Biaya Total Jam Lembur dan Penambahan Tenaga Kerja

Tabel 5.46 Biaya Akibat Penambahan 2 Jam Lembur dan Penambahan Tenaga Kerja 2 Durasi Hari Penambahan Jam Lembur Penambahan Tenaga kerja 156 Rp2.640.551.389,00 Rp2.640.551.389,00 155,81 Rp2.638.477.630,82 Rp2.640.294.295,01 155,62 Rp2.637.971.598,96 Rp2.640.038.021,51 155,06 Rp2.637.174.992,12 Rp2.639.280.964,42 154,5 Rp2.636.462.863,86 Rp2.638.524.682,22 154,13 Rp2.636.038.092,91 Rp2.638.025.003,02 153,94 Rp2.635.929.924,21 Rp2.637.769.096,13 153,75 Rp2.635.836.666,03 Rp2.637.514.044,64 153,56 Rp2.635.758.318,38 Rp2.637.257.519,14 153 Rp2.635.474.040,11 Rp2.636.500.690,30 152,63 Rp2.635.453.163,77 Rp2.636.000.497,50 152,26 Rp2.635.565.244,17 Rp2.635.500.314,60 151,7 Rp2.635.421.990,91 Rp2.634.742.913,21 151,14 Rp2.635.816.280,50 Rp2.633.985.711,46 150,95 Rp2.636.861.485,48 Rp2.633.729.638,37 150,76 Rp2.637.922.143,09 Rp2.633.473.607,27 150,39 Rp2.639.324.182,96 Rp2.632.975.408,57 150,2 Rp2.641.391.287,94 Rp2.632.721.012,58 149,83 Rp2.643.353.341,32 Rp2.632.221.487,88 149,64 Rp2.645.870.246,30 Rp2.631.965.800,04 149,27 Rp2.648.305.261,84 Rp2.631.466.561,84 149,08 Rp2.651.085.619,45 Rp2.631.212.993,14 148,71 Rp2.654.497.943,11 Rp2.630.718.413,64 148,34 Rp2.658.889.018,11 Rp2.630.224.995,74 148,15 Rp2.664.686.059,93 Rp2.629.975.549,25 147,78 Rp2.670.438.599,80 Rp2.629.480.727,35 Tabel 5.47 Biaya Akibat Penambahan 3 Jam Lembur dan Penambahan Tenaga Kerja 3 Durasi Hari Penambahan Jam Lembur Penambahan Tenaga kerja 156 Rp2.640.551.389,00 Rp2.640.551.389,00 155,77 Rp2.639.132.200,22 Rp2.640.240.924,95 Tzbel 5.47 Lanjutan 155,08 Rp2.638.192.516,48 Rp2.639.306.997,50 154,39 Rp2.637.320.224,05 Rp2.638.374.120,54 153,93 Rp2.636.798.870,40 Rp2.637.752.021,24 153,7 Rp2.636.689.055,53 Rp2.637.442.190,79 153,47 Rp2.636.599.405,88 Rp2.637.132.379,14 153,24 Rp2.636.529.917,10 Rp2.636.821.895,84 152,55 Rp2.636.226.856,55 Rp2.635.888.559,43 152,09 Rp2.636.341.683,34 Rp2.635.268.739,03 151,63 Rp2.636.530.284,04 Rp2.634.646.893,93 150,94 Rp2.636.416.501,75 Rp2.633.714.834,08 150,25 Rp2.637.019.039,75 Rp2.632.782.928,12 150,02 Rp2.638.497.990,10 Rp2.632.475.906,47 149,79 Rp2.639.980.005,67 Rp2.632.167.531,22 149,33 Rp2.641.872.012,89 Rp2.631.547.724,92 149,1 Rp2.644.717.376,28 Rp2.631.241.146,07 148,64 Rp2.647.348.224,81 Rp2.630.621.936,77 148,41 Rp2.650.829.083,85 Rp2.630.314.241,42 147,95 Rp2.654.086.306,29 Rp2.629.693.358,71 147,72 Rp2.657.903.047,94 Rp2.629.383.995,06 147,26 Rp2.662.451.487,77 Rp2.628.763.390,36 146,8 Rp2.668.294.286,29 Rp2.628.147.539,86 146,57 Rp2.676.199.519,25 Rp2.627.838.593,41 146,11 Rp2.683.841.082,99 Rp2.627.218.317,91 145,88 Rp2.701.561.181,17 Rp2.626.918.655,26 Dari table diatas dapat dilihat bahwa terdapat perbedaan antara biaya akibat penambahan jam kerja lembur dengan