ANALISA PERCEPATAN DURASI PROYEK DENGAN METODE PERTUKARAN WAKTU DAN BIAYA (TIME COST TRADE OFF METHOD) (Studi Kasus : Proyek Perumahan Cemara Kuta – Medan) TUGAS AKHIR - Analisa Percepatan Durasi Proyek Dengan Metode Pertukaran Waktu Dan Biaya (Time Cost
ANALISA PERCEPATAN DURASI PROYEK DENGAN
METODE PERTUKARAN WAKTU DAN BIAYA
(TIME COST TRADE OFF METHOD)
(Studi Kasus : Proyek Perumahan Cemara Kuta – Medan)
TUGAS AKHIR
Diajukan untuk melengkapi syarat penyelesaian Pendidikan Sarjana Teknik Sipil
Oleh :
Jernih Putri N Gulo
NIM: 10 0404 090
Dosen Pembimbing :
Ir. Syahrizal, MT
NIP 19611231 198111 1 001
BIDANG STUDI STRUKTUR
DEPARTEMEN TEKNIK SIPIL
FAKULTAS TEKNIK
UNIVERSITAS SUMATERA UTARA
MEDAN
2014
KATA PENGANTAR
Puji dan syukur dipanjatkan kepada Tuhan Yesus Kristus atas kasih dan penyertaanNya, sehingga mampu menyelesaikan penulisan tugas akhir yang berjudul ANALISA
PERCEPATAN DURASI PROYEK DENGAN METODE PERTUKARAN WAKTU
DAN BIAYA (TIME COST TRADE OFF METHOD) (Studi Kasus : Proyek Perumahan
Cemara Kuta – Medan). Tugas akhir ini diajukan sebagai syarat untuk menempuh ujian
sarjana di Fakultas Teknik Jurusan Teknik Sipil Universitas Sumatera Utara.Saya sangat menyadari penulisan tugas akhir ini tidak lepas dari dukungan dan bimbingan serta dukungan dari berbagai pihak, oleh karena itu pada kesempatan ini saya ingin menyampaikan ucapan terimakasih kepada: 1.
Bapak Ir. Syahrizal, MT, selaku dosen pembimbing skripsi, dan sekretaris Departemen Teknik Sipil, Fakultas Teknik, Universitas Sumatera Utara. Bapak Prof. Dr. Ing. Johannes Tarigan, selaku ketua Departemen Teknik Sipil, Fakultas Teknik, Universitas Sumatera Utara.
3. Bapak/Ibu dosen dan staf tata usaha Departemen Teknik Sipil, Fakultas Teknik, Universitas Sumatera Utara.
4. Teristimewa Papa saya Mokoginta Gulo, Mama saya Merry Natalina Sitorus, Adik- adik saya Haga Gulo, Nislady Gulo, Satria Gulo dan Halomoan Gulo yang selalu memberikan dukungan, motivasi, dan doa.
5. Teristimewa opung, maktua, paktua, tulang, nantulang, tante, uda, abang/kakak/adik sepupu yang telah banyak membantu dan memberikan semangat selama saya di Medan.
6. Teristimewa sepupu seperjuangan saya Baginda Helbin Sitorus yang selalu membantu dan memberikan semangat selama perkuliahan maupun penyelesaian tugas akhir ini.
7. Teristimewa Faber Banjarnahor yang selalu memberikan semangat, hiburan dan doa selama penyelesaian tugas akhir ini.
8. Sahabat-sahabat tersayang Elfridani Saragih, Zefanya Hutasoit, Prisquilla Sembiring, Essy Ginting yang telah banyak memberikan bantuan, semangat, doa dan hiburan selama perkuliahan maupun penyelesaian tugas akhir ini.
9. Untuk Bang Tian yang telah mengajari saya program Microsoft Project. Serta bersama-sama dengan Bang Ruchon, Bang Cecep, Bang Freddy, Bang Sam, Kak Siska, Kak Sandy yang selalu memberikan hiburan dan jalan-jalan yang merefreshkan di sela-sela penyelesaian tugas akhir ini. i
10. Teman-teman dan abang/kakak/adik GMKI Komisariat FT USU Haposan, Yessy, Angel, Iwin, Dedy, Kak Dewi, Kak Debbie, Bang Falex, Bang Satahi dan lainnya.
11. Teman-teman seperjuangan sipil 2010 Elwis, Fander, Yahya, Freddy, Ebenezer, Grandson, Mike, Dice, Acong, Steven, Bram, Agave, Aziz, Ricky, Boris, Henry, Mardi, Badia, Nagel, Rebekka, Afrissa, Fanny, Tohap, Darwin, Fahmi, Sintong, Cowens, Festus, Dilla, Cece, Melly, Ica, Suci, Eka dan lainnya yang tidak dapat saya sebutkan satu persatu.
12. Abang/kakak/adik seperjuangan teknik sipil angkatan 2007, 2008, 2009, 2011, 2012, 2013, sedikit banyak telah membantu saya dalam menyelesaikan pendidikan di Departemen Teknik Sipil FT USU.
