B2.5. Anang-20140320 PLN on Renewable Energy for Development - LIPI
RENEWABLE ENERGY POWER SUPPLY FOR DEVELOPMENT
Anang Yahmadi
Senior Manager for Geothermal of PT PLN (Persero)
Indonesia National Workshop on Accessible and Sustainable Energy
Jakarta, March 19-20, 2014
(2)
Gas
Geothermal
Hydro
LNG
HSD
MFO
Coal
•
Brief Intro a out PT PLN Persero PLN
•
Renewable Energy potential
•
The Planning in the pipeline
•
The challenge
•
Closing Remarks
1
(3)
PLN AS STATE OWNED WITH THE SUBSIDIARIES
PT PLN Geothermal
Geothermal Energy
Generation
PT PLN Batubara
Coal Supplier for
PLN
PT Prima Layanan
Nasional Enjiniring
Engineering and
Construction
Services
PT PLN Tarakan
Regional Fully
Integrated Electric
Utility
PT PLN Batam
Regional Fully
Integrated Electric
Utility
PT Indonesia Power
Electricity Generation
100% Owned by GoI
PT PLN (Persero)
PT Haleyora Power
Ministry of State Owned
Enterprises (MSOE)
Ministry of Energy and
Mineral Resources (MEMR)
Ministry of Finance (MoF)
National Development
Planning Agency
(BAPPENAS)
Oversight
Majapahit Holding B.V.
Financial Institution
PT Pembangkitan
Jawa Bali
Electricity Generation
PT Pelayaran
Bahtera Adhiguna
Shipping Activities
Note: Excludes Joint Ventures.
PT Indonesia
Comnets Plus
Telecommunications
for
the Electricity Sector
As holding consists of :
8 Directorates
37 Divisions level
36 Business Unit
(4)
PLN BUSSINESSES
Generation
Controls approximately 30,583 MW of
installed generating capacity, over 85%
of Indonesia’s total
Owns and operates 1,267 generation
plants
Main purchaser of electricity from
Independent Power Producers (IPPs)
Transmission
Sole provider of power transmission
in Indonesia
Approximately 36,741 kmc of
transmission lines
66,354 MVA of transmission
transformer capacity
PLN Business Segments:
Distribution
Sole distributor of electricity to end
customers in Indonesia
(1)
Approximately 685,785 kmc of
distribution lines and 36,430 MVA of
transformer capacity
Serving approximately 46 million
customers
(1) PLN is also the provider of electricity of last resort, in that if PLN is not supplying a particular area and there are no regional-owned companies, private enterprises or cooperatives that elect to supply electricity in that area, the Government is obligated to instruct SOEs (which includes PLN) to supply electricity to the area.
PLN is the wholly state-owned power utility company, the largest and the only
fully-integrated power utility company in Indonesia.
(5)
Gas
Geothermal
Hydro
LNG
HSD
MFO
Coal
•
A high potential of varies energy resources (hydro,
geothermal, biomass , solar, sea and wind) but has not
been optimally taped mainly for electricity.
•
Archipelago countries with a high electricity national
demand growth, 4 (four) provinces have electrification
ratio less than 60% and thousands islands without
access electricity
•
Generated power in the remote areas mostly by diesel
power plant, means expensive and susceptible fuel
supply
•
Trend of cost reduction and efficiency improvement
on RE technologies
•
Policy and target decision to increase the role of
renewable energy
4
(6)
MAP OF 29 GW GEOTHERMAL POTENTIAL
276 locations mostly in Sumatera and Java
Source : Geology Agency, MEMR (2010)
