Penghitungan kelandaian memanjang Dengan menggunakan rumus: Tabel elevasi rencana jalan

commit to user

3.4 Penghitungan Alinemen Vertikal

3.4.1 Penghitungan kelandaian memanjang Dengan menggunakan rumus:

100 × ∆ ∆ = L h g n data perhitungan: Sta A = 0 + 000 hA = 99,91 Sta PV 1 = 0 + 400 hPV 1 = 100,53 Sta PV 2 = 0 + 800 hPV 2 = 103,47 Sta Jembatan = 1 + 300 hJem = 103,47 Sta PV 3 = 2 + 250 hPV 3 = 103,47 Sta PV 4 = 2 + 950 hPV 4 = 104,87 Sta B = 3 + 500 hB = 104,87 Penghitungan: 16 , 100 400 91 , 99 53 , 100 1 = × − = g 74 , 100 400 53 , 100 47 , 103 2 = × − = g 100 450 47 , 103 47 , 103 3 = × − = g 2 , 100 600 47 , 103 87 , 104 4 = × − = g 100 550 87 , 104 87 , 104 5 = × − = g commit to user

3.4.2 Penghitungan lengkung vertikal 1.

PV 1 Gambar 3.8. Lengkung Vertikal PV 1 58 , 16 , 74 , 1 2 = − = − = ∆ g g Perhitungan Lv : a. Syarat keluwesan bentuk m V Lv 48 80 6 , 6 , = × = × = b. Syarat drainase m Lv 2 , 23 58 , 40 40 = × = ∆ × = c. Syarat kenyamanan m ik jam km t V Lv 67 , 66 det 3 80 = × = × = d. Pengurangan goncangan m V Lv 31 , 10 360 58 , 80 360 2 2 = × = ∆ × = Diambil Lv terbesar, yaitu = 66,67m a b c d e g 1 = 0,16 g 2 = 0,74 commit to user m Lv Ev 048 , 800 67 , 66 58 , 800 = × = × ∆ = m Lv X Y 012 , 67 , 66 200 67 , 66 4 1 58 , 200 2 2 = × × × = × × ∆ = Stationing lengkung vertikal PV 1 Sta a = Sta PV 1 – 1 2 Lv = 0+400 – 1 2 66,67 = 0+366,67 m Sta b = Sta PV 1 – 1 4 Lv = 0+400 – 1 4 66,67 = 0+383,33 m Sta c = Sta PV 1 = 0+400 m Sta d = Sta PV 1 + 1 4 Lv = 0+400 + 1 4 66,67 = 0+416,67 m Sta e = Sta PV 1 + 1 2 Lv = 0+400 + 1 2 66,67 = 0+433,33 m Elevasi Lengkung vertikal: Elevasi a = Elevasi PV 1 – ½ Lv x g 1 = 100,53 – ½ 66,67 x 0,16 = 100,477 m Elevasi b = Elevasi PV 1 – ¼ Lv x g 1 + y = 100,53 – ¼ 66,67 x 0,16 + 0,012 = 100,515 m Elevasi c = Elevasi PV 1 + Ev = 100,53 + 0,05 = 100,58 m commit to user Elevasi d = Elevasi PV 1 + ¼ Lv x g 2 + y = 100,53 + ¼ 66,67 x 0,74 + 0,012 = 100,665 m Elevasi e = Elevasi PV 1 + ½ Lv x g 2 = 100,53 + ½ 66,67 x 0,74 = 100,777 m

2. PV

2 . Gambar 3.9. Lengkung Vertikal PV 2 74 , 74 , 2 3 = − = − = ∆ g g Perhitungan Lv : e. Syarat keluwesan bentuk m V Lv 48 80 6 , 6 , = × = × = f. Syarat drainase m Lv 60 , 29 74 , 40 40 = × = ∆ × = g. Syarat kenyamanan m ik jam km t V Lv 67 , 66 det 3 80 = × = × = a b c d e g 3 = 0 g 2 = 0,74 commit to user h. Pengurangan goncangan m V Lv 16 , 13 360 74 , 80 360 2 2 = × = ∆ × = Diambil Lv terbesar, yaitu = 66,67m m Lv Ev 06 , 800 67 , 66 74 , 800 = × = × ∆ = m Lv X Y 02 , 67 , 66 200 67 , 66 4 1 74 , 200 2 2 = × × × = × × ∆ = Stationing lengkung vertikal PV 2 Sta a = Sta PV 2 – 1 2 Lv = 0+800 – 1 2 66,67 = 0+766,67 m Sta b = Sta PV 2 – 1 4 Lv = 0+800 – 1 4 66,67 = 0+783,33 m Sta c = Sta PV 2 = 0+800 m Sta d = Sta PV 2 + 1 4 Lv = 0+800 + 1 4 66,67 = 0+816,67 m Sta e = Sta PV 2 + 1 2 Lv = 0+800 + 1 2 66,67 = 0+833,33 m Elevasi Lengkung vertikal: Elevasi a = Elevasi PV 2 – ½ Lv x g 2 = 103,47 – ½ 66,67 x 0,74 = 103,223 m commit to user Elevasi b = Elevasi PV 2 – ¼ Lv x g 2 – y = 103,47 – ¼ 66,67 x 0,74 – 0,015 = 103,362 m Elevasi c = Elevasi PV 2 – Ev = 103,47 – 0,06 = 103,41 m Elevasi d = Elevasi PV 2 – ¼ Lv x g 3 – y = 103,47 – ¼ 66,67 x 0 – 0,015 = 103,455 m Elevasi e = Elevasi PV 2 – ½ Lv x g 3 = 103,47 – ½ 66,67 x 0 = 103,470 m

