Model Simulation LITERATURE REVIEW
173
Moreover, Ibrahim and Nissen 2007 extended the organization theory by integrating it with knowledge-flow theory. Their research used computational methods and tools
to understand how discontinuous membership affects organizational performance. Similarly, since this study is concerned with knowledge flow during the conceptual
design process, we followed Ibrahim and Nissen 2007 to inspect effectiveness of the proposed knowledge-based framework for conceptual design phase.
The base case for this study is Macmillan 2001 framework for the conceptual design phase. The process of choosing this framework was based on the comparison
made among the existing models for this stage See 2.4.4. Using this software we attempted to create the conceptual design process adopting Macmillan 2001
framework for this stage. Although Macmillan 2001 conceptual design framework has 12 main activities, there are some implicit activities which work to specify the
required knowledge and also to exchange of the required knowledge. Therefore, we have added two activities following each activity from Macmillan framework. In
conclusion, the process of the concept design has 36 activities which stem from Macmillan model and 24 more additional activities for identifying and exchanging
the required knowledge for each activity. To simulate the base Macmillan framework through SimVision, the following steps must be considered. After launching
SimVision, a default program opens that contains a default project1 and two milestones namely Start and Finish Figure 5.1.
174
Figure 5.1. Default Workspace for Opened Program in SimVision
A program is a set of related projects that together meet the business needs of a client. The default project and milestones are displayed in the Model pane. Then, by clicking
on the Project1tab at the bottom of the default workspace, the default project elements are viewed in the model pane Figure 5.2.
Tree Pane Properties
Pane Default
Logo Model
Pane Default
Model Title
175
Figure 5.2. Default Project elements
Like the program, the project also has two default milestones: Start and Finish. The project’s start and planned end dates can be set by setting dates for the Start and
Finish milestones. It also has a default task, position, and meeting. The next step is adding Macmillan activities as tasks between the first and second Milestones. Then
the task precedence has to be defined by linking the tasks to each other and to milestones by means of successor links. As a result of which every task and milestone
must have both a predecessor and a successor. The Start milestone only has a
Default Position
Default M eeting
Default M ilestone
Default Task
176
successor; the Finish milestone only has a predecessor. Successor links can be one of the three types: 1 finish-start, 2 start-start, 3 finish-finish.
Once the project tasks are in place, the positions are required to be added. A position is an individual or a group of individuals with a responsibility for one or more tasks.
Like all other objects, positions have a set of properties. These properties which are called micro-behaviors are composed of: 1 Name, 2 role, 3 application
experience, 4 FTE, 5 salary A name is a short label for the position. A Role is the position’s function in the organizational hierarchy. Each position fulfils one of the
three functions: Sub-team ST, Sub-team Leader SL, or Project Manager PM. Project Manager is the position that tends to make many of the decisions, and to
whom others usually go with questions. Typically only one person per project has this role. Sub-teams generally do most of the work. Usually sub-team leaders’ position is
between PM and ST. In this tutorial, we use only PM and ST roles. Application Experience concerns the degree of the experience the position with respect to this
type of project. FTE is the number of full-time equivalent persons represented by the position. Salary is the position’s hourly wage, measured in currency units. After
creating a hierarchy of positions, the tasks can be assigned to these positions. Each task must have a single primary responsible position. More than one position can
work on a task, but only one position is primarily responsible for it. Tasks can only have a single primary responsible position, but positions can have multiple primary
tasks. Tasks can have any number of secondary responsible positions. Positions are available to work on secondary tasks only when they are not working on primary
177
tasks. There are two kinds of assignment links with which you can assign tasks to positions: 1 primary assignment link which links a position to a primary task, 2
secondary assignment link which links a position to a secondary task.
Using the said steps, the researcher attempted to implement Macmillan framework as the base case for this study. As it is shown in Figure 5.3, Macmillan main activities
are in white color. Activities have been ordered in columns. For instance, the first activity is “specifying the business needs”. The next activity in the first column is for
identifying the required knowledge. The following activity is for “exchanging the required knowledge”. Other activities have been ordered consequently. In SimVision
we have to assign activities to project team members. Many experts such as the project manager, architect and mechanicalelectrical engineers are involved in the
concept design phase; therefore each activity is assigned to all these experts. In this way, we can examine the effects of these experts’ skills on the project performance.
178
Figure 5.3 Base Framework for Conceptual Design Phase
Source: adopted from Macmillan, 2001
According to Nissen’s 2006 multidimensional model, the knowledge move from the individual to the group through the shared experience. Now, if experts’ skill matches
the required experience for the related task, the person in charge will know the accurate and complete knowledge which has to be transferred. As a result, the
completeness and the accuracy of the knowledge obtained by the receiver depend on the skill of the sender. In a tacit dominant area such as the conceptual design phase,
the performance of successor’s task relies on the received knowledge which has been sent by a provider. Therefore, the skill of all the team members involved can affect
179
the knowledge exchanging process between experts and by extension the project performance. Considering these experts’ skill experts’ tacit knowledge has an
undeniable effect on the performance of the project See Table 5.1. According to this table the required skills for team member consist of Medium level for Project
Manager PM, High level for Architect AR and High level for MechanicalElectrical engineer ME. These experts possess the required skill,
therefore they are able to provide the required knowledge at the right time. If an expert such as an architect does not possess the required level of skill, other team
member’s task through will suffer through hisher incomplete knowledge transfer. Therefore, this study hypothesizes that:
H1: A building project team member who has sufficient knowledge which is
required for other team members’ tasks can improve performance of the receiver’s task. The study expects the FRI and PRI to be less than 0.5.
