Lampiran 2 RENCANA ANGGARAN BIAYA RAB (1)
Lampiran 2 : RENCANA ANGGARAN BIAYA (RAB)
PROGRAM
: REHABILITASI / PEMELIHARAAN JALAN DAN JEMBATAN
KEGIATAN
: REHABILITASI / PEMELIHARAAN JALAN KABUPATEN TAHUN 2008
SUMBER DANA
: DAK (DANA ALOKASI KHUSUS)
PEKERJAAN
: REHABILITASI / PEMELIHARAAN JALAN PAKET I
TAHUN ANGGARAN
: 2008
HARGA
JUMLAH
NO.
URAIAN PEKERJAAN
VOLUME
SATUAN
( Rp. )
HARGA
( Rp. )
1
2
3
4
5
1 Jalan Moding - Sombang, P = 3,700 Km L = 3,50 M'
- Pengukuran/Uitzet
3.700
Km
Rp.
212,500.00
Rp.
786,250.00
3,237.500
M2
Rp.
37,325.36
Rp.
120,840,843.75
- Lapis Perekat
13,100.000
M2
Rp.
6,121.00
Rp.
80,185,100.00
- HRS
13,100.000
M2
Rp.
53,699.98
Rp.
703,469,734.07
428.000
M3
Rp.
309,200.00
Rp.
132,337,600.00
7.000
M'
Rp.
993,748.78
Rp.
6,956,241.44
- Pemotongan bahu jalan
500.000
M3
Rp.
18,125.00
Rp.
9,062,500.00
- Timbunan dipadatkan
195.000
M3
Rp.
69,366.67
Rp.
13,526,500.00
- Galian Tanah Parit
419.000
M3
Rp.
16,100.00
Rp.
6,745,900.00
Real Cost
Rp.
1,073,910,669.26
PPn 10 %
Rp.
107,391,066.93
Total Cost
Rp.
1,181,301,736.19
Dibulatkan
Rp.
1,181,301,000.00
Rp.
1,181,301,000.00
- Pemel. Kondisi Jalan Dg Lapen
- Pasangan Batu Kali
- Dueker Plat 1,0 m x 1,0 m
T O T A L PAKET I
Negara, 29 Mei 2008
PT. SEKAWAN JAYA UTAMA
H. Agus Sucipto, SH. MBA. MM
Direktur Utama
Lanjutan Lampiran 2
PT. SEKAWAN JAYA UTAMA
TAHUN
ANALISA BIAYA PEKERJAAN
2008
LAPIS PENETRASI MACADAM ( LAPEN )
Uraian
Anggapan
1. Semprot aspal prime coat 0,5 kg/m2
1. Menggunakan tenaga buruh
2. Hamparan agregat pokok 3 - 5 = 25 m2/m3 dan dipadatkan
2. Harga material (agregat pokok, pengunci, penutup aspal) adalah
3. Hamparan agregat pengunci 2 - 3 = 45 m2/m3 dan dipadatkan
harga dilokasi kegiatan
4. Semprotkan aspal 2,5 kg/m2
3. Tebal lapisan penetrasi kurang lebih 5 cm
5. Hamparan agregat pengunci 1- 2 = 90 m2/m3 dan dipadatkan
6. Semprotkan aspal 1,5 kg/m2
7. Taburkan pasir rata-rata 400 m2/m3
PEKERJA
JML
JML
JML
UPAH
BIAYA
JUMLAH
ORANG
HARI
OH
RP./OH
(RP)
(RP)
Mandor
2.00
3.00
6.00
40,000.00
240,000.00
Operator
2.00
3.00
6.00
32,500.00
195,000.00
Sopir
-
-
-
40,000.00
-
Tukang
-
-
-
32,500.00
-
Pekerja
66.00
3.00
198.00
22,500.00
4,455,000.00
JUMLAH I
BAHAN
SATUAN
VOLUME
HARGA
BIAYA
JUMLAH
SATUAN
SATUAN
(RP)
(RP)
Batu Pecah 3 - 5 cm
M3
56.00
70,000.00
3,920,000.00
Batu Pecah 2 - 3 cm
M3
31.00
110,000.00
3,410,000.00
Batu Pecah 1 - 2 cm
M3
15.50
115,000.00
1,782,500.00
Batu Pecah 0,5 - 1 cm
M3
7.50
120,000.00
900,000.00
Pasir Pasang
M3
3.50
90,000.00
315,000.00
Aspal bitumen
Kg
6,258.00
5,500.00
34,419,000.00
Minyak Tanah
Liter
450.00
3,000.00
1,350,000.00
Alat-alat bantu
Set
8.10
60,000.00
486,000.00
JUMLAH II
PERA LATAN
Mesin Gilas 3 Roda 6-8 ton
JAM
JML
UPAH
BIAYA
JUMLAH
ALAT
KERJA
KERJA
RP./JAM
(RP)
(RP)
1.00
15.00
15.00
52,200.00
JUMLAH ( I + II + III )
Rp.