3. PV

3 . Gambar 3.10. Lengkung Vertikal PV 3 20 , 20 , 3 4 = − = − = ∆ g g Perhitungan Lv : a. Syarat keluwesan bentuk m V Lv 48 80 6 , 6 , = × = × = b. Syarat drainase m Lv 8 20 , 40 40 = × = ∆ × = a b c d e g 3 = 0 g 4 = 0,20 commit to user c. Syarat kenyamanan m ik jam km t V Lv 67 , 66 det 3 80 = × = × = d. Pengurangan goncangan m V Lv 56 , 3 360 20 , 80 360 2 2 = × = ∆ × = Diambil Lv terbesar, yaitu = 66,67m m Lv Ev 02 , 800 67 , 66 20 , 800 = × = × ∆ = m Lv X Y 004 , 67 , 66 200 67 , 66 4 1 20 , 200 2 2 = × × × = × × ∆ = Stationing lengkung vertikal PV 3 Sta a = Sta PV 3 – 1 2 Lv = 2+250 – 1 2 66,67 = 2+216,67 m Sta b = Sta PV 3 – 1 4 Lv = 2+250 – 1 4 66,67 = 2+233,33 m Sta c = Sta PV 3 = 2+250 m Sta d = Sta PV 3 + 1 4 Lv = 2+250 + 1 4 66,67 = 2+266,67 m Sta e = Sta PV 3 + 1 2 Lv = 2+250 + 1 2 66,67 = 2+283,33 m commit to user Elevasi Lengkung vertikal: Elevasi a = Elevasi PV 3 + ½Lv x g 3 = 103,47 + ½ 66,67 x 0 = 103,470 m Elevasi b = Elevasi PV 3 + ¼ Lv x g 3 + y = 103,47 + ¼ 66,67 x 0 + 0,004 = 103,474 m Elevasi c = Elevasi PV 3 + Ev = 103,47 + 0,02 = 103,49 m Elevasi d = Elevasi PV 3 + ¼ Lv x g 4 + y = 103,47 + ¼ 66,67 x 0,2 + 0,004 = 103,508 m Elevasi e = Elevasi PV 3 + ½ Lv x g 4 = 103,47 + ½ 66,67 x 0,2 = 103,537 m

4. PV

4 . Gambar 3.11. Lengkung Vertikal PV 4 2 , 2 , 4 5 = − = − = ∆ g g a b c d e g 5 = 0 g 4 = 0,2 commit to user Perhitungan Lv : a. Syarat keluwesan bentuk m V Lv 48 80 6 , 6 , = × = × = b. Syarat drainase m Lv 8 20 , 40 40 = × = ∆ × = c. Syarat kenyamanan m ik jam km t V Lv 67 , 66 det 3 80 = × = × = d. Pengurangan goncangan m V Lv 56 , 3 360 20 , 80 360 2 2 = × = ∆ × = Diambil Lv terbesar, yaitu = 66,67m m Lv Ev 02 , 800 67 , 66 20 , 800 = × = × ∆ = m Lv X Y 004 , 67 , 66 200 67 , 66 4 1 20 , 200 2 2 = × × × = × × ∆ = Stationing lengkung vertikal PV 4 Sta a = Sta PV 4 – 1 2 Lv = 2+ 950 – 1 2 66,67 = 2+916,67 m Sta b = Sta PV 4 – 1 4 Lv = 2+ 950 – 1 4 66,67 = 2+933,33 m commit to user Sta c = Sta PV 4 = 2+ 950 m Sta d = Sta PV 4 + 1 4 Lv = 2+ 950 + 1 4 66,67 = 2+966,67 m Sta e = Sta PV 4 + 1 2 Lv = 2+ 950 + 1 2 66,67 = 2+983,33 m Elevasi Lengkung vertikal: Elevasi a = Elevasi PV 4 – ½ Lv x g 4 = 104,87 – ½ 66,67 x 0,2 = 104,803 m Elevasi b = Elevasi PV 4 – ¼ Lv x g 4 – y = 104,87 – ¼ 66,67 x 0,2 − 0,004 = 104,832 m Elevasi c = Elevasi PV 4 – Ev = 104,87 – 0,02 = 104,850 m Elevasi d = Elevasi PV 4 – ¼ Lv x g 5 – y = 104,87 – ¼ 66,67 x 0 − 0,004 = 104,866 m Elevasi e = Elevasi PV 4 – ½ Lv x g 5 = 104,87 – ½ 66,67 x 0 = 104,870 m commit to user

