Modal Kerja Working Capital Investment,WCI Biaya Pengeluaran Umum General Expenses, GE

Pra Rencana Pabrik Cement Retarder 2 XI.2. Penentuan Total Capital Investment TCI XI.2.1. Modal Tetap Fixed Capital Investment,FCI A. Biaya langsung Direct Cost, DC 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. Harga Peralatan E Ongkos Angkutan Freight 10 E Cost Freight Asuransi 1 E Cost Insurance Freight CIF Instalasi dan pemasangan 30 E Instrumentasi dan Kontrol 15 E Perpipaan terpasang 36 E Listrik terpasang 25 E Fasilitas Pelayanan 55 E Yard Improvement 10 E Tanah Bangunan Total Direct Cost TDC = = = = = = = = = = = = = = Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp 40,164,479,764.02 4,016,447,976.40 44,180,927,740.42 401,644,797.64 44,582,572,538.06 12,049,343,929.21 6,024,671,964.60 14,459,212,715.05 10,041,119,941.01 22,090,463,870.21 4,016,447,976.40 9,345,875,000.00 9,555,000,000.00 132,164,707,934.54 + + + B. Biaya tidak langsung Indirect Cost ,IC 12. 13. 14. 15. Teknik dan supervisi 25 E Biaya Konstruksi 20 E Ongkos Kontraktor 20 TDCTIC Biaya tak terduga 10 TDCTIC Total Indirect Cost TIC Fixed Capital Investment FCI= TDC + TIC = = = = = = Rp Rp Rp Rp Rp Rp 10,041,119,941.01 8,032,895,952.80 30,047,744,765.67 15,023,872,382.84 63,145,633,042.31 195,310,340,976.86

XI.2.2. Modal Kerja Working Capital Investment,WCI

1. 2. 3. Modal Penyimpanan Bahan Baku 1bln Modal Penyimpanan Produk 1 bln Modal Cadangan 1 bln = = = Rp Rp Rp 3,969,907,035.17 750,000,000.00 471,990,703.52 + Working Capital Investment WCI = Rp 5,191,897,738.69 + Hak Cipta © milik UPN Veteran Jatim : Dilarang mengutip sebagian atau seluruh karya tulis ini tanpa mencantumkan dan menyebutkan sumber. Pra Rencana Pabrik Cement Retarder 3 Total Capital Investment TCI = FCI + WCI Total Capital Investment TCI = Rp 200,502,238,715.54 Modal investasi dibagi : 1. Modal sendiri, 60 TCI = Rp120,301,343,229.33 2. Modal pinjaman bank, 40 TCI = Rp 80,200,895,486.22 XI.3. Penentuan Biaya produksi langsung Total Production Cost, TPC XI.3.1. Biaya Pembuatan Manufacturing Cost, MC A. Biaya Produksi Langsung Direct Production Cost ,DPC 1. 2. 3. 4. 5. 6. 7. 8. Bahan baku 1 tahun Gaji Karyawan 1 tahun Biaya Laboratorium 15 gaji karyawan Biaya Pemeliharaan Perbaikan 2FCI Operating Supplies 9 4 Biaya Utilitas 1 tahun Biaya Packaging Biaya supervisi 16 gaji karyawan = = = = = = = = Rp Rp Rp Rp Rp Rp Rp Rp 47,638,884,422.05 7,590,600,000.00 1,138,590,000.00 3,906,206,819.54 351,558,613.76 89,440,609,078.19 9,000,000,000.00 1,214,496,000.00 + Direct Production Cost DPC = Rp 160,280,944,933.54 B. Biaya Tetap Fixed Charge,FC 1. 2. 3. 4. Depresiasi alat 10 FCI – H.tanah - H.bangunan Depresiasi Bangunan10 H.bangunan Asuransi 1 FCI Bunga Bank 14 Pinjaman Bank Fixed Charge FC = = = = = Rp Rp Rp Rp Rp 17,640,946,597.69 955,500,000.00 1,953,103,409.77 11,228,125,368.07 31,777,675,375.52 + Hak Cipta © milik UPN Veteran Jatim : Dilarang mengutip sebagian atau seluruh karya tulis ini tanpa mencantumkan dan menyebutkan sumber. Pra Rencana Pabrik Cement Retarder 4 C. Biaya Plant Overhead 50 Gaji + supervise + pemeliharaan = Rp 6,355,651,409.77 Total Manufacturing Cost TMC = Direct production cost + Fixed Charge + Biaya Plant Overhead = Rp 198,414,271,718.83

XI.3.2. Biaya Pengeluaran Umum General Expenses, GE

1. Biaya admnistrasi = Rp 1,906,695,422.93 15 Gaji + supervise + Pemeliharaan 2. Biaya Distribusi dan Pemasaran 2 TPC = 0,02 TPC 3. Biaya R D 3 TPC = 0,03 TPC + = Rp. 1,906,695,422.93 + 0,05 TPC Total production cost TPC = Total Manufacturing Cost TMC + General expenses GE TPC = TMC + GE = Rp. 198,414,271,718.83 + Rp. 1,906,695,422.93+ 0,05 TPC 0,95 TPC = Rp.200,320,967,141.76 TPC = Rp. 200,320,967,141.76 0,95 = Rp. 210,864,175,938.69 Maka : 4. Biaya Distribusi dan Pemasaran 2 TPC = Rp 4,217,283,518.77 5. Biaya R D 3 TPC = Rp 6,325,925,278.16 + = Rp 12,449,904,219.87

XI.4. Analisa Ekonomi