Penulangan Balok Portal
7.3 Penulangan Balok Portal
7.3.1 Perhitungan Tulangan Lentur Rink Balk
Bidang momen rink balk dan bidang geser rink balk dapat dilihat pada Gambar
7.5 dan 7.6.
Gambar 7.5 Bidang Momen Ringbalk As F (1-19)
Gambar 7.6 Bidang Geser Ringbalk As 4 (A-J)
Data perencanaan :
h = 350 mm
b = 250 mm p = 40 mm fy = 320 Mpa f’c = 20 MPa Ø t = 19 mm Ø s = 10 mm
d =h-p-Ø s - ½.Ø t = 350 – 40 – 10 - ½.19 = 290,5 mm
0,85.f' c
= 0,02945 r max = 0,75 . rb = 0,75 . 0,02945
= 0,02209 r min
fy
a. Daerah Tumpuan
Dari Perhitungan SAP 2000 diperoleh momen terbesar pada As F (1 – 19) batang 412 (Output SAP Portal hal. 98)
Mu = 1609,81 kgm = 1,609 × 10 7 Nmm
Mn = φ
Mu
= 2,011 × 10 7 Nmm
Rn =
Mn
0,953 Nmm 2
0,85.f' c
2.m.Rn
= 0,00307 r<r max ® dipakai tulangan tunggal r> r min ® dipakai r min = 0,00438 As perlu = r min .b.d = 0,00438 × 250 × 290,5 = 318,098 mm 2
Digunakan tulangan D 19 = ¼ . p . (19) 2 = 283,39 mm 2
Jumlah tulangan =
As ada = 2 . ¼ . p . 19 2 = 566,77 mm 2 > As ……… aman !
c f' 0,85 f'
ada fy As
Mn ada = As ada × fy (d – a/2) = 566,77 × 320 (290,5 – 42,67/2)
= 4,8817. 10 7 Nmm
Mn ada > Mn ......... aman !
Jadi dipakai tulangan 2 D 19 mm Jadi dipakai tulangan 2 D 19 mm
Dari Perhitungan SAP 2000 diperoleh momen terbesar pada As F (1 – 19) batang 413 (Output SAP Portal hal. 98)
Mu = 1073,72 kgm = 1,074 × 10 7 Nmm
0,85.f' c
2.m.Rn
= 0,00201 r < r max ® dipakai tulangan tunggal r > r min ® dipakai r min = 0,00438 As perlu = r min .b.d = 0,00438 × 250 × 290,5 = 318,098 mm 2
Digunakan tulangan D 19 = ¼ . p . (19) 2 = 283,39 mm 2
Jumlah tulangan =
As ada = 2 . ¼ . p . 19 2 = 566,77 mm 2 > As ……… aman !
c f' 0,85 f'
ada fy As
Mn ada = As ada × fy (d – a/2) = 566,77 × 320 (290,5 – 42,67/2)
= 4,8817. 10 7 Nmm
7.3.2 Perhitungan Tulangan Geser Ring Balk
Dari Perhitungan SAP 2000 diperoleh gaya geser terbesar pada As 4 (A-J) batang 437 (Output SAP Portal hal. 49) Vu
= 2215,08 = 22150,8 N Vc = 1/6 .
f c ' .b.d
= 1/6 ×
20 × 250 × 290,5 = 54131,48 N
Ø Vc = 0,75 × 54131,48 = 32478,88 N
3 Ø Vc = 3 × 32478,88 = 97436,66 N Syarat tulangan geser : Ø Vc < Vu < 3 Ø Vc
: 32478,88 N < 22150,8 N < 97436,66 N
Jadi tidak diperlukan tulangan geser Smax = d/2 = 290,5/2 = 145,25 mm ~ 140 mm
Dipakai tulangan Ø 10 – 140 mm
7.3.3 Hitungan Tulangan Lentur Balok Portal Memanjang
Bidang momen balok portal memanjang dan bidang geser balok portal memanjang terlihat dalam Gambar 7.7 dan 7.8.
Gambar 7.7 Bidang Momen Balok Portal Memanjang As F (1-19)
Gambar 7.8 Bidang Geser Balok Portal Memanjang As G (1-19)
Untuk pehitungan tulangan lentur balok portal memanjang, diambil pada bentang dengan moment terbesar dari perhitungan SAP 2000, yaitu pada batang 256.
