerjaan
3.0 Pemberitahuan
4.0 Jangka Waktu dan Pemutusan
5.0 Penghentian Sementara Pekerjaan
6.0 Kompensasi
7.0 Penagihan dan Pembayaran
8.0 Tanggungjawab Kontraktor dan Perusahaan
9.0 Jaminan
10.0 Manajemen /Pemeriksaan Mutu
11.0 Asuransi
12.0 Ganti Kerugian
13.0 Pemenuhan Jadwal Kontrak/Ganti Rugi Keterlambatan
Pengiriman
14.0 Kandungan Lokal
15.0 Nilai Kontrak
16.0 Jaminan Pelaksanaan
17.0 Hukum Yang Mengatur
18.0 Penyelesaian Sengketa
19.0 Pajak dan Bea
20.0 Pemenuhan Hukum Yang Berlaku

TABLE OF CONTENTS
Contract Signature Document
1.0 The Contract
2.0 The Work
3.0 Notices
4.0 Term and Termination
5.0 Temporary Suspension of the Work
6.0 Compensation
7.0 Invoicing and Payment
8.0 Contractor and Company Responsibilities
9.0 Warranty
10.0 Quality Management/Inspection
11.0 Insurance
12.0 Indemnification
13.0 Contract Schedule Compliance/Late Delivery Charges
14.0
15.0
16.0
17.0
18.0
19.0
20.0

Local Content
Contract Value
Securities
Governing Law
Settlement of Disputes
Taxes and Duties
Compliance with Applicable Law

ISI KONTRAK EPCI - contoh
DAFTAR ISI

TABLE OF CONTENTS

21.0 Kesehatan, Keselamatan dan Lingkungan (“KKL”)

21.0 Health, Safety and Environment (“HSE”)

22.0 Keadaan Kahar

22.0 Force Majeure

23.0 Etika Bisnis dan Pembayaran kepada Pejabat

23.0 Business Ethics and Payments to Officials

24.0 Catatan dan Audit

24.0 Records and Audits

25.0 Alas Hak /Kepemilikan atas Pengembangan-pengembangan
Kontraktor
26.0 Pengalihan dan Sub-kontrak

25.0 Title/Ownership of Contractor Developments

27.0 Kerahasiaan, Publisitas dan Pengungkapan

27.0 Confidentiality, Publicity and Disclosure

28.0 Dokumen-dokumen Yang Bertentangan

28.0 Conflicting Documents

29.0 Kewajiban-kewajiban Yang Berlanjut

29.0 Continuing Obligations

30.0 Keterpisahan

30.0 Severability

31.0 Pengesampingan

31.0 Waiver

32.0 Keseluruhan Kontrak dan Perubahan Kontrak

32.0 Entire Contract and Contract Modification

33.0 Bahasa

33.0 Language

34.0 Data Yang Disediakan Perusahaan

34.0 Company Supplied Data

35.0 Operasi-operasi di Lepas Pantai

35.0 Offshore Operations

36.0 Pembatasan Tangungjawab

36.0 Limitation of Liability

37.0 Bagian-bagian

37.0 Counterparts

26.0 Assignment and Subcontracting

ISI KONTRAK EPCI - contoh
LAMPIRAN-LAMPIRAN

EXHIBITS

Lampiran A Rincian Khusus Kontrak

Exhibit A

Contract-Specific Details

Lampiran B Penjelasan Proyek

Exhibit B

Project Description

Lampiran C Lingkup Pekerjaan

Exhibit C

Scope of Work

Lampiran D Penyelesaian Pekerjaan

Exhibit D

Completion of Work

Lampiran E Kompensasi

Exhibit E

Compensation

Lampiran F Ketentuan-ketentuan Administrasi dan Umum

Exhibit F

Administration and General Requirements

Lampiran G Data Yang Disediakan Perusahaan

Exhibit G

Company Supplied Data

Lampiran H Jadwal Kontrak

Exhibit H

Contract Schedule

Lampiran I Perubahan

Exhibit I

Changes

Lampiran J Bahan Yang Disediakan Perusahaan

Exhibit J

Company Furnished Material

Lampiran K Formulir Perjanjian Ganti Kerugian Perusahaan Induk/
Korporasi

Exhibit K

Form of Parent Company / Corporate Indemnity
Agreement

Lampiran F Bentuk Jaminan Pelaksanaan

Exhibit L

Form of Performance Bond

Lampiran M Ketentuan-ketentuan Kesehatan, Keselamatan dan
Lingkungan

Exhibit M

Health, Safety & Environmental Requirements

Lampiran N Kode Etik Dan Perilaku Bisnis Perusahaan

Exhibit N

Company’s Code of Business Ethics and Conduct

Lampiran O Rincian-rincian Armada Kontraktor

Exhibit O

Contractor’s Spread Details

Exhibit Scope of Work – contoh :
1. GENERAL
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9

