43
Key Milestones and Staff Responsibilities for Major Activity Areas
Program Areas Lead Partner
Date for completion
ICFG Supervisor
CRC Backstopping
Tech Support
3.1 Baseline
3.1.1 Training SM
Feb MF
BC, SO 3.1.2 Document analyze response
SM May
MF SO 3.1.3 Governance Response
SM May
KA SO
3.1.4 Biodiversity Threats UG
May KA
BC 3.1.5 Coastal Communities
FON May
KA BC
3.1.6 Fisheries Sector WF
Aug MF
KC 3.1.7 Coastal Habitats
UG July
MF BC
3.1.8 State of Coast Report SM
Sept MF
SO
3.2 Early Actions
3.2.1.1 Fisheries regulations ICFG
Mar HB
BC 3.2.1.2 Network meetings
ICFG ongoing
HB BC 3.1.3 Fish sector meetings
ICFG ongoing
HB BC
3.2.2.1 WERENGO support FON
ongoing KA
MF 3.2.2.2 Small Grants
ICFG Sept
MF BC 3.2.2.3 Pilot wetlands
FON Sept
MF BC
3.3 Public-Private Partnerships
3.3.1 Tourism ICFG
July MF
DR 3.3.2 Oil and Gas
ICFG April
MF JT
3.4 Communications
Communications development FoN
August MF
BC
3.5 Capacity Building
3.5.1 Technical training URI
Sept MF
BC 3.5.2 Gender
WF July
MF BC
3.5.3 Diversified Livelihoods WF
Sept KA
KC 3.5.4 Fisheries Department
URI July
KA KC
3.6 Design Phase 2
Phase 2 Design ICFG
Sept MF BC,
SO SM-SustainaMatrix, FON-Friends of the Nation, WF –WorldFish Center, UG-University of Ghana,
URI – University of Rhode Island, MF-Mark Fenn, KA-Kofi Agbogah, HB-Harry Barnes-Dabben, BC-Brian Crawford CRC, SO-Stephen Olsen, DB-Donald Rubinof, KC-Kathy Castro, JT-Jim Tobey
44
4.5 International Travel
Schedule
The following table provides tentative dates and purposes for all international travel budgeted by the Program during the implementation plan period. This travel is shown for each of the main
international partners. Travel of any local partners or CRC international consultants is subsumed under the CRC-URI column.
MONTH CRC-URI WorldFish
Center SustainaMetrix
Jan. CRC 2 to Ghana for ICFG
training and research orientations Jan 25 – Feb
10 SM 1 to Ghana for ICFG
training and research orientations Jan 25 – Feb
10
Feb. CRC 1 to Ghana for
administrative support Feb 01-10
March -ICFG staff 1 to
Washington DC USAID SUCCESS Project Learning
workshop on Sustainable Livelihoods
-GoG and Traditional chiefs 3 to 4 to USA on oil and
gas study trip
April -CRC 2 to Ghana for mid-
term assessments and 2
nd
ICFG training April 15-30 -URI 1 to Ghana for
wetlands assessment -WF 1 to Ghana for mid-
term assessments and fisheries sector study April
15-May 30 WF 1 to Ghana for ICFG
for mid-term assessments and 2
nd
ICFG training April 15-30
May June
Ghana Participants in URI Coastal 3 and Fisheries
Institutes 2
July -URI 1 to Ghana for
capacity building assessment at Universities
in Ghana July 15-30 -URI 1 to Ghana for
trawler fleet study and Fisheries Department
capacity building action plan July 15-30
WF 2 or 3 for gender study, livelihoods
diversification assessment, and aquaculture feasibility
study July 1-30
August -CRC 3 to Ghana for
finalization of reports and Phase 2 development and
Year 2 workplan and budget Aug 15-30
-University of Ghana MS students 2 to URI for
Masters Program WF 1 to Ghana for
finalization of reports and Phase 2 development and
Year 2 workplan Aug 15- 30
SM 1 to Ghana for finalization of reports and
State of the Coast Report Aug 25-Sept 10
Sept.
45
4.6 Environmental Monitoring and Compliance