110
49. COMMITMENTS continued a. Capital expenditures continued
The above balance includes the following significant agreements: i
Company
Contracting parties
Date of agreement
Significant provisions of the agreement
Total contract value Outstanding
purchase commitment as of
June 30, 2010
Company and Huawei Consortium
“Huawei” September 28,
2007 Procurement and installation
agreement for
Speedy Access Batch 3
US19.2 million and Rp.130,774 million
Rp.296 million
Company and PT Datacomm
Diangraha November 28,
2007 Procurement and installation
agreement Metro Ethernet Batch 2
Rp.238,948 million Rp.757 million Company
and Huawei Tech
March 31,
2008 Procurement and installation
agreement for
Metro Ethernet Batch 3 in Divre V
Rp.103,376 million Rp.1,271 million
Company and
G-Pas Consortium April 18, 2008
Procurement and installation agreement for Outside Plant
Fiber Optic 2008 Batch 8 Divre VII
Rp.142,823 million Rp.30,864 million
Company and PT Konsorsium Jembo-
Karteksi-Tridayasa April 18, 2008
Procurement and installation agreement for Outside Plant
Fiber Optic 2008 Batch 9 Netre Sumbagut Area
Rp.216,498 million Rp.47,527 million
Company and
G-Pas Consortium April 18, 2008
Procurement and installation agreement for Outside Plant
Fiber Optic 2008 Batch 10 in Netre Sumbagsel Area
Rp.117,449 million Rp.48,863 million
Company and PT Telekomindo
Primakarya “Telekomindo”
April 18, 2008 Procurement and installation
agreement for Outside Plant Fiber Optic 2008 Batch 11
Netre Sumbagsel Rp.126,873 million
Rp.5,847 million Company and PT
Brimbun Raya
Indah April 18, 2008
Procurement and installation agreement for Outside Plant
Fiber Optic Batch 12 Netre, Jakarta and West Java
Rp.157,315 million Rp.19,933 million
Company and PT Datacraft Indonesia
December 4,
2008 Procurement and installation
agreement for Tera Router 2008 in Divre I, Divre II and
Divre V Rp.108,968 million
Rp.12,100 million Company and PT
Nokia Siemens
Networks December
5, 2008
Procurement and installation agreement for Softswitch
and modernization of MSAN Divre V and trial location of
Bali and Timika Rp.71,377 million
Rp.1,534 million
PERUSAHAAN PERSEROAN PERSERO P.T. TELEKOMUNIKASI INDONESIA Tbk AND SUBSIDIARIES
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS UNAUDITED continued JUNE 30, 2009 AND 2010,
AND SIX MONTHS PERIOD ENDED JUNE 30, 2009 AND 2010 Figures in tables are presented in millions of Rupiah, unless otherwise stated
111
49. COMMITMENTS continued a. Capital expenditures continued
i Company continued
Contracting parties
Date of agreement
Significant provisions of the agreement
Total contract value Outstanding
purchase commitment as of
June 3, 2010
Company and ISS Reshetnev
March 2, 2009 Procurement agreement for
Telkom-3 Satellite US178.9 million
US129.3 million Company and APT
Satellite Company
Limited March
23, 2009
142E Degree
Orbital Position
Cooperation Agreement
US18.5 million US13.3 million
Company and
Sansaine Huawei
Consortium May 27, 2009
June 15, 2009 a. Cooperation agreement
for procurement
and installation of MSAN ALU
and Secondary Access 2008 Batch 3
b. Cooperation agreement for
procurement and
installation of MSAN ALU and Secondary Access
2008 Batch 1 US6.4 million and
Rp.77,159 million
US5.7 million and Rp.52,646 million
US4.6 million and Rp.41,422 million
US3.4 million and Rp.22,410 million
Company and ZTE Consortium
June 2, 2009 Cooperation agreement for
procurement and installation of
MSAN ALU
and Secondary
Access 2008
Batch 2 US15.1 million and
Rp.60,122 million US9.8 million and
Rp.21,079 million
Company and PT Aldomaru
June 11, 2009 Procurement agreement Roll
Out Infusion PL 2009 Rp.63,761 million
Rp.34,271 million Company and PT
Dharma Kumala
Utama July 29, 2009
Procurement and installation agreement for Fiber Optic
Cable Access RMJ 2009 in Central Java and East
Java Batch 1 Rp.62,180 million
Rp.31,292 million
Company and
Sansaine - Huawei Consortium
August 3, 2009 Procurement and installation
agreement for Softswitch and modernization of MSAN
Divre I, Divre II, Divre III and Divre IV
US14.8 million and Rp.29,140 million
US4.8 million and Rp.18,597 million
Company and
Huawei - Sansaine Consortium
November 24, 2009
Procurement and installation agreement for Palapa Ring
Mataram-Kupang Cable
System Project MKCS US52.3 million and
Rp.114,949 million US52.3
million and
Rp.114,949 million
Company and
Tekken -
DMT Concortium
November 25, 2009
Procurement and installation agreement for Fiber Optic
Cable Access Divre VI Kalimantan
Rp.52,904 million Rp.24,434 million