12291,24
8906,88
-14875,60
Data perencanaan :
h = 400 mm
b = 300 mm p = 40 mm fy = 320 Mpa f’c = 20 MPa Ø t = 22 mm Ø s = 10 mm
d =h-p-Ø s - ½.Ø t = 400 – 40 – 10 - ½.22 =339 mm
0,85.f' c
= 0,02945 r max = 0,75 . rb = 0,75 . 0,02945
= 0,02209 r min
fy
a. Daerah Tumpuan
Dari Perhitungan SAP 2000 diperoleh momen terbesar pada As F (1 – 19) batang 256 (Output SAP Portal hal. 79)
Mu = 14875,60 kgm = 14,876 × 10 7 Nmm
Mn = φ
Mu
= 18,595 × 10 7 Nmm
Rn =
Mn
5,394 Nmm 2
0,85.f' c
2.m.Rn
= 0,02101 r<r max ® dipakai tulangan tunggal
r> r min ® dipakai r = 0,02101
As perlu = r. b . d = 0,02101 × 300 × 339 = 2136,717 mm 2
Digunakan tulangan D 22 = ¼ . p . (22) 2 = 379,94 mm 2
Jumlah tulangan =
As ada = 6 . ¼ . p . 22 2 = 2279,64 mm 2 > As ……… aman !
c f' 0,85 f'
ada fy As
Mn ada = As ada × fy (d – a/2) = 2279,64 × 320 (339 – 143,04/2)
= 19,512. 10 7 Nmm
Mn ada > Mn ......... aman ! Kontrol Spasi :
n tulangan - sengkang 2 - 2p - b f f
22 6 - 10 2. - 2. 40 2 - 300
= 13,6 mm < 25 mm (dipakai tulangan 2 lapis) = 13,6 mm < 25 mm (dipakai tulangan 2 lapis)
Di pakai d
d 1 =h-p-Ø s - ½Ø t
= 400 – 40 –10 – ½ .22 = 339 mm
d 2 =h-p-Ø s -Ø t - s - ½Ø t
T = As ada . fy = 2279,64. 320
= 7,295.10 5 Mpa
ØMn = Ø . T ( d – a/2 )
= 0,85 . 7,295.10 5 (321,67 – 143,04/2 ) = 15,511 × 10 7 Nmm > Mu ® Aman..!!
Kontrol Spasi : S =
n tulangan - sengkang 2 - 2p - b f f
22 4 - 10 2. - 2. 40 2 - 300
= 37,33 mm > 25 mm ........ok.
b. Daerah Lapangan
Dari Perhitungan SAP 2000 diperoleh momen terbesar pada As F (1 – 19) batang 256 (Output SAP Portal hal. 79)
Mu = 8906,88 kgm = 8,907 × 10 7 Nmm
0,85.f' c
2.m.Rn
= 0,01129 r<r max ® dipakai tulangan tunggal
r> r min ® dipakai r = 0,01129
As perlu = r. b . d = 0,01129 × 300 × 339
= 1148,193 mm 2
Digunakan tulangan D 22 = ¼ . p . (22) 2 = 379,94 mm 2
Jumlah tulangan =
As ada = 4 . ¼ . p . 22 2 = 1519,76 mm 2 > As ……… aman !
c f' 0,85 f'
ada fy As
Mn ada = As ada × fy (d – a/2) = 1519,76 × 320 (339 – 95,36/2)
Mn ada > Mn ......... aman ! Kontrol Spasi :
n tulangan - sengkang 2 - 2p - b f f
22 4 - 10 2. - 2. 40 2 - 300
= 37,33 mm > 25 mm..................ok.