Saya menyadari sepenuhnya bahwa tugas akhir ini masih banyak terdapat kekurangan dan jauh dari sempurna, karena keterbatasan pengetahuan dan pengalaman, serta referensi yang dimiliki. Oleh karena itu sangat diharapkan saran-saran serta kritikan yang membangun dari pembaca untuk kesempurnaan tugas akhir ini.
Akhir kata, diharapkan tugas akhir ini bermanfaat bagi rekan mahasiswa lainnya dan pihak-pihak lain yang membutuhkan.
Medan, Januari 2015 Jernih Putri N Gulo 10 0404 090 ii
ABSTRAK
Proyek pembangunan villa 38 unit type 10 m x 19 m Blok Legian dipilih sebagai objek penelitian karena mengalami keterlambatan pada pelaksanaannya sebesar 12,71 % dari kondisi yang direncanakan. Keterlambatan durasi proyek dapat diatasi dengan mengadakan percepatan durasi proyek. Salah satu metode percepatan durasi yang dapat digunakan adalah metode pertukaran waktu dan biaya atau time cost trade off.
Alternatif percepatan yang digunakan adalah penambahan jam kerja (lembur) dengan 4 (empat) jam kerja dan penambahan jumlah tenaga kerja sebanyak 25% dari jumlah pekerja. Percepatan durasi proyek dilakukan dengan 2 (dua) langkah, yaitu : crashing program yang hanya diadakan pada kegiatan-kegiatan yang berada pada lintasan kritis dan analisa time cost
trade off yaitu dengan mengadakan kompresi (penekanan) durasi proyek yang dilakukan pada
kegiatan-kegiatan yang berada pada lintasan kritis.proyek pembangunan villa 38 unit type 10 m x 19 m Blok Legian, untuk alternatif penambahan jam kerja (lembur) diperoleh waktu optimum 260 HK dan total biaya optimum Rp 24.338.574.520,42. Sedangkan untuk alternatif penambahan jumlah tenaga kerja diperoleh waktu optimum 261 HK dan total biaya optimum Rp 24.206.637.473,90.
Kata kunci : keterlambatan, percepatan, time cost trade off, crashing program. iii
iv
BAB III. METODOLOGI PENELITIAN ........................................................................... 23
4.5.Pembiayaan Proyek ................................................................................................. 31 4.5.1.
4.4.Uraian Pekerjaan dan Penjadwalan Proyek ............................................................ 30
4.3.Gambar Proyek ....................................................................................................... 26
4.2.Struktur Organisasi .................................................................................................. 25
4.1.Data Umum Proyek ................................................................................................. 25
BAB IV. ANALISA DAN PEMBAHASAN ....................................................................... 25
3.2.Bagan Alir Penelitian .............................................................................................. 24
3.1.Metode Penelitian ................................................................................................... 23
2.2.Penelitian Tardahulu ............................................................................................... 20
DAFTAR ISI
Proyek ............................................................................................................ 4 2.1.2. Manajemen Proyek ........................................................................................ 6 2.1.3. Penjadwalan Proyek ...................................................................................... 7 2.1.4. Kurva S .......................................................................................................... 14 2.1.5. Rancangan Anggaran Biaya .......................................................................... 14 2.1.6. Mempercepat Waktu Penyelesaian Proyek (Crashing) ................................. 16 2.1.7. Metode Time Cost Trade Off ......................................................................... 17 2.1.8. Hubungan Antara Waktu dan Biaya .............................................................. 18
2.1.Landasan Teori ........................................................................................................ 4 2.1.1.
1.4.Batasan Masalah ...................................................................................................... 3
1.3.Tujuan ..................................................................................................................... 3
1.2.Perumusan Masalah ................................................................................................. 3
1.1.Latar Belakang ........................................................................................................ 1
BAB I. PENDAHULUAN .................................................................................................... 1
KATA PENGANTAR ............................................................................................................ i ABSTRAK ............................................................................................................................... iii DAFTAR ISI .......................................................................................................................... iv DAFTAR GAMBAR ............................................................................................................ vi DAFTAR TABEL .................................................................................................................. vii
DAFTAR LAMPIRAN ......................................................................................................... viii
Biaya Langsung ............................................................................................. 31 4.5.2. Biaya Tidak Langsung ................................................................................... 34
v
4.5.3.
Biaya Total Proyek ........................................................................................ 35 4.6. Identifikasi Kondisi Proyek dan Hubungan Antar Aktivitas .................................. 36 4.7. Perhitungan Crashing Program .............................................................................. 41 4.7.1.
Penambahan Jam Kerja (Lembur) ................................................................. 41 4.7.2. Penambahan Jumlah Tenaga Kerja ............................................................... 50 4.8. Analisa Pertukaran Biaya dan Waktu (Time Cost Trade Off) ................................. 59 4.8.1.