Installed
Ready to be implemented
Detailed Survey
Preliminary y survey
RESOURCE (MW)
%
RESERVE (MW)
%
Speculative
Hypothetical
45.36%
Possible
Probable
Proven
54.64%
8.780
4.391
12.756
823
2.288
13.171
15.867
29.038
86 LOCATIONS
13.516 MW
27 LOCATIONS
1.767 MW
8 LOCATIONS
115
MW
55 LOCATIONS
2.519 MW
26 LOCATIONS
954 MW
3 LOCATIONS
75
MW
71 LOCATIONS
10,092 MW
(7)
6
ACEH:
5.062 MW
SUMUT:
3.808 MW
SUMSEL, JAMBI,
BENGKULU & LAMPUNG:
3.102 MW
JABAR:
2.861 MW
JATENG:
813 MW
SUMBAR & RIAU:
3.607 MW
JATIM:
525 MW
BALI NUSRA:
624 MW
KALBAR:
4.737 MW
KALSELTENGTIM:
16.844 MW
SULUTTENG:
3.967 MW
SULSELRA:
6.340 MW
MALUKU:
430 MW
PAPUA:
22.371 MW
HIDROPOWER POTENTIAL MAP
75 GW (HPPS 1983) with 12,9 GW mostly in Kalimantan and Papua
(8)
ELECTRIFICATION RATIO (2012)
Electrification Ratio
Target
Realization
PLN
71.2%
73.1%
(PLN+ Non PLN)
73.7%
75.9%
PAPUA BARAT: 66.5%
SUMUT: 87.2%
SUMBAR: 76.9%
RIAU:78.4%
SUMSEL: 66.7%
BENGKULU: 71.2%
BABEL: 92.8%
LAMPUNG: 70.0%
DKI: 96.4%
BANTEN: 80.5%
JABAR: 75.9%
JATENG: 77.8%
JAMBI: 70.0%
DIY: 77.8%
JATIM: 75.2% BALI:74.5%
NTB: 53.3%
NTT: 53.2%
KALBAR: 89.7%
KALTENG: 56.6%
KALSEL:75.9%
KALTIM:75.9%
SULUT: 76.4%
GORONTALO: 60.7%
SULTENG: 66.0%
SULTRA: 68.8%
SULSEL: 81.2%
MALUT: 85.4%
MALUKU: 77.3%
PAPUA: 33.1%
SULBAR: 89.3%
NAD: 88.8%
(9)
Power Plant Capacity:
•
Non RE Power Plant : 86 %
•
Renewable Energy Power Plant : 14 %
Generation (2013):
•
Fossil power plant is dominant by 91 % (Coal, Oil and
Gas ).
•
Share of renewable energy by 9 % only (2013) and plan
to increase by 16 % on 2022.
Generation Share (2013)
Existing Total Capacity 38,320 MW
14006
7704
3224
3267
564
3524
4797
645
291
60
745
345
0
2000 4000 6000 8000 10000 12000 14000 16000
Coal Steam PP
Combine Cycle PP
Gas Turbine PP
Diesel PP
Geothermal PP
Hydro PP
IPP
PLN
Geothermal,
3.5%
Hydro,
10.2%
Coal STPP,
46.6%
CCPP,
21.7%
GTPP,
9.2%
Diesel,
8.8%
Power plant composition (35.617 MW in 2012)
8
STATUS OF POWER GENERATION
(10)
ELECTRICITY DEMAND PROJECTION (2013-2022)
Average annual growth by 8.4%
9
Sumatera: 10,6%
26
TWh
66
TWh
TWh
IT :
10,8%
18
44
TWh
JB :
7,6%
144
TWh
275
TWh
2013 2022
TWh
TWh
188
385
Kalimantan: 10,7%
Sulawesi: 10,8%
Indonesia: 8,4%
Papua: 10%
Maluku: 10,9%
Nusa Tenggara: 11,1%
Year
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
Demand (TWh)
189
208
227
246
266
286
308
332
358
387
(11)
Gas
Geothermal
LNG
HSD
MFO
Coal
To support the National Policies on utilizing RE development for electricty :
•
President Regulation 5/2006: Contribution of renewable in 2025;
•
President Decree 4/2010 : PT. PLN to Accelerate 10,000 MW FTP II;
•
MoEMR Regulation 1/2012 : List of FTP II ( Geothermal Power Plants 49 %);
•
MoF Regulation 139/2011 : Guarantee for
PLN’s
Viability for IPP Project included in
FTP II;
•
MoEMR Regulation 2/2011 jo MoEMR Regulation 22/2012 : Assignment to PLN to
purchase electricity from geothermal power plant and its ceilings price;
•
MoEMR Regulation 4/2012 : FIT for small scale RE
IPP’s
Consistently increasing the role of RE as capacity expansion: to supply electricity demand
growth, to meet the electrification ratio target and to acheive the target of Fossil Fuel
Consumption Reduction Program.