Jadi dipakai tulangan 4 D 22 mm
7.3.4 Perhitungan Tulangan Geser Balok Portal Memanjang
Dari Perhitungan SAP 2000 diperoleh gaya geser terbesar pada As G (1-19) batang 257 (Output SAP Portal hal. 26) Vu
= 12291,24 kg = 122912,4 N Vc = 1/6 .
f c ' .b.d
20 × 300 × 339 = 75802,70 N
Ø Vc = 0,75 × 75802,70 = 45481,62 N
3 Ø Vc = 3 × 45481,62 = 136444,87 N Syarat tulangan geser : Ø Vc < Vu < 3 Ø Vc : 45481,62 N < 122912,4 N < 136444,87 N Jadi diperlukan tulangan geser
Ø Vs = Vu - Ø Vc = 122912,4 N – 45481,62 N = 77430,78 N
Vs perlu =
S= Vsperlu
= 98,98 mm ~ 90 mm
Smax = d/2 = 339/2 = 169,5 mm
B1 (30x40)
Tumpuan
Lapangan
Vs ada > Vs perlu 141928 N > 129051,3 N........(Aman)
Dipakai tulangan Ø 10 – 90 mm
7.3.5 Hitungan Tulangan Lentur Balok Portal Melintang
Bidang momen balok portal melintang dan bidang geser balok portal melintang terlihat dalam Gambar 7.9 dan 7.10.
Gambar 7.9 Bidang Momen Balok Portal Melintang As 3 (A - J)
Gambar 7.10 Bidang Geser Balok Portal Melintang As 3 (A - J)
Untuk pehitungan tulangan lentur balok portal melintang, diambil pada bentang
-11270,22
7499,74
-15081,92
Data perencanaan :
h = 400 mm
b = 300 mm p = 40 mm fy = 320 Mpa f’c = 20 MPa Ø t = 22 mm Ø s = 10 mm
d =h-p-Ø s - ½.Ø t = 400 – 40 – 10 - ½.22 =339 mm
0,85.f' c
= 0,02945 r max = 0,75 . rb = 0,75 . 0,02945
= 0,02209 r min
fy
a. Daerah Tumpuan
Dari Perhitungan SAP 2000 diperoleh momen terbesar pada As 3 (A – J) batang 283 (Output SAP Portal hal. 84)
Mu = 15081,92 kgm = 15,082 × 10 7 Nmm
Mn = φ
Mu
= 18,853 × 10 7 Nmm
Rn =
Mn
5,468 Nmm 2
0,85.f' c
2.m.Rn
= 0,02139 r<r max ® dipakai tulangan tunggal
r> r min ® dipakai r = 0,02139
As perlu = r. b . d = 0,02139 × 300 × 339 = 2175,363 mm 2
Digunakan tulangan D 22 = ¼ . p . (22) 2 = 379,94 mm 2
Jumlah tulangan =
As ada = 6 . ¼ . p . 22 2 = 2279,64 mm 2 > As ……… aman !
c f' 0,85 f'
ada fy As
Mn ada = As ada × fy (d – a/2) = 2279,64 × 320 (339 – 143,04/2)
= 19,512. 10 7 Nmm
Mn ada > Mn ......... aman ! Kontrol Spasi :
n tulangan - sengkang 2 - 2p - b f f
22 6 - 10 2. - 2. 40 2 - 300
= 13,6 mm < 25 mm (dipakai tulangan 2 lapis) = 13,6 mm < 25 mm (dipakai tulangan 2 lapis)
Di pakai d
d 1 =h-p-Ø s - ½Ø t
= 400 – 40 –10 – ½ .22 = 339 mm
d 2 =h-p-Ø s -Ø t - s - ½Ø t
T = As ada . fy = 2279,64. 320
= 7,295.10 5 Mpa
ØMn = Ø . T ( d – a/2 )
= 0,85 . 7,295.10 5 (321,67 – 143,04/2 ) = 15,511 × 10 7 Nmm > Mu ® Aman..!!
Kontrol Spasi : S =
n tulangan - sengkang 2 - 2p - b f f
22 4 - 10 2. - 2. 40 2 - 300
= 37,33 mm > 25 mm ........ok.
b. Daerah Lapangan
Dari Perhitungan SAP 2000 diperoleh momen terbesar pada As 3 (A – J) batang 283 (Output SAP Portal hal. 79)
Mu = 7499,74 kgm = 7,499 × 10 7 Nmm
0,85.f' c
2.m.Rn
= 0,00931 r<r max ® dipakai tulangan tunggal
r> r min ® dipakai r = 0,00931
As perlu = r. b . d = 0,00931 × 300 × 339
= 946,827 mm 2
Digunakan tulangan D 22 = ¼ . p . (22) 2 = 379,94 mm 2
Jumlah tulangan =
As ada = 3 . ¼ . p . 22 2 = 1139,82 mm 2 > As ……… aman !
c f' 0,85 f'
ada fy As
Mn ada = As ada × fy (d – a/2) = 1139,82 × 320 (339 – 71,52/2)
Mn ada > Mn ......... aman ! Kontrol Spasi :
n tulangan - sengkang 2 - 2p - b f f
22 3 - 10 2. - 2. 40 2 - 300
= 67 mm > 25 mm..................ok.