penambahan tenaga kerja, biaya diatas adalah biaya yang langsung dibebankan kepada proyek. Pada penambahan lembur 1 jam dan penambahan tenaga kerja 1 pada durasi ke 153,51 dapat diketahui bahwa biaya yang efisien terdapat pada penambahan tenaga kerja 1 yaitu sebesar Rp2.637.198.442,50. Pada penambahan lembur 2 jam dan penambahan tenaga kerja 2 pada durasi ke 152,63 dapat diketahui bahwa biaya yang efisien terdapat pada penambahan tenaga kerja 2 yaitu sebesar Rp2.636.000.497,50. Sedangkan pada penambahan lembur 3 jam dan penambahan tenaga kerja 3 pada durasi ke 152,55 dapat diketahui bahwa biaya yang efisien terdapat pada penambahan tenaga kerja 3 yaitu sebesar Rp2.635.888.559.43. Dan dari ke tiga perbandingan diatas didapat durasi tercepat dan biaya termurah yaitu pada penambahan tenaga kerja 3 dengan durasi sebesar 152,55 hari dan dengan penggunaan biaya sebesar Rp2.635.888.559,43. Selanjutnya untuk mengetahui penambahan biaya akibat lembur, tenaga kerja, dan biaya denda dapat dilihat di Tabel 5.48, Tabel 5.49, dan Tabel 5.50 berikut ini : Tabel 5.48 Perbandingan Penambahan Biaya Akibat 1 Jam Lembur, Tenaga Kerja 1 dan Biaya Denda Durasi Hari Penambahan Lembur Penambahan Tenaga Kerja Denda 156 155,89 Rp443.184,00 Rp385,50 Rp290.460,65 155,55 Rp482.797,00 Rp 1.468,50 Rp1.188.248,13 155,21 Rp473.641,00 Rp 2.658,90 Rp2.086.035,60 154,98 Rp463.653,00 Rp 3.294,15 Rp2.693.362,42 154,87 Rp452.926,00 Rp 5.222,15 Rp2.983.823,07 154,76 Rp441.126,00 Rp 7.185,65 Rp3.274.283,72 154,65 Rp426.968,00 Rp 9.306,45 Rp3.564.744,38 154,31 Rp328.090,00 Rp10.345,65 Rp4.462.531,85 154,08 Rp251.560,00 Rp13.871,15 Rp5.069.858,67 153,85 Rp167.377,00 Rp15.057,50 Rp5.677.185,49 153,51 Rp39.407,00 Rp18.834,50 Rp6.574.972,96 153,17 Rp200.798,00 Rp21.394,75 Rp7.472.760,43 152,95 Rp364.878,00 Rp24.013,75 Rp8.053.681,74 152,84 Rp456.714,00 Rp25.284,25 Rp8.344.142,39 152,73 Rp549.890,00 Rp29.438,95 Rp8.634.603,04 152,5 Rp811.931,00 Rp30.824,95 Rp9.241.929,86 152,27 Rp1.151.953,00 Rp34.575,95 Rp9.849.256,68 152,04 Rp1.556.621,00 Rp36.501,45 Rp10.456.583,50 151,93 Rp1.754.438,00 Rp40.608,30 Rp10.747.044,15 151,82 Rp1.968.199,00 Rp42.602,30 Rp11.037.504,81 151,59 Rp2.507.747,00 Rp44.717,30 Rp11.644.831,63 Tabel 5.48 Lanjutan 151,36 Rp3.181.697,00 Rp46.910,70 Rp12.252.158,44 151,13 Rp4.043.514,00 Rp49.303,50 Rp12.859.485,26 151,02 Rp4.472.210,00 Rp59.047,30 Rp13.149.945,92 150,91 Rp5.412.374,00 Rp69.350,30 Rp13.440.406,57 Tabel 5.49 Perbandingan Penambahan Biaya Akibat 2 Jam Lembur, Tenaga Kerja 2 dan Biaya Denda Durasi Hari Penambahan Lembur Penambahan Tenaga Kerja Denda 156 155,81 Rp345.130,00 Rp190,50 Rp977.004,01 155,62 Rp392.392,00 Rp1.201,50 Rp1.954.008,03 155,06 Rp413.837,00 Rp2.456,60 Rp3.432.716,81 154,5 Rp387.974,00 Rp4.486,60 Rp3.934.421,57 154,13 