Lean Implementation Strategies and Tactics 405

Chapter 19. Lean Implementation Strategies and Tactics 405

distributions, box plots, and a four-way probability plot. Also, more traditional lean tools were used, such as listing the process steps and determining which could be done externally while the machine was running and which had to be done internally while the machine was down. These activities were prioritized, from those taking the most time to those taking the least. A fishbone diagram of the materials, man, methods, machine, measurement, and environment causal factors effecting inefficient changeovers was developed. The top two causal factors were identified as waiting for a changeover cart and the process of heating the die, which accounted for 38 percent of the changeover time, or 1.3 hours per changeover. They also discovered 12 of 22 other steps that could be done while the machine was running (external).

The Black Belt in training generated a brainstorm of ideas for improvement with some input from the floor. This was narrowed down to action items to be implemented:

◆ Schedule mold changes to coincide with lunch breaks so the dies could be heated during lunch (they could not justify the cost of

equipment to preheat the dies). ◆ Add one additional cart, which would be enough to optimize the

carts needed. ◆ Assign a dedicated changeover team instead of asking operators to

do it, so they could prepare a lot of the external changeover items while the machines were running.

The results exceeded the goal. Detailed data were collected, put on run charts and statistically analyzed. It showed significant improve- ments. The result was a 98 percent improvement resulting in 2,828 parts per million defects (defining a defect as a changeover taking more than 2.5 hours). The average changeover took 1.2 hours, well below the 2.5 hour target. Analysis of the savings focused on the reduced amount of labor for changeovers, which amounted to almost $300,000 per year. Actually, the number of changeovers done in a week was over the budgeted number, and they had a parallel program to stabilize the schedule and reduce the number of changeovers. So there were arguments about whether her project should get credit for the labor savings based on the current number of changeovers or on the anticipated reduced number of changeovers.

So this was a big success, right? Or was it? Let’s consider what’s wrong with this picture:

1. The total process took several months. Much of that time was spent on sophisticated statistical analysis and preparation of

T HE T OYOTA W AY F IELDBOOK

presentation materials. If an experienced lean specialist did this, it could have been done within a one-week kaizen workshop.

2. The young engineer did most of the work while working mostly alone. There was little involvement or buy in of the workforce in the area.

3. The young engineer ruled out some of the most important ideas. For example, she ruled out preheating the molds, which would have had a major impact. A more experienced manufacturing change agent would have fought for this.

4. The objective of 2.5 hours is not a challenging goal, and even

1.2 hours is not a stretch objective for an injection-molding changeover. A more reasonable goal would have been 15 to 20 minutes, and a stretch objective would be five minutes, which is done routinely in lean plants. A 15-minute changeover could have allowed for more changeovers, reducing batch size, and still reduced the amount of labor significantly.

5. The overall value stream became less lean. There was no value stream map done. After the fact, a map showed that there had been five days of injected molded parts after molding, before the changeover reduction activities. By reducing the time of changeovers, doing changeovers only around lunch, and then reducing the number of changeovers, days of molded parts inventory actually increased, increasing flow days. Value stream mapping would have suggested reducing changeover in order to increase the frequency of changeovers to drive down inventory.

Dokumen yang terkait

ALOKASI WAKTU KYAI DALAM MENINGKATKAN KUALITAS SUMBER DAYA MANUSIA DI YAYASAN KYAI SYARIFUDDIN LUMAJANG (Working Hours of Moeslem Foundation Head In Improving The Quality Of Human Resources In Kyai Syarifuddin Foundation Lumajang)

1 46 7

Analisis Komparasi Internet Financial Local Government Reporting Pada Website Resmi Kabupaten dan Kota di Jawa Timur The Comparison Analysis of Internet Financial Local Government Reporting on Official Website of Regency and City in East Java

19 819 7

FAKTOR-FAKTOR YANG BERPENGARUH TERHADAP PENDAPATAN TENAGA KERJA PENGRAJIN ALUMUNIUM DI DESA SUCI KECAMATAN PANTI KABUPATEN JEMBER The factors that influence the alumunium artisans labor income in the suci village of panti subdistrict district jember

0 24 6

The Correlation between students vocabulary master and reading comprehension

16 145 49

An analysis of moral values through the rewards and punishments on the script of The chronicles of Narnia : The Lion, the witch, and the wardrobe

1 59 47

The Effectiveness of Computer-Assisted Language Learning in Teaching Past Tense to the Tenth Grade Students of SMAN 5 Tangerang Selatan

4 116 138

The correlation between listening skill and pronunciation accuracy : a case study in the firt year of smk vocation higt school pupita bangsa ciputat school year 2005-2006

9 128 37

DESKRIPSI PELAKSANAAN PERJANJIAN KREDIT USAHA RAKYAT KEPADA USAHA MIKRO KECIL dan MENENGAH (Studi Pada Bank Rakyat Indonesia Unit Way Halim)

10 98 46

Model Stokastik Curah Hujan Harian dari beberapa Stasiun Curah Hujan di Way Jepara

6 35 58

PENGARUH KOSENTRASI SARI KUNYIT PUTIH (Curcuma zediaria) TERHADAP KUALITAS TELUR ASIN DITINJAU DARI AKTIVITAS ANTIOKSIDAN, TOTAL FENOL, KADAR PROTEIN DAN KADAR GARAM The Addition of White Turmeric (Curcuma zedoaria) Concentrated Base on Quality Antioxidan

1 1 8