Jadi dipakai tulangan 3 D 22 mm
7.3.6 Perhitungan Tulangan Geser Balok Portal Melintang
Dari Perhitungan SAP 2000 diperoleh gaya geser terbesar pada As 3 (A - J) batang 283 (Output SAP Portal hal. 30) Vu
= 11270,2 kg = 112702 N Vc = 1/6 .
f c ' .b.d
20 × 300 × 339 = 75802,70 N
Ø Vc = 0,75 × 75802,70 = 45481,62 N
3 Ø Vc = 3 × 45481,62 = 136444,87 N Syarat tulangan geser : Ø Vc < Vu < 3 Ø Vc
: 45481,62 N < 112702 N < 136444,87 N
Jadi diperlukan tulangan geser
Ø Vs = Vu - Ø Vc = 112702 N N – 45481,62 N = 67220,38 N
Vs perlu =
S= Vsperlu
= 114,01 mm ~ 110 mm
B2 (30x40)
Tumpuan
Lapangan
Vs ada > Vs perlu 116122,91 N > 112033,97 N........(Aman)
Dipakai tulangan Ø 10 – 110 mm
7.3.7 Hitungan Tulangan Lentur Sloof
Bidang momen sloof dan bidang geser sloof terlihat dalam Gambar 7.11 dan 7.12.
Gambar 7.11 Bidang Momen Sloof As 16 (A - J)
Gambar 7.12 Bidang Geser Sloof As E (5 - 15)
1200,03 -2484,99
Data perencanaan :
h = 350 mm
b = 250 mm p = 40 mm fy = 320 Mpa f’c = 20 MPa Ø t = 19 mm Ø s = 10 mm
d =h-p-Ø s - ½.Ø t = 350 – 40 – 10 - ½.19 = 290,5 mm
0,85.f' c
= 0,02945 r max = 0,75 . rb = 0,75 . 0,02945
= 0,02209 r min
fy
a. Daerah Tumpuan
Dari Perhitungan SAP 2000 diperoleh momen terbesar pada As 16 (A – J) batang 150 (Output SAP Portal hal. 69)
Mu = 2484,99 kgm = 2,485× 10 7 Nmm
Mn = φ
Mu
= 3,106 × 10 7 Nmm
Rn =
Mn
1,472 Nmm 2
0,85.f' c
2.m.Rn
= 0,00482 r<r max ® dipakai tulangan tunggal r> r min ® dipakai r min = 0,00482
As perlu = r .b.d = 0,00482 × 250 × 290,5 = 350,053 mm 2
Digunakan tulangan D 19 = ¼ . p . (19) 2 = 283,39 mm 2
Jumlah tulangan =
As ada = 2 . ¼ . p . 19 2 = 566,77 mm 2 > As ……… aman !
c f' 0,85 f'
ada fy As
Mn ada = As ada × fy (d – a/2) = 566,77 × 320 (290,5 – 42,67/2)
= 4,8817. 10 7 Nmm
Mn ada > Mn ......... aman !
