Performance Security

Section 39. Performance Security

39.1. To guarantee the faithful performance by the winning bidder of its obligations under the contract in accordance with the Bidding Documents, it shall post a performance security prior to the signing of the contract.

39.2. The performance security shall be in an amount not less than the required percentage of the total contract price in accordance with the following schedule: (a)

Amount of Performance Security (Not less than the required

Form of Performance Security percentage of the Total Contract

Price)

a) Cash or cashier’s/manager’s check issued by a Universal or Commercial Bank.

For biddings conducted by LGUs, the Goods and Consulting Services – cashier’s/manager’s check may be issued by Five percent (5%) other banks certified by the BSP as authorized

to issue such financial instrument. (a) Infrastructure Projects – Ten

b) Bank draft/guarantee or irrevocable letter of

percent (10%)

credit issued by a Universal or Commercial Bank: Provided, however, That it shall be confirmed or authenticated by a Universal or Commercial Bank, if issued by a foreign bank.

For biddings conducted by LGUs, bank draft/guarantee, or irrevocable letter of credit may be issued by other banks certified by the BSP as authorized to issue such financial instrument. (a)

c) Surety bond callable upon demand issued by a surety or insurance company duly certified by

Thirty percent (30%) the Insurance Commission as authorized to

issue such security.

39.3. The performance security shall be denominated in Philippine Pesos and posted in favor of the Procuring Entity, which shall be forfeited in the event it is established that the winning bidder is in default in any of its obligations under the contract.

39.4. The performance security shall remain valid until issuance by the Procuring Entity of the Certificate of Final Acceptance.

39.5. The performance security may be released by the Procuring Entity after the issuance of the Certificate of Final Acceptance, subject to the following conditions:

a) Procuring Entity has no claims filed against the contract awardee or the surety company;

b) It has no claims for labor and materials filed against the contractor; and

c) Other terms of the contract. (a)

39.6. For the procurement of Infrastructure Projects, the winning bidder shall post an additional performance security following the schedule above to cover any cumulative increase of more than ten percent (10%) over the original value of the contract as a result of amendments to order or change orders, extra work orders and supplemental agreements, as the case may be. The winning bidder shall cause the extension of the validity of the Performance Security to cover approved contract time extensions.

39.7. In case of a reduction in the contract value, or, in the case of procurement of Infrastructure Projects, for partially completed works under the contract which are usable and accepted by the GoP, and the use of which, in the judgment of the implementing agency or the Procuring Entity, will not affect the structural integrity of the entire project, the said agency or Procuring Entity shall allow a proportional reduction in the original performance security: Provided, That any such reduction is more than ten percent (10%) and that the aggregate of such reductions is not more than fifty percent (50%) of the original Performance Security.