Introduction
Nomenclature
Facilities
Contract Objective and Work
Schedule
Responsibilities
Conformance of the Work
Co t a to s E e utio Pla
Structure of Scope of Work

Exhibit Scope of Work – contoh :
2. SCOPE OF WORK
2.1 WBS-01-01-00-00 Management and Administration Activities
2.1.1 Project Management
2.1.2 Interface Management
2.1.3 Quality Management
2.1.4 HSE Management
2.1.5 Engineering Management
2.1.6 Procurement & Material Management
2.1.7 Construction and Commissioning Management
2.1.8 Marine Activities Management
2.1.9 As-Built Management
2.1.10 Information Management
2.1.11 Regulations, Certificates & Permits
2.1.12 Project Control
2.1.13 Supporting Service

Exhibit Scope of Work – contoh :
2.2 WBS-01-02-00-00 Engineering Activities
2.2.1 General Engineering Activities
2.2.2 Detailed Engineering Activities
2.3 WBS-01-03-00-00 Procurement and Material Management
2.4 WBS-01-04-00-00 Manufacturing and Fabrication
2.4.1 Subsea Structure Fabrication
2.4.2 Subsea Tie-In Spool Fabrication
2.4.3 Coatings and Anodes
2.4.4 Contractor Representing, Inspection and Testing
2.4.5 Load Out, Seafastening and Transportation

Exhibit Scope of Work – contoh :
2.5 WBS-01-05-00-00 Installation
2.5.1 General Installation Requirements
2.5.2 Mobilization
2.5.3 Surveys and Positioning
2.5.4 Seabed Preparation
2.5.5 Pipeline/Cable Crossings
2.5.6 Electro/Hydraulic (E/H) Flying Leads Instalation
2.5.7 Subsea Structures
2.5.8 Tie-In Spool Metrology and Installation
2.5.9 Pipeline System Pre-commissioning
2.5.10 Subsea Production System Function Testing
2.5.11 Mechanical Completion and Handover

Exhibit Scope of Work – contoh :
2.6 WBS-01-06-00-00 As Built Activities and Final Documentation
2.6.1 As-built Scope of Work
2.6.2 As-built Procedures
2.6.3 As-built Register
2.6.4 Schedule
2.6.5 Vendor Data
2.6.6 As-built Survey
2.6.7 Final Documentation

Source : IFP Training

Cycle in EPCI
FEED

Tender by KKKS

E

P C I

Detailed
Engineering

- Specification
- Calculation
- Data Sheet
- Drawing
- MTO

Vendor A
Vendor ....

Procurement

Construction
Installation

- Procure MTO
- Expediting
- A i al Mat l & E pt

Vendor X

- Procesure, Construction Eng & Shop
Drawing
-Advance Constructability
- Resources : Manpower& Equipment

- Procedure, Installation Engineering, Inst
Drawing
- Installation Vessel
- Installation Requirement & Aid

-Data sheet
-Vendor Data
-Vendor Engineering

Source : JGC

DETAILED ENGINEERING

Source : Amec

Deliverable Detailed Engineering (Semua Discipline : Process, Safety, Mechanical, Electrical,
Instrument, Piping, Structure, Pipeline) adalah pendetailan lebih lanjut dari Deliverable
FEED baik Design Calculation, Specification, Data Sheet dan Drawing yang telah dilakukan
validasi :
• data pre-engineering survey,
• verifikasi dengan Operation & Maintenance,
• review constructibility termasuk instalasi,
• verifikasi data vendor
• Interface
dan status dokumen akhir adalah AFC (Approved for Construction)

PROCUREMENT

CONSTRUCTION

- Ready for Commissioning Certificate
- Mechanical Completion (All Subsys tem)
- Operational Test Certificate
- Ready for Start Up Certificate
- Handover State
- Oil/ Gas in
-Ready for Start Up
- Provisional Acceptance Certificate
- Final Acceptance Cerificate

The Top 10 Mistakes in Project Management :
1.
2.
3.
4.

Project Scope is too big
The Schedule is too ambitious
The P oje t does t follo a sta da d PM Methodolog
Communication breakdowns between the Project Manager
and The Team
5. Risk Assessment process was skimped
6. The Team Members are not productive
7. Resources have been over-allocated
8. Not cracking down hard enough on productivity leaks
9. Incomplete data
10. Not sa i g NO