46,582,500.000
JML
783,000.00
JUMLAH I
VOLUME
HARGA SATUAN
4,890,000.00
1,400.00 M2
37,325.36 Per M2
Rp.
783,000.00
52,255,500.00
Lanjutan Lampiran 2
PT. SEKAWAN JAYA UTAMA
TAHUN
ANALISA BIAYA PEKERJAAN
2008
LATASTON (HRS) TEBAL 3 CM
Uraian
Anggapan
1 Wheel loader memuat agr. dan asphalt ke dlm Cold Bin AMP
1 Menggunakan alat berat
2 Agr. Dan aspal dicampur dan dipanaskan dgn AMP utk dimuat
2 Lokasi pekerjaan sepanjang jalan.
langsung ke dalam DT dan diangkut ke dlm pekerjaan
3 Tebal Lapis padat rata-rata 3 cm
3 Campuran panas HRS dihampar dgn Finisher dan dipadatkan
dgn Tandem dan Pneumatic Tire Roler
5 Komposisi campuran : Course Agregat, Fine Agregat, Fraksi Filler
4 Selama pemadatan sekelompok pekerja akan merapikan tepi
hamparan dengan menggunakan alat bantu.
PEKERJA
4 Jam kerja Efektif per hari : 5 jam
dan asphalt
6 Berat jenis bahan padat : 2,20 ton/m3
JML
JML
JML
UPAH
BIAYA
JUMLAH
ORANG
HARI
OH
RP./OH
(RP)
(RP)
Mandor
2.00
1.00
2.00
40,000.00
80,000.00
Operator
5.00
1.00
5.00
32,500.00
162,500.00
Sopir
2.00
1.00
2.00
40,000.00
80,000.00
-
32,500.00
-
12.00
22,500.00
270,000.00
Tukang
-
Pekerja
12.00
1.00
JUMLAH I
BAHAN
SATUAN
VOLUME
HARGA
BIAYA
JUMLAH
SATUAN
SATUAN
(RP)
(RP)
Agregat Kasar
M3
12.30
130,000.00
1,599,000.00
Agregat Halus
M3
2.10
135,000.00
283,500.00
Filler
Kg
5,691.80
2,441.50
13,896,529.70
Aspal bitumen
Kg
5,150.90
5,500.00
28,329,950.00
Alat-alat bantu
Set
1.50
60,000.00
90,000.00
JUMLAH II
PERA LATAN
JAM
JML
UPAH
BIAYA
JUMLAH
ALAT
KERJA
KERJA
RP./JAM
(RP)
(RP)
1.00
5.00
5.0000
250,000.00
1,250,000.00
Asphalt Mixing Plant
1.00
5.00
5.0000
550,000.00
2,750,000.00
Generator Set
1.00
5.00
5.0000
108,500.00
542,500.00
Dump Truck 10 Ton
2.00
5.00
10.0000
85,500.00
855,000.00
Asphalt Finisher
1.00
5.00
5.0000
400,000.00
2,000,000.00
Pneumatic Tire Roller
1.00
5.00
5.0000
250,000.00
1,250,000.00
Mesin Gilas Tandem 8 - 10 Ton
1.00
5.00
5.0000
52,200.00
261,000.00
JUMLAH I
JUMLAH ( I + II + III )
Rp.
44,198,979.700
JML
Whell Loader
VOLUME
HARGA SATUAN
592,500.00
1,000.00 M2
53,699.98 Per M2
Rp.