Rp359.759,00 Rp5.835,10 Rp4.911.425,58 153,94 Rp331.427,00 Rp7.212,70 Rp5.413.130,35 153,75 Rp300.262,00 Rp9.445,70 Rp6.891.839,13 153,56 Rp266.264,00 Rp10.204,70 Rp7.868.843,14 153 Rp805,00 Rp11.688,05 Rp8.370.547,90 152,63 Rp176.851,00 Rp12.522,95 Rp8.872.252,67 152,26 Rp403.701,00 Rp13.367,75 Rp9.849.256,68 151,7 Rp748.134,00 Rp14.278,55 Rp11.327.965,46 151,14 Rp1.393.591,00 Rp15.389,00 Rp11.829.670,22 150,95 Rp1.641.064,00 Rp16.600,40 Rp13.308.379,00 150,76 Rp1.891.473,00 Rp17.853,80 Rp14.285.383,01 150,39 Rp2.595.608,00 Rp20.682,80 Rp14.787.087,78 150,2 Rp3.037.242,00 Rp23.571,30 Rp16.265.796,56 149,83 Rp3.948.582,00 Rp25.074,30 Rp17.242.800,57 149,64 Rp4.475.678,00 Rp26.670,95 Rp17.744.505,33 149,27 Rp5.562.014,00 Rp28.460,45 Rp18.721.509,35 149,08 Rp6.139.166,00 Rp32.176,25 Rp19.223.214,11 148,71 Rp7.587.106,00 Rp38.624,45 Rp19.724.918,88 148,34 Rp9.397.184,00 Rp46.234,25 Rp20.701.922,89 148,15 Rp10.547.506,00 Rp54.072,25 Rp21.203.627,65 147,78 Rp12.861.326,00 Rp60.278,05 Rp21.705.332,42 Tabel 5.50 Perbandingan Penambahan Biaya Akibat 3 Jam Lembur, Tenaga Kerja 3 dan Biaya Denda Durasi Hari Penambahan Lembur Penambahan Tenaga Kerja Denda 156 155,77 Rp254.780,00 Rp985,60 Rp 607.326,82 155,08 Rp258.461,00 Rp1.407,10 Rp 2.429.307,28 154,39 Rp215.642,00 Rp2.879,10 Rp 4.251.287,74 153,93 Rp168.931,00 Rp3.679,10 Rp 5.465.941,38 153,7 Rp122.555,00 Rp5.298,30 Rp 6.073.268,19 153,47 Rp71.541,00 Rp6.936,30 Rp 6.680.595,01 153,24 Rp15.890,00 Rp7.902,65 Rp 7.287.921,83 152,55 Rp419.699,00 Rp8.915,20 Rp 9.109.902,29 152,09 Rp759.053,00 Rp11.994,10 Rp10.324.555,93 151,63 Rp1.132.343,00 Rp13.048,30 Rp11.539.209,57 150,94 Rp1.698.534,00 Rp15.337,40 Rp13.361.190,03 150,25 Rp2.758.986,00 Rp17.780,40 Rp15.183.170,49 150,02 Rp3.170.778,00 Rp22.208,40 Rp15.790.497,31 149,79 Rp3.583.275,00 Rp25.282,80 Rp16.397.824,13 149,33 Rp4.740.132,00 Rp28.375,80 Rp17.612.477,76 149,1 Rp5.466.199,00 Rp33.246,60 Rp18.219.804,58 148,64 Rp6.962.923,00 Rp36.936,60 Rp19.434.458,22 148,41 Rp7.835.154,00 Rp40.690,90 Rp20.041.785,04 147,95 Rp9.620.010,00 Rp42.707,50 Rp21.256.438,68 147,72 Rp10.569.494,00 Rp44.793,50 Rp21.863.765,50 147,26 Rp12.948.310,00 Rp47.088,10 Rp23.078.419,14 146,8 Rp15.922.531,00 Rp54.136,90 Rp24.293.072,78 146,57 Rp17.812.368,00 Rp56.640,10 Rp24.900.399,60 146,11 Rp21.614.021,00 Rp59.263,90 Rp26.115.053,24 145,88 Rp25.761.277,00 Rp71.050,90 Rp26.722.380,06 Dari Tabel diatas dapat dilihat bahwa penambahan biaya akibat penambahan tenaga kerja lebih murah dibandingkan dengan biaya penambahan jam lembur pada durasi percepatan proyek yang sama. Biaya mempercepat durasi proyek penambahan jam lembur atau penambahan tenaga kerja lebih murah dibandingkan dengan biaya yang harus dikeluarkan apabila proyek mengalami keterlambatan dan dikenakan denda. 98

