Prencanaan Atap Prencanaan Atap Prencanaan Atap Beban P

commit to user 30 Tugas Akhir Perencanaan Struktur Factory Outlet dan Resto 2 Lantai

BAB 3 Prencanaan Atap

Beban bracing = 10 x beban kuda-kuda = 0,1 x 50,5 = 5,05 kg Beban plafon = Luas plafon abjk x berat plafon = 6,345x 18 = 114,21 kg Beban P 2 Beban gording = Berat profil gording x Panjang Gording = 11 x 5,625 = 61,875 kg Beban atap = Luas atap atap bcij x berat atap = 10,594 x 50 = 529,7 kg Beban kuda-kuda = ½ x Btg 5 + 9 + 10+6 x berat profil kuda kuda = ½ x 2,165 + 1,083 + 2,165 + 2,165 x 25 = 94,725 kg Beban plat sambung = 30 x beban kuda-kuda = 0,3 x 94,725 = 28,418 kg Beban bracing = 10 x beban kuda-kuda = 0,1 x 94,725 = 9,472 kg Beban P 3 Beban gording = Berat profil gording x Panjang Gording = 11 x 3,75 = 41,25 kg Beban atap = Luas atap cdhi x berat atap = 7,031 x 50 = 351,55 kg commit to user 31 Tugas Akhir Perencanaan Struktur Factory Outlet dan Resto 2 Lantai

BAB 3 Prencanaan Atap

Beban kuda-kuda = ½ x Btg6 +11 +12 +7 x berat profil kuda kuda = ½ x 2,165 + 2,165 + 2,864 +2,165 x 25 = 116,988 kg Beban plat sambung = 30 x beban kuda-kuda = 0,3 x 116,988 = 35,096 kg Beban bracing = 10 x beban kuda-kuda = 0,1 x 116,988 = 11,699 kg Beban P 4 Beban gording = Berat profil gording x Panjang Gording = 11 x 1,875 = 20,625 kg Beban atap = Luas atap degh x berat atap = 3,469 x 50 = 173,45 kg Beban kuda-kuda = ½ x Btg7 + 13 + 14 + 8 x berat profil kuda kuda = ½ x 2,165 +3,248 +3,750 +2,165 x 25 = 141,6 kg Beban plat sambung = 30 x beban kuda-kuda = 0,3 x 141,6 = 42,48 kg Beban bracing = 10 x beban kuda-kuda = 0,1 x 141,6 = 14,16 kg commit to user 32 Tugas Akhir Perencanaan Struktur Factory Outlet dan Resto 2 Lantai

BAB 3 Prencanaan Atap Beban P

5 Beban atap = Luas atap efg x berat atap = 0,422 x 50 = 21,1 kg Beban kuda-kuda = ½ x Btg8 + 15 x berat profil kuda kuda = ½ x 2,165 +4,33 x 25 = 81,187 kg Beban plat sambung = 30 x beban kuda-kuda = 0,3 x 81,187 = 24,356 kg Beban bracing = 10 x beban kuda-kuda = 0,1 x 81,187 = 8,119 kg Beban P 6 Beban plafon = Luas atap efg x berat plafon = 0,422 x 18 = 7,596 kg Beban kuda-kuda = ½ x Btg4 + 14 + 15 x berat profil kuda kuda = ½ x 1,875 +3,75 +4,33 x 25 = 124,437 kg Beban plat sambung = 30 x beban kuda-kuda = 0,3 x 124,437 = 37,331 kg Beban bracing = 10 x beban kuda-kuda = 0,1 x 124,437 = 12,444 kg commit to user 33 Tugas Akhir Perencanaan Struktur Factory Outlet dan Resto 2 Lantai

BAB 3 Prencanaan Atap Beban P