8,908,500.00
53,699,979.70
Lanjutan Lampiran 2
PT. SEKAWAN JAYA UTAMA
TAHUN
ANALISA BIAYA PEKERJAAN
2008
TACK COAT (LAPIS PEREKAT)
Uraian
Anggapan
1 Permukaan akan dilapisi dibersihkan dari debu dan kotoran
1 Menggunakan alat berat
dengan alat kompresor
2 Lokasi pekerjaan sepanjang jalan.
2 Campuran asphalt cair disemprotkan dengan aspal sprayer
3 Menyemprotkan teak coat ( lapis perekat ) : 0,5 ltr / m2.
keatas permukaan yang akan dilapis
4 Jam kerja Efektif per hari
3 Angkutan campuran aspal menggunakan Dump truk
5 Komposisi campuran : asphalt dan pencair = 4 : 1
6 Berat jenis bahan : asphalt dan pencair
7 Bahan dasar semuanya diterima di lokasi pekerjaan
PEKERJA
Mandor
JML
JML
JML
UPAH
BIAYA
JUMLAH
ORANG
HARI
OH
RP./OH
(RP)
(RP)
1.00
1.00
1.00
40,000.00
40,000.00
Operator
-
-
-
32,500.00
-
Sopir
-
-
-
40,000.00
-
Tukang
-
-
-
32,500.00
-
Pekerja
5.00
1.00
5.00
22,500.00
112,500.00
JUMLAH I
BAHAN
SATUAN
VOLUME
HARGA
BIAYA
JUMLAH
SATUAN
SATUAN
(RP)
(RP)
Minyak Tanah
Liter
480.00
3,000.00
1,440,000.00
Aspal bitumen
Kg
252.00
5,500.00
1,386,000.00
Alat-alat bantu
Set
1.00
60,000.00
60,000.00
JUMLAH II
PERA LATAN
JAM
JML
UPAH
BIAYA
JUMLAH
ALAT
KERJA
KERJA
RP./JAM
(RP)
(RP)
Kompresor
1.00
2.00
1.00
1.00
2.00
1,000.00
2,000.00
1.00
20,000.00
20,000.00
JUMLAH I
JUMLAH ( I + II + III )
Rp.
2,886,000.000
JML
Asphalt Sprayer
VOLUME
HARGA SATUAN
152,500.00
500.00 M2
6,121.00 Per M2
Rp.
22,000.00
3,060,500.00
PROGRAM
: REHABILITASI / PEMELIHARAAN JALAN DAN JEMBATAN
KEGIATAN
: REHABILITASI / PEMELIHARAAN JALAN KABUPATEN TAHUN 2008
SUMBER DANA
: DAK (DANA ALOKASI KHUSUS)
PEKERJAAN
: REHABILITASI / PEMELIHARAAN JALAN PAKET I
TAHUN ANGGARAN
: 2008
HARGA
JUMLAH
NO.
URAIAN PEKERJAAN
VOLUME
SATUAN
( Rp. )
HARGA
( Rp. )
1
2
3
4
5
1 Jalan Moding - Sombang, P = 3,700 Km L = 3,50 M'
- Pengukuran/Uitzet
3.700
Km
Rp.
212,500.00
Rp.
786,250.00
3,237.500
M2
Rp.
37,325.36
Rp.
120,840,843.75
- Lapis Perekat
13,100.000
M2
Rp.
6,121.00
Rp.
80,185,100.00
- HRS
13,100.000
M2
Rp.
53,699.98
Rp.
703,469,734.07
428.000
M3
Rp.
309,200.00
Rp.
132,337,600.00
7.000
M'
Rp.
993,748.78
Rp.
6,956,241.44
- Pemotongan bahu jalan
500.000
M3
Rp.
18,125.00
Rp.
9,062,500.00
- Timbunan dipadatkan
195.000
M3
Rp.
69,366.67
Rp.
13,526,500.00
- Galian Tanah Parit
419.000
M3
Rp.
16,100.00
Rp.
6,745,900.00
Real Cost
Rp.
1,073,910,669.26
PPn 10 %
Rp.
107,391,066.93
Total Cost
Rp.
1,181,301,736.19
Dibulatkan
Rp.
1,181,301,000.00
Rp.