BAB VI KESIMPULAN DAN SARAN

6.1. Kesimpulan

Berdasarkan data serta hasil analisis dan pembahasan yang dilakukan pada Proyek Pembangunan Hotel Cordela Yogyakarta, dapat ditarik kesimpulan sebagai berikut: 1. Waktu dan biaya optimum akibat penambahan lembur 1 jam didapat pada umur proyek 153,51 hari kerja dengan total biaya proyek sebesar Rp2.634.803.961,39. Untuk penambahan lembur 2 jam didapat pada umur proyek 152,63 hari kerja dengan total biaya proyek sebesar Rp2.635.453.163,77, dan untuk penambahan lembur 3 jam didapat pada umur proyek 152,55 hari kerja dengan total biaya proyek sebesar Rp2.636.226.856,55. Dari ketiga penambahan jam lembur didapatkan biaya termurah yaitu terdapat pada penambahan lembur 1 jam dengan durasi 153,51 hari dan total biaya proyek Rp2.634.803.961,39. 2. Waktu dan biaya total akibat penambahan tenaga kerja 1 didapat pada umur proyek 153,51 hari kerja dengan total biaya proyek sebesar Rp2.637.198.442,50. Untuk penambahan tenaga kerja 2 didapat pada umur proyek 152,63 hari kerja dengan total biaya proyek sebesar Rp2.636.000.497,50, dan untuk penambahan tenaga kerja 3 didapat pada umur proyek 152,55 hari kerja dengan total biaya proyek sebesar Rp2.635.888.559,43. 3. Biaya mempercepat durasi proyek dengan penambahan jam lembur atau penambahan tenaga kerja lebih murah dibandingkan dengan biaya yang harus dikeluarkan apabila proyek mengalami keterlambatan dan dikenakan denda.

6.2. Saran

1. Pembuatan hubungan antar pekerjaan dalam Microsoft Project hendaknya dilakukan secara cermat dan teliti agar diperoleh hasil analisis yang akurat. 99 2. Melakukan pengecekan ulang terhadap durasi secara berkala setiap melakukan pengubahan data. 3. Penambahan data berupa metode konstruksi akan lebih mempermudah dalam pembuatan Microsoft Project. 4. Pada penelitian ini, hendaknya mengetahui bagaimana keadaan di lapangan secara langsung agar pembuatan hubungan antar pekerjaan dalam Microsoft Project lebih akurat. 5. Memiliki data yang lengkap dan valid agar bisa megetahui perbandingan yang akurat dari hasil program Microsoft Project.