H2: A building project team member who does not have sufficient knowledge
which has to be considered by other team members to do their task, by transferring incomplete knowledge can increase the risk involved in the
receiver’s task. The study expects the FRI and PRI to be less than 0.5.
To prove the abovementioned hypothesis, what the researcher does is compare and contrast the results when a team member -- such as architect -- possesses the required
skill which matches the required experience to participate in a project with the situation in which the same person does not.
180
Table 5.1. The awareness of team members about the required knowledge Awareness
PM AR
ME Sufficient
Medium High
High
Insufficient
Medium Medium High
For example when mechanicalelectrical engineers ME do not possess the sufficient knowledge for using the solar bowl to generate electricity, they may let the architects
AR design many blocks for the building. The researcher experienced a similar problem with Group 3 concept design. In the middle of the day set for doing the
concept design, mechanicalelectrical experts stated that due to the high cost of generating electricity by means of solar bowl, they would not approve of the
presented concept design. Thus, they lost their time through redesigning their concept. Similarly, if architects had sufficient experience about the solar bowl
requirements they could have prevented the loss of time. If they knew that they had to allow for specific requirements for various kinds of technologies, they would have
demanded these requirements from mechanicalelectrical experts.
In such a situation, of the project manager’s skill PM as the leader of the design team has a great impact on knowledge exchange process. If the project manager
knows that some knowledge is required to be exchange at a given time, he will facilitate this process. Therefore, explication of the entity of the knowledge required
181
to be considered during the conceptual design phase can affect project performance. In other words, when the entity of the required knowledge has been specified, we can
avoid spending time on identifying it. In such a situation, team members deal with the explicit knowledge which does not depend on the skill of the experts involved.
Therefore, this study has one more hypothesis to offer as regards Nissen theory 2006:
H3: By specifying the entity of the required knowledge during conceptual
design phase, performance of building project improves due to explicitness of entity of knowledge. The study expects the FRI and PRI to be less than 0.5.
For instance, when an architect knows about the entity of the required mechanicalelectrical knowledge which has to be considered through each step of the
conceptual design, the time needed to determine the knowledge required is reduced.
Test case 1: Base Case Sufficient Awareness
Following Ibrahim and Nissen 2005 example for the situation in which there is a small number of task volumes in the base case, the behavior parameters are set higher
than the normal in construction industry to amplify the effects of knowledge flow on the outcome. According to SimVision a project represents a work process when it
must be performed by the project team members to achieve an outcome. Each project is composed of tasks, positions, milestones, meeting and also links among
182
components. We set the parameters for project, positions and tasks as stated here: Medium level for team experience, Low for centralization, Medium for formalization,
Medium for matrix strength, 0.7 for communication probability, and finally 0.15 for noise problem, project error probabilities and also for functional error probability. As
mentioned before, the values of the above parameters have been set in accordance with the normal construction industry values.
Position parameters for experts including of the project manager, architect and mechanicalelectrical engineers are shown in Table 5.2. The micro-behaviors include
fulltime-equivalent FTE, role, application experience App. Exp. and salary.
Table 5.2. Baseline parameters for team members Position
FTE Role
Application Experience
salary Knowledge
Skill
1 Project Manager
0.3 PM
Medium 100
Medium 2
Architect 1
SL High
80 High
3 MechanicalElectrical
Engineer 2
ST High
70 High
In the base case, all team members’ skill satisfies the required skill for carrying out the job. For instance, the required skill for architect and mechanicalelectrical
engineers is high. In case base these experts’ skill satisfies the required skill. In other
183
words, architects and mechanicalelectrical experts are fully aware of the knowledge which has to be exchanged between the experts.
Test case 2: Proposed Case Insufficient Awareness
The second case test is about insufficient awareness for experts. All the project, position and tasks parameters are similar to the case test. To represent the effect of
insufficient awareness of the experts on performance we changed their skill. Accordingly, the skill of architect changed from High to Medium so as to gauge the
effect of the experts’ skill on project performance Table 5.3. As it is shown, the skill of the architect has not fulfilled application experience requirements. It means that
the architect does not have the sufficient knowledge to accomplish hisher own task.
Table 5.3. Changed parameter for architect skill
Position FTE
Role Application
Experience Salary
Knowledge Skill
1 Project Manager
0.3 PM
Medium 100
Medium 2
Architect 1
SL High
80
Medium
3 MechanicalElectrical
Engineer 2
ST High
70 High
184