Inspector’s Responsibilities Regarding Coating Materials
9.5.6 Inspector’s Responsibilities Regarding Coating Materials
Make sure that the coatings and allowable thinners used are those specified. Know where the coatings are stored on site. Ensure storage conditions are in accordance with specifications and the manufacturer’s latest instructions. Check containers for any sign of damage.
Know how the coatings are to be mixed, thinned, and agitated, and then ensure that this happens. Be sure all pigments are worked into the liquid coating. If the coating is a two-pack or three-pack product, be sure the correct components are stirred properly, combined as specified and then mixed thor- oughly. Make sure the workers observe manufacturer’s recommended pot life and induction or sweat-in times. Know the vol- ume of solids, wet-film and dry-film thick- nesses specified and allowable tolerances, dry, and re-coat times, and times for proper cure.
Figure 9.6 Coating Materials in Packaging
9.5.6.1 Sampling Coatings
The specification may require the contractor or inspector to take samples of the coatings on the project, spelling out the sampling pro- cedure, number of samples taken, labeling procedures, and storage requirements, etc.
The sampler should use only clean contain- ers when taking partial samples to avoid contaminating the sample. Samples may be partial 0.5 pint to 1 qt. (250 mLto 1 L) or unopened containers, 1 to 5 gals (5 to 20 L). The inspector may be required to visit the manufacturer’s plant to take samples of the coating.
Inspector’s Responsibilities Regarding Sampling Coatings
Alternatively, the coating specification may require the inspector to take samples of the coating materials on site. The inspector should follow the specification carefully, as well as the following:
• Select coatings to be sampled at random • Ensure coatings are thoroughly mixed • Place the amount specified in the correct
container • Label the sample container with the fol-
lowing data:
— Product name and number
9-14 Coating Project Specification
— Color — Batch number — Date the sample was taken — Inspector’s name
The inspector should ensure that each sam- ple container is correctly sealed and is stored under safe and appropriate conditions. To avoid sampling error, some clients prefer that an unopened coating container be sent to the testing lab, where the material can be mixed and sampled under more controlled
Figure 9.7 Proper Application of the Specified
conditions.
Coating is Critical to it’s Performance and life Cycle
9.5.7 Inspector’s Responsibilities Regarding Workmanship
9.5.8 Inspector’s Responsibilities
Inspectors must understand the nature of the
Regarding Application
work to be done. Have a copy of the manu- Ensure that the coating application is done facturer’s latest instructions and understand
as specified (in a proper “workmanlike” them thoroughly. At the pre-job conference,
manner) and is free from defects. Know ensure that workmanship performance
exactly what thickness tolerances are expectations are clearly understood by all
allowed. A good specification states a mini- participants.
mum and a maximum DFT for each coat and for the total system: for example, 4–6 mils
Observe the workers and report any unac- (100–150 µm) per coat and 12–18 mils ceptable work to the supervisor, the owner’s (300–450 µm) for the total system. If this is representative, or to the contractor for cor- not the case, then insist in the pre-job con- rection ( Figure 9.7 ). Stay safe. You are ference that clear, practical DFT standards responsible for your own safety and for per-
be established, understood, and agreed upon sonally following all safety requirements
by all parties.
established for the job. Report any question- able conditions or practices to the safety
It is important to understand that the inspec- engineer immediately.
tor’s responsibility is to ensure the specified DFT range is achieved ( Figure 9.8 ). It is a disservice to both the client and the contrac- tor if an inspector insists on an extra topcoat just to make sure that any thin spots or defects possibly missed in inspection are covered.
If the contractor fails to meet the specifica- tions to any substantive degree, and the inspector has made a reasonable effort to gain compliance, then it is important that
Coating Project Specification 9-15
this information is brought to the attention of
9.5.10 Inspector’s Responsibilities
the supervisor or the owner’s representative
Regarding Coating Repair and
for determination of appropriate remedial
Remedial Work
actions. By making a clear, accurate, and The procedure for coating repair ( Figure objective report and recommendation, the
9.9 ) should be addressed in the specification inspector may have an important bearing on
and discussed in the pre-job conference. the decisions made.
• Ensure the areas to be repaired are clearly
In extreme cases, an owner could cancel the
identified and the coated surface properly prepared (e.g., feather edged by sanding)
contract, seek legal redress, or bring various
as specified
influences to bear to gain better cooperation. In some cases, it may be more economical to • Monitor the number of repair coats
applied, observe recoat times, and check
waive compliance with the specifications,
WFT and DFT as specified
finish the work, and accept the inevitable
• Document the work
lower coating performance. Such a judg- ment, however, must be made only by the designated supervisor or owner’s representa- tive, not by the coating inspector.
Figure 9.9 Runs and Sags