1,181,301,000.00
- Pemel. Kondisi Jalan Dg Lapen
- Pasangan Batu Kali
- Dueker Plat 1,0 m x 1,0 m
T O T A L PAKET I
Negara, 29 Mei 2008
PT. SEKAWAN JAYA UTAMA
H. Agus Sucipto, SH. MBA. MM
Direktur Utama
Lanjutan Lampiran 2
PT. SEKAWAN JAYA UTAMA
TAHUN
ANALISA BIAYA PEKERJAAN
2008
LAPIS PENETRASI MACADAM ( LAPEN )
Uraian
Anggapan
1. Semprot aspal prime coat 0,5 kg/m2
1. Menggunakan tenaga buruh
2. Hamparan agregat pokok 3 - 5 = 25 m2/m3 dan dipadatkan
2. Harga material (agregat pokok, pengunci, penutup aspal) adalah
3. Hamparan agregat pengunci 2 - 3 = 45 m2/m3 dan dipadatkan
harga dilokasi kegiatan
4. Semprotkan aspal 2,5 kg/m2
3. Tebal lapisan penetrasi kurang lebih 5 cm
5. Hamparan agregat pengunci 1- 2 = 90 m2/m3 dan dipadatkan
6. Semprotkan aspal 1,5 kg/m2
7. Taburkan pasir rata-rata 400 m2/m3
PEKERJA
JML
JML
JML
UPAH
BIAYA
JUMLAH
ORANG
HARI
OH
RP./OH
(RP)
(RP)
Mandor
2.00
3.00
6.00
40,000.00
240,000.00
Operator
2.00
3.00
6.00
32,500.00
195,000.00
Sopir
-
-
-
40,000.00
-
Tukang
-
-
-
32,500.00
-
Pekerja
66.00
3.00
198.00
22,500.00
4,455,000.00
JUMLAH I
BAHAN
SATUAN
VOLUME
HARGA
BIAYA
JUMLAH
SATUAN
SATUAN
(RP)
(RP)
Batu Pecah 3 - 5 cm
M3
56.00
70,000.00
3,920,000.00
Batu Pecah 2 - 3 cm
M3
31.00
110,000.00
3,410,000.00
Batu Pecah 1 - 2 cm
M3
15.50
115,000.00
1,782,500.00
Batu Pecah 0,5 - 1 cm
M3
7.50
120,000.00
900,000.00
Pasir Pasang
M3
3.50
90,000.00
315,000.00
Aspal bitumen
Kg
6,258.00
5,500.00
34,419,000.00
Minyak Tanah
Liter
450.00
3,000.00
1,350,000.00
Alat-alat bantu
Set
8.10
60,000.00
486,000.00
JUMLAH II
PERA LATAN
Mesin Gilas 3 Roda 6-8 ton
JAM
JML
UPAH
BIAYA
JUMLAH
ALAT
KERJA
KERJA
RP./JAM
(RP)
(RP)
1.00
15.00
15.00
52,200.00
JUMLAH ( I + II + III )
Rp.
46,582,500.000
JML
783,000.00
JUMLAH I
VOLUME
HARGA SATUAN
4,890,000.00
1,400.00 M2
37,325.36 Per M2
Rp.
783,000.00
52,255,500.00
Lanjutan Lampiran 2
PT. SEKAWAN JAYA UTAMA
TAHUN
ANALISA BIAYA PEKERJAAN
2008
LATASTON (HRS) TEBAL 3 CM
Uraian
Anggapan
1 Wheel loader memuat agr. dan asphalt ke dlm Cold Bin AMP
1 Menggunakan alat berat
2 Agr. Dan aspal dicampur dan dipanaskan dgn AMP utk dimuat
2 Lokasi pekerjaan sepanjang jalan.
langsung ke dalam DT dan diangkut ke dlm pekerjaan
3 Tebal Lapis padat rata-rata 3 cm
3 Campuran panas HRS dihampar dgn Finisher dan dipadatkan
dgn Tandem dan Pneumatic Tire Roler
5 Komposisi campuran : Course Agregat, Fine Agregat, Fraksi Filler
4 Selama pemadatan sekelompok pekerja akan merapikan tepi
hamparan dengan menggunakan alat bantu.