Dokumen yang terkait

ANALISIS WAKTU DAN BIAYA PROYEK KONSTRUKSI DENGAN PENAMBAHAN JAM KERJA (LEMBUR) DIBANDINGKAN DENGAN PENAMBAHAN TENAGA KERJA MENGGUNAKAN METODE TIME COST TRADE OFF

1 5 11

ANALISIS BIAYA DAN WAKTU PROYEK KONSTRUKSI DENGAN PENAMBAHAN JAM KERJA (LEMBUR) DIBANDINGKAN DENGAN PENAMBAHAN TENAGA KERJA MENGGUNAKAN METODE TIME COST TRADE OFF

0 7 1

ANALISIS BIAYA DAN WAKTU PROYEK KONSTRUKSI DENGAN PENAMBAHAN JAM KERJA (LEMBUR) DIBANDINGKAN DENGAN PENAMBAHAN TENAGA KERJA MENGGUNAKAN METODE TIME COST TRADE OFF

0 4 3

ANALISIS BIAYA DAN WAKTU PROYEK KONSTRUKSI DENGAN PENAMBAHAN JAM KERJA (LEMBUR) DIBANDINGKAN DENGAN PENAMBAHAN TENAGA KERJA MENGGUNAKAN METODE TIME COST TRADE OFF (Studi Kasus : Pekerjaan Pembangunan Hotel Cordela Yogyakarta Lantai 4 – Lantai Atap)

0 4 131

ANALISIS BIAYA DAN WAKTU PROYEK KONSTRUKSI DENGAN PENAMBAHAN JAM KERJA (LEMBUR) DIBANDINGKAN DENGAN PENAMBAHAN TENAGA KERJA MENGGUNAKAN METODE TIME COST TRADE OFF (Studi Kasus : Pekerjaan Pembangunan Jembatan Sungai Naik – Kabupaten Musi Rawas)

0 11 110

ANALISIS BIAYA DAN WAKTU PROYEK KONSTRUKSI DENGAN PENAMBAHAN JAM KERJA (LEMBUR) DIBANDINGKAN DENGAN PENAMBAHAN TENAGA KERJA MENGGUNAKAN METODE TIME COST TRADE OFF (Studi Kasus : Pekerjaan Proyek Pembangunan Gedung Twin Building UMY (Lantai Dasar – Lantai

1 10 129

ANALISIS BIAYA DAN WAKTU PROYEK KONSTRUKSI DENGAN PENAMBAHAN JAM KERJA (LEMBUR) DIBANDINGKAN DENGAN PENAMBAHAN TENAGA KERJA MENGGUNAKAN METODE TIME COST TRADE OFF (Studi Kasus : Pekerjaan Proyek Pembangunan Hotel Tosan Solo Baru (Lantai Dasar – Lantai 4))

2 13 104

ANALISIS BIAYA DAN WAKTU PROYEK KONSTRUKSI DENGAN PENAMBAHAN JAM KERJA (LEMBUR) DIBANDINGKAN DENGAN PENAMBAHAN TENAGA KERJA MENGGUNAKAN METODE TIME COST TRADE OFF (Studi Kasus : Pembangunan Rumah Susun TNI Wilayah Jawa Barat)

2 12 113

ANALISIS WAKTU DAN BIAYA PROYEK KONSTRUKSI DENGAN PENAMBAHAN JAM KERJA (LEMBUR) DIBANDINGKAN DENGAN PENAMBAHAN TENAGA KERJA MENGGUNAKAN METODE TIME COST TRADE OFF

0 6 109

OPTIMASI BIAYA DAN WAKTU PROYEK KONSTRUKSI DENGAN PENAMBAHAN JAM KERJA (LEMBUR) DIBANDINGKAN DENGAN PENAMBAHAN TENAGA KERJA MENGGUNAKAN METODE TIME COST TRADE OFF (Studi kasus : Proyek Pembangunan Gedung Indonesia)

1 4 64