The development of renewable energy currently is not based on
least
ost
but on the
readiness of the scheme
PLN Policies on RE Development (Inc. Geothermal)
(12)
Hydro
Geothermal
Gas
LNG
Fuel Oil
PLN’s
10 YEARS ELECTRICITY DEVELOPMENT PLAN (RUPTL 2013
–
2022)
( Share of RE will increase from 9 % to 19 % by 2022 )
11
Total 60 GW additional capacity in the period of
(2013
–
2022) consisting of:
Coal fired
: 38 GW
Hydro
: 6.5 GW
Geothermal
: 6.0 GW
Combined cycle
: 5.0 GW
Gas Turbine/Engine : 3.7 GW
Other
: 0.3 GW
Coal will be more dominant and geothermal is
expected to increase significantly (from 4% to 11%)
Fuel Mixed Projection
Capacity Expantion Plan
(13)
GEOTHERMAL CAPACITY EXPANSION PLAN (2013-2022)
•
Expected commissioning years
mostly after 2016.
•
By
regulation,
Geothermal
development will be dominated
by IPP (96)
•
Mostly, 93%, developed in Java
Bali and Sumatra system as
base loader generation power
plant.
12
YEAR
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
TOTAL
SUMATRA
0
0
0
55
330
445
360
490
405
770
2855
JAVA-BALI
0
55
30
30
225
0
1275
110
220
855
2800
OUT OF JBS
0
5
0
0
25
50
30
50
45
200
405
TOTAL
0
60
30
85
580
495
1665
650
670
1825
6060
(14)
13
13
RENEWABLES NON GEOTHERMAL AND LARGE HYDRO DEVELOPMENT PLAN
( Small Hydro and Solar PV will dominate)
No
Renewable Energy
Type/technology
Unit
Years
Total
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
1
Small Hydro
MW
40
99
113
112
101
185
188
201
189
260
1488
2
Solar PV
MWp*)
6
84
125
150
100
75
75
80
80
80
855
3
Wind
MW
0
10
50
50
15
15
20
20
25
25
230
4
Biomass
MW
22
40
90
35
40
40
45
45
50
40
447
5
Ocean
MW
0
2
0
0
5
5
5
5
5
27
54
6
Bio-fuel
MW**)
10
15
15
14
8
7
7
8
9
8
101
0
500
1000
1500
2000
2500
3000
3500
2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
Small Hydro
Solar PV
Biomass
Wind
Bio-fuel
Ocean
Small RE Expansion Plan
Notes :
The small scale RE power plants (up to10
MW) is not necessarily put in the RUPTL
Solar PV target up to 2015 is 1
st
Phase of
1000 islands program and PV to be
developed by IPP. Plan for following years is
indication only.
Bio Fuel is estimated based on equivalent of
fossil fuel consumption on existing power
plant . Higher target expected in relation to
the bio fuel acceleration program.
(15)
DEVELOPMENT OF MINI HYDROPOWER PLN + IPP (MARCH 2013)
Number
Installed Capacity (kW)
N
West Indonesia
39
26,570
Operation
34
15,582
Construction
0
-Procurement
0
-Study
5
10,988
East Indonesia
75
117,185
Operation
43
52,330
Construction
3
5,500
Procurement
17
37,700
Study
12
21,655
Java-Bali
36
72,768
Operation
36
72,768
Construction
0
-Procurement
0
-Study
0
-Total Indonesia
150
216,523
Total Operation
113
140,680
Total Construction
3
5,500
Total Procurement
17
37,700
Total Study
17
32,643
Maret 2013
Region
PLN
Number
Installed Capacity (kW)
N
West Indonesia
90
570,315
Operation
7
21,095
Construction
13
100,858
Financing
25
161,120
PPA Process
14
85,668
Proposal
31
201,574
East Indonesia
55
193,920
Operation
13
37,640
Construction
10
31,700
Financing
13
48,700
PPA Process
9
39,780
Proposal
10
36,100
Java-Bali
94
302,383
Operation
9
2,530
Construction
13
28,180
Financing
15
70,790
PPA Process
30
93,684
Proposal
27
107,199
Total Indonesia
239
1,066,618
Total Operation
29
61,265
Total Construction
36
160,738
Total Financing
53
280,610
Total PPA Process
53
219,132
Total Proposal
68