PEKERJA
4 Jam kerja Efektif per hari : 5 jam
dan asphalt
6 Berat jenis bahan padat : 2,20 ton/m3
JML
JML
JML
UPAH
BIAYA
JUMLAH
ORANG
HARI
OH
RP./OH
(RP)
(RP)
Mandor
2.00
1.00
2.00
40,000.00
80,000.00
Operator
5.00
1.00
5.00
32,500.00
162,500.00
Sopir
2.00
1.00
2.00
40,000.00
80,000.00
-
32,500.00
-
12.00
22,500.00
270,000.00
Tukang
-
Pekerja
12.00
1.00
JUMLAH I
BAHAN
SATUAN
VOLUME
HARGA
BIAYA
JUMLAH
SATUAN
SATUAN
(RP)
(RP)
Agregat Kasar
M3
12.30
130,000.00
1,599,000.00
Agregat Halus
M3
2.10
135,000.00
283,500.00
Filler
Kg
5,691.80
2,441.50
13,896,529.70
Aspal bitumen
Kg
5,150.90
5,500.00
28,329,950.00
Alat-alat bantu
Set
1.50
60,000.00
90,000.00
JUMLAH II
PERA LATAN
JAM
JML
UPAH
BIAYA
JUMLAH
ALAT
KERJA
KERJA
RP./JAM
(RP)
(RP)
1.00
5.00
5.0000
250,000.00
1,250,000.00
Asphalt Mixing Plant
1.00
5.00
5.0000
550,000.00
2,750,000.00
Generator Set
1.00
5.00
5.0000
108,500.00
542,500.00
Dump Truck 10 Ton
2.00
5.00
10.0000
85,500.00
855,000.00
Asphalt Finisher
1.00
5.00
5.0000
400,000.00
2,000,000.00
Pneumatic Tire Roller
1.00
5.00
5.0000
250,000.00
1,250,000.00
Mesin Gilas Tandem 8 - 10 Ton
1.00
5.00
5.0000
52,200.00
261,000.00
JUMLAH I
JUMLAH ( I + II + III )
Rp.
44,198,979.700
JML
Whell Loader
VOLUME
HARGA SATUAN
592,500.00
1,000.00 M2
53,699.98 Per M2
Rp.
8,908,500.00
53,699,979.70
Lanjutan Lampiran 2
PT. SEKAWAN JAYA UTAMA
TAHUN
ANALISA BIAYA PEKERJAAN
2008
TACK COAT (LAPIS PEREKAT)
Uraian
Anggapan
1 Permukaan akan dilapisi dibersihkan dari debu dan kotoran
1 Menggunakan alat berat
dengan alat kompresor
2 Lokasi pekerjaan sepanjang jalan.
2 Campuran asphalt cair disemprotkan dengan aspal sprayer
3 Menyemprotkan teak coat ( lapis perekat ) : 0,5 ltr / m2.
keatas permukaan yang akan dilapis
4 Jam kerja Efektif per hari
3 Angkutan campuran aspal menggunakan Dump truk
5 Komposisi campuran : asphalt dan pencair = 4 : 1
6 Berat jenis bahan : asphalt dan pencair
7 Bahan dasar semuanya diterima di lokasi pekerjaan
PEKERJA
Mandor
JML
JML
JML
UPAH
BIAYA
JUMLAH
ORANG
HARI
OH
RP./OH
(RP)
(RP)
1.00
1.00
1.00
40,000.00
40,000.00
Operator
-
-
-
32,500.00
-
Sopir
-
-
-
40,000.00
-
Tukang
-
-
-
32,500.00
-
Pekerja
5.00
1.00
5.00
22,500.00
112,500.00
JUMLAH I
BAHAN
SATUAN
VOLUME
HARGA
BIAYA
JUMLAH
SATUAN
SATUAN
(RP)
(RP)
Minyak Tanah
Liter
480.00
3,000.00
1,440,000.00
Aspal bitumen
Kg
252.00
5,500.00
1,386,000.00
Alat-alat bantu
Set
1.00
60,000.00
60,000.00
JUMLAH II
PERA LATAN
JAM
JML
UPAH
BIAYA
JUMLAH
ALAT
KERJA
KERJA
RP./JAM
(RP)
(RP)
Kompresor
1.00
2.00
1.00
1.00
2.00
1,000.00
2,000.00
1.00
20,000.00
20,000.00
JUMLAH I
JUMLAH ( I + II + III )
Rp.
2,886,000.000
JML
Asphalt Sprayer
VOLUME
HARGA SATUAN
152,500.00
500.00 M2
6,121.00 Per M2
Rp.
22,000.00
3,060,500.00