PEKERJAAN PENDAHULUAN PENGADAAN TIANG PANCANG PEKERJAAN PEMANCANGAN PEKERJAAN BETON

3 PEMBANGUNAN DERMAGA HARGA SATUAN JUMLAH HARGA Rp. Rp. 1 3 4 5 6

I. PEKERJAAN PENDAHULUAN

1 Pek. Pengukuran 1.00 ls 2,000,000.00 2,000,000.00 2 Mobilisasi dan Demobilisasi Alat 1.00 ls 346,500,000.00 346,500,000.00 3 Pembuatan Direksi Keet + Kelengkapan 30.00 m2 5,540,678.70 166,220,361.00 4 Pembuatan Gudang + Bedeng Kerja 20.00 m2 1,218,886.10 24,377,722.00 5 Listrik Kerja 1.00 ls 2,500,000.00 2,500,000.00 6 Administrasi dan Dokumentasi 1.00 ls 3,500,000.00 3,500,000.00 7 Papan Nama Proyek digital printing lapis 1.00 bh 300,000.00 300,000.00 tripleks 6 mm + tiang kayu 8 Pejaga Malam 1.00 Ls 2,500,000.00 2,500,000.00 Sub Jumlah I. ................................................................................................. 547,898,083.00

II. PENGADAAN TIANG PANCANG

1 Pengadaan tiang pancang dia. 40 cm, 26.00 bh 6,892,335.61 179,200,725.95 panjang 9 meter tiang bawah 2 Pengadaan tiang pancang dia. 40 cm, 52.00 bh 6,892,335.61 358,401,451.91 panjang 9 meter tiang atas Sub Jumlah II. ................................................................................................ 537,602,177.86

III. PEKERJAAN PEMANCANGAN

1 Handling Tiang Pancang ke Titik Pancang 702.00 m 123,481.99 86,684,357.69 2 Pemancangan Tiang 624.00 m 518,312.17 323,426,793.97 3 Penyambungan Tiang 52.00 bh 530,052.50 27,562,730.00 4 Memotong Pangkal Tiang 26.00 bh 549,650.00 14,290,900.00 Sub Jumlah III. ............................................................................................... 451,964,781.67

IV. PEKERJAAN BETON

1 Beton pengisi tiang pancang 1.19 m3 7,166,700.68 8,528,373.81 2 Pile Caps - 80x80x70 11.65 m3 5,986,433.46 69,741,949.82 3 Balok 4070 - Memanjang 27.72 m3 6,134,185.66 170,039,626.48 4 Balok 4070 - Melintang 16.02 m3 6,134,185.66 98,245,117.52 5 Plat Lantai, tebal rata-rata 25 Cm 51.38 m3 6,545,455.15 336,305,485.80 6 Balok tepi lisplank 2560 17.33 m3 6,182,147.02 107,105,697.19 7 Balok fender 8.84 m3 6,134,185.66 54,226,201.23 8 Pek. Kanstin Beton K. 300 1.44 m3 5,591,068.91 8,051,139.23 9 Bollard beton 7.00 Bh 1,068,256.84 7,477,797.86 10 Pek. Besi Stek Poer 742.00 kg 23,047.26 17,101,066.18 11 Pek. Tes Kubus Beton 30.00 bh 150,000.00 4,500,000.00 12 Pengecatan Kanstin 21.32 m2 37,434.70 798,107.80 Sub Jumlah IV. ............................................................................................... 882,120,562.92 2 VOLUME KETERANGAN NO. SAT. HARGA SATUAN JUMLAH HARGA Rp. Rp. 1 3 4 5 6 2 VOLUME KETERANGAN NO. SAT.

V. PEKERJAAN FASILITAS DERMAGA FINISHING