344,873
IPP
Region
(16)
SOLAR PV DEVELOPED BY PLN (2012)
Contact us : PT PLN (Persero), Jl. Trunojoyo Blok M I/135, Jakarta 12160 Phone : 7261875 Fac :
62-21-7221330
RIAU&KEPRI Location: TAREMPA ANAMBAS Island Capacity: 200 kWp Status : Operation
RIAU&KEPRI Location: MORO. KARIMUN Island Capacity: 200 kWp Status : Operation
EAST KALIMANTAN Location: SEBATIK SEBATIK Island Capacity : 300 kWp Status : Operation
EAST KALIMANTAN Location: BUNYU BUNYU Island Capacity : 150 kWp Status : Construction
EAST KALIMANTAN Location: DERAWAN Island Capacity : 170 kWp + Battery Status : Operation on March 2011
WEST SUMATERA Location: SIMALEPET SIPORA Island Capacity: 40 kWp Status : Operation
WEST NUSA TENGGARA Location : GILI TRAWANGAN Capacity : 200 kWp
Status : Operation on Feb 2011
SOUTH SULAWESI Location: TOMIA Island Capacity : 75 kWp
Status : Operation on May 2011
MALUKU
Location: BANDA NAIRA Capacity : 100 kWp
Status : Operation on Dec. 2010 PAPUA
Location: SAONEK
RAJA AMPAT Islands Capacity : 40 kWp
Status : Operation on Dec. 2010 NORTH SULAWESI
Location : BUNAKEN Island Capacity : 335 kWp + Battery Status : Operation on Feb. 2011 NORTH SULAWESI
Location : MARAMPIT Island Capacity : 50 kWp
Status : Final Construction NORTH SULAWESI
Location : MIANGAS Island Capacity : 30 kWp
Status : Operation on Oct 2011
EAST NUSATENGGARA Location: LEMBATA Capacity : 200 kWp
Status : Operation on Sept 2011 WEST SUMATERA
Location: TUA PEJAT SIPORA Island Capacity: 150 kWp Status : Operation
INDONESIA
-Average Solar Irradiation between 4
–
6 kW/m
2. Most
higher radiation is in Eastern of Indonesia
- Estimating, the radiation can generate energy about
3.7 kWh/day.
NORTH MALUKU
Location : MOROTAI Island Capacity : 600 kWp
(17)
Tourism
islands
-6 locations
- 0,92 MWp)
Outer islands
- 8 locations
-1,34 MWp)
Outer islands
( 861 locations; 379 MWp)
100 islands stage I
-36 locations
-- 7 MWp
100 islands stage II
-78 locations
-- 13 MWp
1000 islands
-- 672 locations
-- 119 MWp
IPP > 1 MWp
-- 114 locations
-- 140 MWp
OPERATION
OPERATION
OPERATION/CONSTRUCTION
FINANCING
FIT
94 locations ; 19,5 MWp (Hybrid
scheme) financing preparation
(18)
NAD: 44 lokasi, 7.4 MWp
Sumut: 27 lokasi 6.1 MWp
Sumbar:
42 lokasi 7.7 MWp
Babel: 16 lokasi 35.0 MWp
Riau: 151 lokasi 60.1 MWp
Jabar, Banten: 3 lokasi 1.1 MWp
Sulselrabar:
17 lokasi 29.7 MWp
NTB: 15 lokasi 44.5 MWp
Bali: 1 lokasi 0.3 MWp
Jateng DIY: 5 lokasi 0.7 MWp
NTT: 99 lokasi 45.2 MWp
Jatim: 12 lokasi 4.3 MWp
Lampung: 18 lokasi 2.5 MWp
Sumsel, Jambi, Bengkulu:
6 lokasi 3.4 MWp
Kalbar: 63 lokasi 40.1 MWp
Kaltim: 30 lokasi 24,9 MWp
Kalselteng: 96 lokasi 48.7 MWp
Sulut, Sulteng, Gorontalo:
39 lokasi 30.9 MWp
Maluku, Malut:
29 lokasi 33.5 MWp
Papua, Pabar:
66 lokasi 44.9 MWp
1000 ISLANDS - SOLAR PV DEVELOPMENT PROGRAM
850 MW up to 2021
PLN plan to developed Solar as an hybrid system with existing Diesel, Biomass or other RE potentials in a small islands, to respond
with GOI policy to reduce oil consumption
(19)
•
An abundant potential of Biomass using palm oil shell, bagasse, rice husk, municipal waste and
wood chips (
Biomass potential resources 50000 MW)
•
Private participation will be encourage, either as an IPP or
Excess Power
to PLN grid. (Existing
Biomass Power Plant 61 MW all IPPs)
•
PLN Pilot Plants of small scale Biomass ( cap. 500 kw up to 1 MW ) using
wood chip on
progress
.