3.5.4 Tabel elevasi rencana jalan

Tabel 3.4 Elevasi Tanah asli dan rencana jalan Stationing Elev. Tanah asli Elev. Renc. jalan. Stationing Elev. Tanah asli Elev. Renc. jalan. Stationing Elev. Tanah asli Elev. Renc. jalan. 0+000 99,91 99,91 1+250 100,54 103,47 2+500 104,95 103,97 0+050 100,32 99,99 1+300 95,38 103,47 2+550 105,30 104,07 0+100 100,57 100,07 1+350 95,50 103,47 2+600 105,20 104,17 0+150 100,66 100,14 1+400 103,56 103,47 2+650 105,43 104,27 0+200 100,60 100,22 1+450 102,96 103,47 2+700 105,46 104,37 0+250 100,59 100,30 1+500 104,22 103,47 2+750 105,31 104,47 0+300 100,63 100,38 1+550 105,20 103,47 2+800 105,13 104,57 0+350 100,60 100,45 1+600 105,85 103,47 2+850 104,98 104,67 0+400 100,53 100,53 1+650 105,92 103,47 2+900 104,90 104,77 0+450 100,52 100,90 1+700 105,37 103,47 2+950 104,87 104,87 0+500 100,54 101,27 1+750 104,72 103,47 3+000 104,90 104,87 0+550 100,81 101,63 1+800 104,09 103,47 3+050 104,97 104,87 0+600 101,48 102,00 1+850 103,46 103,47 3+100 105,02 104,87 0+650 102,31 102,37 1+900 103,07 103,47 3+150 105,03 104,87 0+700 102,74 102,74 1+950 102,84 103,47 3+200 104,89 104,87 0+750 103,11 103,10 2+000 102,80 103,47 3+250 104,69 104,87 0+800 103,47 103,47 2+050 102,83 103,47 3+300 104,44 104,87 0+850 103,89 103,47 2+100 102,88 103,47 3+350 104,22 104,87 0+900 104,33 103,47 2+150 103,00 103,47 3+400 103,99 104,87 0+950 104,58 103,47 2+200 103,18 103,47 3+450 103,78 104,87 1+000 104,59 103,47 2+250 103,37 103,47 3+500 103,60 104,87 1+050 104,46 103,47 2+300 103,66 103,57 1+100 104,04 103,47 2+350 104,02 103,67 1+150 103,40 103,47 2+400 104,33 103,77 1+200 102,68 103,47 2+450 104,62 103,87 commit to user Tabel 3.5 Hasil Perhitungan Kelandaian Memanjang Titik Stationing Elevasi m Jarak m Kelandaian memanjang 1 2 3 4 5 A 0+000 99,91 400 g 1 = 0,16 PV 1 a 0+366,67 100,477 b 0+383,33 100,515 c 0+400 100,58 d 0+416,67 100,665 400 g 2 = 0,74 e 0+433,33 100,777 PV 2 a 0+766,67 103,223 b 0+783,33 103,362 c 0+800 103,41 d 0+816,67 103,455 1450 g 3 = 0 e 0+833,33 103,470 PV 3 a 2+216,67 103,470 b 2+233,33 103,474 c 2+250 103,49 d 2+266,67 103,508 700 g 4 = 0,2 e 2+283,33 103,537 PV 4 a 2+916,67 104,803 b 2+933,33 104,832 c 2+950 104,850 d 2+966,67 104,866 550 g 5 = 0 e 2+983,33 104,870 B 3+500 104,870 commit to user 81 BAB IV PERENCANAAN TEBAL PERKERASAN

4.1 Data Perencanaan Tebal Perkerasan

a Tebal perkerasan untuk 2 jalur dan 2 arah. b Masa konstruksi n 1 = 1 tahun, angka pertumbuhan lalu lintas i 1 = 2 . c Umur rencana n 2 = 10 tahun, angka pertumbuhan lalu lintas i 2 = 7 . d Jalan yang direncanakan adakah jalan kelas III jalan kolektor. e Curah hujan diperkirakan 120 mm tahun. f Mencari harga CBR yang mewakili. g Susunan lapis perkerasan : 9 Lapisan Permukaan Surface Course = LAPEN Mekanis 9 Lapisan Pondasi Atas Base Course = Batu Pecah CBR 80 9 Lapisan Pondasi Bawah Sub Base Course = SIRTU CBR 50 Tabel 4.1. Data hasil survey lalu lintas survey dilakukan pada hari rabu No JENIS KENDARAAN JUMLAH KENDARAAN Pagi 06 .0 - 07 .0 S iang 13 .0 - 14 .0 Sore 1 7 .00 - 18.0 1 Kendaraan Roda Tiga 5 4 4 13 4 29 2 Sedan, Station Wagon, Jeep 70 64 69 203 68 451 ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ Σ 3 R ⎠ ⎞ ⎜⎜ ⎝ ⎛ 15 R LHR ⎟ ⎟ ⎟ ⎠ ⎞ ⎜ ⎜ ⎜ ⎝ ⎛ Σ sore siang pagi Bersambung