V. PEKERJAAN LANTAI
1 Pas.Lantai Keramik 40 x 40 warna
m
2
31.67 208,940.84
6,617,156.40 2
Dinding Keramik 20 x 20 warna m
2
10.45 187,234.91
1,956,604.81 3
Pas.Rabat Beton Tumbuk m
3
18.52 924,471.95
17,124,687.28
Sub Jumlah V…………………………………………………………………………………….. 25,698,448.50
VI. PEKERJAAN KUSEN, ATAP, PLAFOND
1 Pas.Woodplank Motif Urat Kayu 2x 1.8 x 20 cm
m
1
36.40 66,986.05
2,438,292.22 2
Pas. Rangka Plafond Besi Hollow m
2
50.41 98,762.10
4,978,597.46 3
Pas. Plafond Gypsum 9 mm m
2
50.41 61,646.61
3,107,605.61 4
Pas. Lis Plafond Gypsum m
1
40.00 18,991.00
759,640.00 5
Pek.Kuda-Kuda Baja ringan m
2
56.69 128,610.97
7,290,956.08 6
Pek.Atap Spandek m
2
56.69 74,856.70
4,243,626.32 7
Pek.Nok Zincalum m
1
22.00 63,944.26
1,406,773.72 8
Pas.Baut Moor, Angker, Beugel Ls
1.00 500,000.00
500,000.00
Sub Jumlah VI…………………………………………………………………………………….. 24,725,491.41
VII. PEKERJAAN KUSEN DAN PENGUNCI
1 Pek.Kusen Pintu Jendela Aluminium
m
1
70.56 107,764.64
7,603,873.07 2
Pek. Pintu dan Jendala Kaca Rangka Aluminium m
2
7.40 439,401.25
3,251,569.25 3
Pek. Ventilasi Profil bh
6.00 250,000.00
1,500,000.00 4
Pas. Roster bh
20.00 35,000.00
700,000.00 5
Pekerjaan Teralis Besi m
2
2.16 750,000.00
1,620,000.00 6
Pas.Grendel Tanam Jendela Bh
4.00 45,515.00
182,060.00 7
Hak Angin Bh
8.00 22,081.40
176,651.20 8
Pas.Engsel Jendela Bh
8.00 30,470.20
243,761.60 9
Pas.Kunci Pintu 2 Kali Putar Bh
2.00 107,366.55
214,733.10 10
Pas.Engsel Pintu Psg
12.00 27,811.40
333,736.80
Sub Jumlah VII…………………………………………………………………………………….. 15,826,385.02
VIII. PEKERJAAN PENGECATAN
1 Pekerjaan Acian
m
2
163.06 17,943.37
2,925,845.17 2
Pekerjaan Cat Tembok m
2
163.06 37,434.70
6,104,102.18 3
Pekerjaan Cat Plafond m
2
50.41 37,434.70
1,887,083.23
Sub Jumlah VIII…………………………………………………………………………………….. 10,917,030.58
IX. PEKERJAAN INSTALASI LISTRIK
1 Instalasi Listrik
Ttk 4.00
198,824.00 795,296.00
2 Pasangan Lampu TL 1 x 20 Wtt
Ttk 4.00
170,000.00 680,000.00
3 Pasangan Saklar Ganda Putih
Bh 1.00
115,080.00 115,080.00
4 Pasangan Saklar Tunggal Putih
Bh 2.00
57,540.00 115,080.00
5 Pasangan Stop Kontak Putih
Bh 1.00
57,540.00 57,540.00
6 Pasangan Panel Penerangan
Ls 1.00
2,500,000.00 2,500,000.00
7 Pasangan Sekring Box
Ls 1.00
120,000.00 120,000.00
Sub Jumlah IX …………………………………………………………………………………….. 4,382,996.00
X. PEKERJAAN SANITASI
1 Pasangan Pipa PVC Diameter 12
m1 8.00
34,547.60 276,380.80
2 Pasangan Pipa PVC Diameter 34
m1 4.00
34,547.60 138,190.40
3 Pasangan Kran air 12
Bh 6.00
34,547.60 207,285.60
Sub Jumlah X…………………………………………………………………………………….. 414,571.20
XI. PEKERJAAN AKHIR
1 Pembersihan Akhir
Ls 1.00
550,000.00 550,000.00
Sub Jumlah XI…………………………………………………………………………………….. 550,000.00
JUMLAH BIAYA PEMBANGUNAN MUSHOLLAH
138,276,000.51
4 PEMBANGUNAN MESS PENGINAPAN NELAYAN
HARGA SATUAN JUMLAH HARGA Rp.
Rp.
1 3
4 5
6
I. PEKERJAAN PERSIAPAN
1 Pengukuran dan Pemasangan Bowplank
m
2
1.00 700,000.00
700,000.00 2
Administrasi dan Pelaporan Ls
1.00 500,000.00
500,000.00
Sub Jumlah I……………………………………………………………………………………… 1,200,000.00
II. PEKERJAAN TANAH