Nias Island (1x1 MW) and Sumba Island (1x1 MW)
Preparation of Feasibility Study Final Report and design system specification
Land for fuel plantation has been approved and agreed by local government
Study on type of tree for biomass/wood fuel has been finished
Bio-fuel program in 2013 of
converting High Speed Diesel
Oil (HSD) to Biodiesel in 16
PLN Unit Wilayah with total
volume about 186.000 KL is
undergoing
BIOMASS DEVELOPMENT PLAN
(20)
West Java (Sukabumi): 2 locations, 10 & 30 MW
South Sulawesi ():
1 location, 70 MW
Bali (Nusa Penida): 1 location, < 1 MW
Yogyakarta (Samas): 1 location,
50
MW
NTT (Sumba & Timor): 2 locations, 10 & 10 MW
North Maluku :
1 location, 10 MW
•
Indonesia’s
wind power potential is not much because of average wind velocity is low (< 5 m/s).
•
Wind Power Development Program up to 2020 : 200 MW, in study and procurement stage.
(21)
Gas
Geothermal
Hydro
LNG
HSD
MFO
Coal
20
THE CHALENGES AND STAKEHOLDERS (1/2)
Government
and
Regulation
•
To create a harmonic coordination among government
institution for permits, land acquisition, land use,
national productivity, etc.
•
To provide certain, applicable and synchronous
policies and regulation.
•
To reduce the number, complexity and duration
process of permits
Key stake holder
: ministries
(MEMR, forestry,
MoF)
government
agencies, local
government
Technical
•
A long duration to achieve COD especially geothermal
and large hydro
•
To maintain natural resources
•
To have the knowledge and expertise in solar PV
technology and biomass technology
•
High risk on geothermal drilling
•
To manage the system stability due to intermittent and
high fluctuation of solar PV
•
To provide a sufficient infrastructure
•
To manage the miss match between available resource
and electricity demand
Key stake holder
: Government
agencies, PLN,
developer,
academic
(22)
Gas
Geothermal
Hydro
LNG
HSD
MFO
Coal
21
Financial
•
To obtain tariff, which is a commercially viable for
developer and acceptable for the off taker
•
To provide cheap sources of fund
•
To provide an appropriate cost and risk allocation based on
available data
•
To prioritize the lower risk and lower cost RE source such
as hydro and biomass (solar tends to decrease)
Key stake holder :
ministries (MEMR, MoF),
government agencies
(PIP), lender, banks, PLN
Capacity
•
To increase the national capacity on both skilled /expertise
human resources and institution
•
To increase the role of national capacity in RE development
•
To increase the participation small and local capacity for
appropriate portion of development
Key stake holder :
universisties, consultant,
contractor,
manufactures,PLN
Social and
environme
ntal
•
To manage the difference interest between environment
sustainability and energy security (ex. Conservation area
vs. geothermal development)
•
To provide benefit for local community to increase
economic growth and capacity building
•
To manage the local interest to become supporting factor
of the development
Key stake holder :
ministries (MEMR, MoF),
government agencies
(PIP), lender, banks
(23)
The potential of RE development in Indonesia is challenging and promising, therefore
Indonesia is attractive for RE industries
The most expected RE the contribution for electricity will be from large geothermal
and hydropower plant
For remotes and small distributed islands, the hybrid of solar PV and biomass power
plan is promising solution for electricity
PLN committed to support RE dev. due to the potentials and security of energy to
meet the demand
Synergy among stakeholders is key factors to provide supportive climate for RE
development
CLOSING REMARKS
Terima kasih - Thank
You)
(1)
NAD: 44 lokasi, 7.4 MWp
Sumut: 27 lokasi 6.1 MWp
Sumbar:
42 lokasi 7.7 MWp
Babel: 16 lokasi 35.0 MWp Riau: 151 lokasi 60.1 MWp
Jabar, Banten: 3 lokasi 1.1 MWp
Sulselrabar:
17 lokasi 29.7 MWp
NTB: 15 lokasi 44.5 MWp Bali: 1 lokasi 0.3 MWp
Jateng DIY: 5 lokasi 0.7 MWp
NTT: 99 lokasi 45.2 MWp Jatim: 12 lokasi 4.3 MWp
Lampung: 18 lokasi 2.5 MWp Sumsel, Jambi, Bengkulu:
6 lokasi 3.4 MWp
Kalbar: 63 lokasi 40.1 MWp
Kaltim: 30 lokasi 24,9 MWp
Kalselteng: 96 lokasi 48.7 MWp
Sulut, Sulteng, Gorontalo: 39 lokasi 30.9 MWp
Maluku, Malut: 29 lokasi 33.5 MWp
Papua, Pabar: 66 lokasi 44.9 MWp
1000 ISLANDS - SOLAR PV DEVELOPMENT PROGRAM
850 MW up to 2021
PLN plan to developed Solar as an hybrid system with existing Diesel, Biomass or other RE potentials in a small islands, to respond with GOI policy to reduce oil consumption
(2)
• An abundant potential of Biomass using palm oil shell, bagasse, rice husk, municipal waste and wood chips (Biomass potential resources 50000 MW)
• Private participation will be encourage, either as an IPP or Excess Power to PLN grid. (Existing Biomass Power Plant 61 MW all IPPs)
• PLN Pilot Plants of small scale Biomass ( cap. 500 kw up to 1 MW ) using wood chip on progress.
