Tugas Akhir
Perencanaan Struktur Gedung Bengkel 2 Lantai
Bab IV Perencanaan Tangga 104
Jarak tulangan 1 m =
3 1000
= 330 mm
Dipakai tulangan D 16 mm – 330 mm
As yang timbul = 3 . ¼ x p x d
2
= 603,186 mm
2
As 547,288.....Aman
4.5. Perencanaan Balok Bordes
qu balok
246
54
3 m
200
Data perencanaan: h = 300 mm
b = 200 mm d`= 54 mm
d = h – d` = 300 – 54 = 246 mm
4.5.1. Pembebanan Balok Bordes Ø
Beban mati q
D
Berat sendiri = 0,20 x 0,30 x 2400
= 144 kgm Berat plat bordes
= 0,15 x 2 x 2400 = 720 kgm +
q
D
= 864 kgm Ø
Akibat beban hidup q
L
q
L
= 300 kgm
commit to user
Tugas Akhir
Perencanaan Struktur Gedung Bengkel 2 Lantai
Bab IV Perencanaan Tangga 105
Ø Beban ultimate q
U
q
U
= 1,2 . q
D
+ 1,6. q
L
= 1,2 . 864 + 1,6.300 = 1516,8 kgm
Ø Akibat reaksi bordes
qU =
. Re
s lebarborde
aksibordes
=
3 78
, 3814
= 1271,6 kgm Ø
Total q
U
= 1516,8 + 1217,6 = 2734,4 kgm
4.5.2. Perhitungan tulangan lentur
Tulangan tumpuan
M
u
= 5720,8 kgm = 5,7208.10
7
Nmm Mn
= f
Mu
= =
8 ,
10 .
7208 ,
5
7
7,15 . 10
7
Nmm m
= 88
, 17
25 .
85 ,
380 .
85 ,
= =
fc fy
rb =
÷÷ ø
ö çç
è æ
+
fy fy
fc
600 600
. .
. 85
, b
=
÷ ø
ö ç
è æ
+ 380 600
600 .
. 380
25 .
85 ,
b = 0,029
r
max
= 0,75 . rb = 0,75 . 0,029
= 0,02175 r
min
= 0,0037
commit to user
Tugas Akhir
Perencanaan Struktur Gedung Bengkel 2 Lantai
Bab IV Perencanaan Tangga 106
Rn =
=
2
.d b
Mn
=
2 7
246 .
200 10
. 15
, 7
5,91 Nmm
r
ada
=
÷ ÷
ø ö
ç ç
è æ
- -
fy 2.m.Rn
1 1
m 1
= .
88 ,
17 1
÷ ÷
ø ö
ç ç
è æ
- -
380 91
, 5
. 88
, 17
. 2
1 1
= 0,0187 r
ada
r
max
r
ada
r
min
di pakai r
ada
= 0,0187 As
= r ada . b . d = 0,0187 x 200 x 246
= 920,04 mm
2
Dipakai tulangan D 16 mm = ¼ . p x 16
2
= 201,06 mm
2
Jumlah tulangan =
06 ,
201 04
, 920
= 4,57 ≈ 5 buah
As yang timbul = 5. ¼ .
π. d
2
= 1005,3 mm
2
As 920,04....... Aman
Dipakai tulangan 5 D 16 mm
a =
200 25
85 ,
380 04
, 20
9 b
c f
0,85 fy
ada As
´ ´
´ =
´ ´
´ = 82,26
Cek jarak =
1 -
n t
- s
2 -
p 2
- b
f f
1 -
5 16
5. -
2.8 -
2.40 -
200 =
= 6 mm 25 mm dipakai tulangan dua lapis
Di pakai d d1 = 246 mm
d2 = d1 – s – 2 x ½ Ø
commit to user
Tugas Akhir
Perencanaan Struktur Gedung Bengkel 2 Lantai
Bab IV Perencanaan Tangga 107
= 246 – 30 – 2 x ½.16 = 200 mm
dx4 = d1 x 2 + d2 x 2 d
5 2
x 200
3 x
246 +
=
= 227,6 mm Mn ada = As ada . fy d – a2
= 920,04. 380 227,6 – 82,262 = 6,51.10
7
Nmm Mn ada Mn
® Aman..
Jadi dipakai tulangan 5 D 16 mm 4.5.3.
Perhitungan Tulangan Geser Balok Bordes
Vu = 4290,6 kg = 42906 N
Vc = .
c f
b.d. .
6 1
= 16 . 200 . 246. 25 . = 41000 N
Æ Vc = 0,75 . Vc = 30750 N
3 Æ Vc = 92250 N Æ Vc Vu 3 Æ Vc
30750 N 42906 N 92250 N Jadi di perlukan tulangan geser
Ø Vs = Vu - Ø Vc
= 42906 N – 30750 N = 12156 N Vs perlu =
75 ,
Vs
f =
75 ,
12156 = 16208 N
Av = 2 . ¼ p 8
2
= 2 . ¼ . 3,14 . 64 = 100,48 mm
2
commit to user
Tugas Akhir
Perencanaan Struktur Gedung Bengkel 2 Lantai
Bab IV Perencanaan Tangga 108
s =
52 ,
579 16208
246 380
48 ,
100 perlu
Vs d
. fy
. Av
= ´
´ =
mm S max = d2 =
2 246
= 123 mm
Jadi dipakai sengkang dengan tulangan D 8 – 120 mm
4.6.Perhitungan Pondasi Tangga
Gambar 4.3 Pondasi Tangga
Direncanakan pondasi telapak dengan kedalaman 1,00 m dan panjang 1,5 m -
Tebal = 250 mm
- Ukuran alas
= 1500 x 1400 mm -
g tanah = 1,75 tm
3
= 1750 kgm
3
- s tanah
= 3 kgcm
2
= 30000 kgm
2
- Pu
= 23059,77 kg
- h = 250 mm
- d = h - p - 12 Ø
t
- Ø
s
= 250 – 50 – ½ .16 – 8 = 184 mm
Pu
Mu
0.63 0.63
0.25 0.75
0.25 1.50
commit to user
Tugas Akhir
Perencanaan Struktur Gedung Bengkel 2 Lantai
Bab IV Perencanaan Tangga 109
4.7. Perencanaan kapasitas dukung pondasi