Penambahan Jam Kerja (Lembur) ................................................................. 59 4.8.2. Penambahan Jumlah Tenaga Kerja ............................................................... 69
BAB V. KESIMPULAN DAN SARAN .............................................................................. 79 5.1. Kesimpulan .......................................................................................................... 79 5.2. Saran .................................................................................................................. 80 DAFTAR PUSTAKA ........................................................................................................... 81
DAFTAR GAMBAR
Gambar 2.1 Sasaran proyek yang juga merupakan tiga kendala (triple constraint) ............. 5Gambar 2.2 Kegiatan Seri ..................................................................................................... 10Gambar 2.3 Kegiatan Paralel ............................................................................................... 10Gambar 2.4 Kegiatan Seri ..................................................................................................... 11Gambar 2.5 Kegiatan Overlap ............................................................................................. 11Gambar 2.6 Grafik indikasi menurunnya produktivitas karena kerja lembur....................... 12Gambar 2.7 Hubungan Waktu – Biaya Total, Biaya Tidak Langsung, BiayaLangsung dan Biaya Optimal .......................................................................... 18
Gambar 2.8 Hubungan Waktu – Biaya Normal dan Dipersingkat untuk suatuKegiatan .......................................................................................................... 19
Gambar 3.1 Bagan Alir Penelitian ....................................................................................... 24Gambar 4.2 Denah Lantai Dasar dan Lantai 2 ..................................................................... 26Gambar 4.3 Denah Lantai 3 dan Rencana Atap ................................................................... 27Gambar 4.4 Tampak Depan dan Tampak Belakang ............................................................ 28Gambar 4.5 Foto Dokumentasi Proyek ................................................................................ 29Gambar 4.6 Grafik Perubahan Biaya Langsung terhadap Waktuuntuk altenatif penambahan jam kerja (lembur) ............................................ 66
Gambar 4.7 Grafik Perubahan Biaya Total terhadap Waktuuntuk altenatif penambahan jam kerja (lembur) .............................................. 67
Gambar 4.8 Grafik Hubungan Waktu-Biaya Normal dan Dipercepatuntuk altenatif penambahan jam kerja (lembur) ............................................. 68
Gambar 4.9 Grafik Perubahan Biaya Langsung terhadap Waktuuntuk altenatif penambahan tenaga kerja ........................................................ 76
Gambar 4.10 Grafik Perubahan Biaya Total terhadap Waktuuntuk altenatif penambahan tenaga kerja ....................................................... 77
Gambar 4.11 Grafik Hubungan Waktu-Biaya Normal dan Dipercepatuntuk altenatif penambahan tenaga kerja ....................................................... 78 vi
DAFTAR TABEL
Tabel 1.1 Proyek Pembangunan Perumahan Cemara Kuta – Medan .................................. 2Tabel 2.1 Perbedaan Manajemen Proyek dengan Manajemen Klasik ................................. 6Tabel 4.1 Time Schedule normal dengan menggunakan kurvs S ........................................ 30Tabel 4.2 Rincian Biaya Langsung (untuk 1 unit) ............................................................... 31Tabel 4.3 Rincian Biaya Tidak Langsung ............................................................................ 35Tabel 4.4 Rincian Biaya Total ............................................................................................. 35Tabel 4.5 Hubungan Keterkaitan Antar Aktivitas ................................................................ 36Tabel 4.6 Produktifitas harian, Produktifitas per jam, Produktifitas harian setelah di-crash dan Crash Duration tiap kegiatan kritis ..................................43 Tabel 4.7 Upah kerja harian normal, Upah kerja per jam normal, Upah lembur
per hari (4 jam kerja), Crash cost per hari dan Crash total tiap kegiatan
Tabel 4.8 Cost slope tiap kegiatan kritis ............................................................................. 48Tabel 4.9 Penambahan jumlah tenaga kerja ....................................................................... 50Tabel 4.10 Produktifitas harian, Produktifitas penambahan jumlah tenaga kerja dan Crash duration tiap kegiatan kritis .....................................................................52 Tabel 4.11 Upah kerja harian normal, Upah kerja setelah crashing (penambahan jumlah tenaga kerja) dan Crash cost untuk tiap kegiatan kritis .........................
55 Tabel 4.12 Cost slope tiap kegiatan kritis ............................................................................. 57
Tabel 4.13 Urutan Kegiatan dengan Cost Slope Terendah ................................................... 59Tabel 4.14 Total durasi proyek setelah crashing .................................................................. 61Tabel 4.15 Hasil Perhitungan Direct Cost (Biaya Langsung) .............................................. 64Tabel 4.16 Hasil Perhitungan Direct Cost (Biaya Langsung) .............................................. 65Tabel 4.17 Urutan Kegiatan dengan Cost Slope Terendah ................................................... 69Tabel 4.18 Total durasi proyek setelah crashing .................................................................. 71Tabel 4.19 Hasil Perhitungan Direct Cost (Biaya Langsung) .............................................. 74Tabel 4.20 Hasil Perhitungan Direct Cost (Biaya Langsung) .............................................. 75vii