Nias Island (1x1 MW) and Sumba Island (1x1 MW)
Preparation of Feasibility Study Final Report and design system specification
Land for fuel plantation has been approved and agreed by local government
Study on type of tree for biomass/wood fuel has been finishedBio-fuel program in 2013 of converting High Speed Diesel Oil (HSD) to Biodiesel in 16 PLN Unit Wilayah with total volume about 186.000 KL is undergoing
BIOMASS DEVELOPMENT PLAN
(3)
West Java (Sukabumi): 2 locations, 10 & 30 MW
South Sulawesi (): 1 location, 70 MW
Bali (Nusa Penida): 1 location, < 1 MW Yogyakarta (Samas): 1 location, 50 MW
NTT (Sumba & Timor): 2 locations, 10 & 10 MW North Maluku :
1 location, 10 MW
• Indonesia’s wind power potential is not much because of average wind velocity is low (< 5 m/s).
• Wind Power Development Program up to 2020 : 200 MW, in study and procurement stage.
(4)
Gas
Geothermal Hydro
LNG
HSD MFO
Coal
20
THE CHALENGES AND STAKEHOLDERS (1/2)
Government
and
Regulation
•
To create a harmonic coordination among government
institution for permits, land acquisition, land use,
national productivity, etc.
•
To provide certain, applicable and synchronous
policies and regulation.
•
To reduce the number, complexity and duration
process of permits
Key stake holder
: ministries
(MEMR, forestry,
MoF)
government
agencies, local
government
Technical
•
A long duration to achieve COD especially geothermal
and large hydro
•
To maintain natural resources
•
To have the knowledge and expertise in solar PV
technology and biomass technology
•
High risk on geothermal drilling
•
To manage the system stability due to intermittent and
high fluctuation of solar PV
•
To provide a sufficient infrastructure
•
To manage the miss match between available resource
and electricity demand
Key stake holder
: Government
agencies, PLN,
developer,
academic
(5)
Gas
Geothermal Hydro
LNG
HSD MFO
Coal
21 Financial
• To obtain tariff, which is a commercially viable for developer and acceptable for the off taker
• To provide cheap sources of fund
• To provide an appropriate cost and risk allocation based on available data
• To prioritize the lower risk and lower cost RE source such as hydro and biomass (solar tends to decrease)
Key stake holder :
ministries (MEMR, MoF), government agencies (PIP), lender, banks, PLN
Capacity
• To increase the national capacity on both skilled /expertise human resources and institution
• To increase the role of national capacity in RE development
• To increase the participation small and local capacity for appropriate portion of development
Key stake holder :
universisties, consultant, contractor, manufactures,PLN Social and environme ntal
• To manage the difference interest between environment sustainability and energy security (ex. Conservation area vs. geothermal development)
• To provide benefit for local community to increase economic growth and capacity building
• To manage the local interest to become supporting factor of the development
Key stake holder :
ministries (MEMR, MoF), government agencies (PIP), lender, banks
(6)
The potential of RE development in Indonesia is challenging and promising, therefore Indonesia is attractive for RE industries
The most expected RE the contribution for electricity will be from large geothermal and hydropower plant
For remotes and small distributed islands, the hybrid of solar PV and biomass power plan is promising solution for electricity
PLN committed to support RE dev. due to the potentials and security of energy to meet the demand
Synergy among stakeholders is key factors to provide supportive climate for RE development