Jadi dipakai tulangan 2 D 19 mm Jadi dipakai tulangan 2 D 19 mm
Dari Perhitungan SAP 2000 diperoleh momen terbesar pada As 16 (A – J) batang 150 (Output SAP Portal hal. 69)
Mu = 1200,03 kgm = 1,2 × 10 7 Nmm
0,85.f' c
2.m.Rn
= 0,00227 r < r max ® dipakai tulangan tunggal r > r min ® dipakai r min = 0,00438 As perlu = r min .b.d = 0,00438 × 250 × 290,5 = 318,098 mm 2
Digunakan tulangan D 19 = ¼ . p . (19) 2 = 283,39 mm 2
Jumlah tulangan =
As ada = 2 . ¼ . p . 19 2 = 566,77 mm 2 > As ……… aman !
c f' 0,85 f'
ada fy As
Mn ada = As ada × fy (d – a/2) = 566,77 × 320 (290,5 – 42,67/2)
= 4,8817. 10 7 Nmm
7.3.8 Perhitungan Tulangan Geser Sloof
Dari Perhitungan SAP 2000 diperoleh gaya geser terbesar pada As E(1 – 15) batang
85 (Output SAP Portal hal. 7) Vu
= 3673,86 kg = 36738,6 N Vc = 1/6 .
f c ' .b.d
= 1/6 ×
20 × 250 × 290,5 = 54131,48 N
Ø Vc = 0,75 × 54131,48 = 32478,88 N
3 Ø Vc = 3 × 32478,88 = 97436,66 N Syarat tulangan geser : Ø Vc < Vu < 3 Ø Vc
: 32478,88 N < 36738,6 N < 97436,66 N
Jadi diperlukan tulangan geser
Ø Vs = Vu - Ø Vc = 36738,6 N – 32478,88 N = 4259,72 N
Vs perlu =
S= Vsperlu
Smax = d/2 = 339/2 = 169,5 mm ~ 150 mm Vs ada
Vs ada > Vs perlu 72973,6 N > 7099,53 N........(Aman)
Dipakai tulangan Ø 10 – 150 mm
7.3.9 Hitungan Tulangan kolom
Bidang momen kolom, geser kolom dan aksial kolom terlihat dalam Gambar 7.13-
7.15.
Gambar 7.13 Bidang Momen Kolom As F (1 - 19)
Gambar 7.14 Bidang Geser Kolom As F (1 - 19)
Gambar 7.15 Bidang Aksial kolom As B (1 - 5)
-6734,70
-45583,55
-1760,18
Untuk pehitungan tulangan lentur kolom, diambil pada bentang dengan moment terbesar dari perhitungan SAP 2000, yaitu pada batang 198
Data perencanaan :
b = 400 mm
h = 400 mm f’c = 20 MPa fy = 320 MPa
Ø tulangan =16 mm Ø sengkang = 10 mm s (tebal selimut) = 40 mm
Dari perhitungan SAP didapat :
Pu = 45583,55 kg
= 455835,5 N
Mu = 6734,70 kgm
= 6,7347 ×10 7 Nmm
d = h – s – Ø sengkang –½ Ø tulangan utama = 400 – 40 – 10 –½ .16 = 342 mm d’
= h – d = 400 – 342= 58 mm
e min = 0,1.h = 0,1. 400 = 40 mm Cb =
ab = β 1 .cb = 0,85 × 223,04 = 189,584
Pn b = 0,85 × f’c × ab × b = 0,85 × 20 ×189,584 × 400
= 12,8917 × 10 5 N
Pn Perlu =
Pnb
12,8917 5 ´
= 19,833 ×10 5 N
= -5,84 mm 2
As t = 1 % Ag =0,01 . 400. 400 = 1600 mm 2 As t = As’ + As , dimana As t > As’
Dipakai As’ = 800 mm 2 Menghitung jumlah tulangan :
= 803,84 mm 2 > 800 mm 2
As ada > As perlu………….. Ok! Kontrol Spasi :
n tulangan - sengkang - 2 - 2p - b f f
16 4 - 10 2. - 2. 40 2 - 0 40 0
= 78,67 > 25 mm…..oke!!
4 D 16 mm
10 mm-200 mm
4 D 16 mm
400
7.3.10 Hitungan Tulangan Geser Kolom
Vu = 1760,18 kg = 1,760 × 10 4 N
Pu = 45583,55 kg = 455835,5 N
Ø Vc = 0,75 × Vc = 0,75 ×
10 059 , 30 , ´ = 18,035 × 10 4 N
0,5 Ø Vc = 0,5 × 18,035 × 10 4 = 9,018× 10 4 N
Vu < 0,5 Ø Vc => tanpa diperlukan tulangan geser. Dipakai sengkang praktis untuk penghubung tulangan memanjang : Æ10 – 200