The failure of permit holders to submit required documentation to

ANAO Report No.3 2015–16 Regulation of Great Barrier Reef Marine Park Permits and Approvals 116

7.21 While the hard-copy or electronic templates were not used in all cases to

report permit-related non-compliances, sufficient information was obtained in all instances to allow the FMCU to undertake an initial assessment and decide whether the incident warranted investigation. However, evidence has not been retained by GBRMPA to demonstrate that its Complexity and Priority Model for prioritising incidents for investigation had been applied as required by the Compliance Management and Investigations Procedures . 132 The only evidence retained by GBRMPA relating to the prioritisation of incidents for investigation was a notation attached to 15 incidents 19.7 per cent indicating that the incident was ranked a ‘High’, ‘Medium’ or ‘Low’ priority without any rationale documented for the priority allocated.

7.22 In general, the decision to investigate or not, the relevant

decision-maker and the date of the decision were appropriately documented for all incidents. However, the reasons underpinning the decisions were not documented in most cases. Of the 76 permit-related non-compliance incidents examined by the ANAO, the reasons for the decisions were documented in only eight cases 10.5 per cent—with the decision in seven of these cases being to not investigate the incident. The limited documentation prepared by GBRMPA outlining the reasons for its decisions to investigate incidents inhibits its ability to demonstrate that resources have been prioritised appropriately to those instances of non-compliance posing the greatest risks. The preparation and retention of appropriate documentation outlining the reasons for prioritising incidents to investigate would improve GBRMPA’s ability to demonstrate the effectiveness and consistency of its investigatory activities.

7.23 While the FMCU has not established target timeframes for determining

whether to investigate a reported incident, its decisions on whether to investigate permit-related incidents generally occurred in a timely manner, with most decisions being made within eight days and 80 per cent of decisions made within 44 days. Decisions relating to eight incidents, however, took in excess of 132 Application of the GBRMPA Complexity and Priority Model requires the consideration of the possible impact from any incident examples of which are provided for each permit type—categorised on a five-point scale insignificant, minor, moderate, major and extreme. The investigation priority is based on the impact rating and other factors such as politicalmedia subject interest, relationship to corporate priorities and potential damage in financial terms—to arrive at an investigation priority rating of high, medium or low. The complexity of an investigation is based on factors such as the clarity of jurisdiction and offences committed, ease of access to relevant information and number of inspectors required—to arrive at a complexity rating of high, medium or low. The combination of the priority and complexity ratings determines the type and timeliness of GBRMPA’s intended response.