In the Summary of Servers screen, select the Control tab. Select bi_server2 in the table and then click Shutdown.

Configuring High Availability for Oracle Business Intelligence and EPM 15-55 1. Log into the Oracle WebLogic Server Administration Console.

2. In the Change Center, click Lock Edit.

3. Expand the Environment node in the Domain Structure window.

4. Click Servers.

5. Select bi_server2 in the Names column of the table.

The Setting page for bi_server2 opens. 6. Set the Listen Address to APPHOST2VHN1.

7. Click Save.

8. Click Activate Changes.

9. The changes do not take effect until the BI_SERVER2 managed server restarts.

a. In the Summary of Servers screen, select the Control tab.

b. Select bi_server2 in the table and then click Shutdown.

10. Restart the BI System components, for example: cd ORACLE_BASEadmininstance2bin .opmnctl restartproc

15.1.12.14.1 Updating the Oracle BI Publisher Scheduler Configuration on APPHOST1 and

APPHOST2 Follow the steps in this section to update the WebLogic JNDI URL for the Oracle BI Publisher Scheduler. To update the Oracle BI Publisher Scheduler configuration: 1. Log in to Oracle BI Publisher at the following URLs: http:APPHOST1VHN1:9704xmlpserver http:APPHOST2VHN1:9704xmlpserver

2. Click the Administration link.

3. Click Scheduler Configuration under System Maintenance.

4. Update the WebLogic JNDI URL under JMS Configuration, as follows:

t3:APPHOST1VHN1:9704,APPHOST2VHN1:9704

5. Click Apply.

6. Check the Scheduler status from the Scheduler Diagnostics tab.

15.1.12.15 Disabling Host Name Verification for the BI_SERVER2 Managed Server

This step is required if you have not set up the appropriate certificates to authenticate the different nodes with the Administration Server. If you have not configured the server certificates, you receive errors when managing the different WebLogic Servers. To avoid these errors, disable host name verification while setting up and validating the topology, and enable it again once the high availability topology configuration is complete. To disable host name verification: 1. Log into Oracle WebLogic Server Administration Console.

2. In the Change Center, click Lock Edit.

15-56 Oracle Fusion Middleware High Availability Guide

3. Expand the Environment node in the Domain Structure window.

4. Click Servers.

5. Select bi_server2 in the Names column of the table.

6. Open the SSL tab.

7. Expand the Advanced section of the page.

8. Set Hostname Verification to None.

9. Click Save.

10. Click Activate Changes.

The changes don’t take effect until the BI_SERVER2 managed server restarts.

15.1.12.16 Configuring Oracle BI for Microsoft Office SSO Properties

To configure Oracle BI for Microsoft Office Single Sign-On SSO properties:

1. Validate the Oracle BI EE Office Server setup by accessing the following URLs:

■ http:APPHOST1VHN1:9704biofficeabout.jsp ■ http:APPHOST2VHN1:9704biofficeabout.jsp The About Oracle BI EE Office Server page appears, as shown in Figure 15–7 . Figure 15–7 About Oracle BI EE Office Server Page 2. Go to the Oracle BI EE Office Server directory. For example: Configuring High Availability for Oracle Business Intelligence and EPM 15-57 DOMAIN_HOMEserversmanaged_servertmp_WL_userbioffice_ 11.1.1cvsibbwarWEB-INF If you are not sure how to locate the Oracle BI EE Office Server directory, check the LogDir parameter on the About Oracle BI EE Office Server page. The Oracle BI Enterprise Edition Office Server directory is the parent directory of the log directory. 3. On both APPHOST1 and APPHOST2, open bioffice.xml for editing and modify the BI Office properties shown in Table 15–5 . 4. Restart the Oracle BI for Microsoft Office application, as follows: a. Log in to the Administration Console.

b. Click Deployments in the Domain Structure window.