commit to user Tugas A khir Perencanaan Struktur Gedung Factory Outlet 2 Lantai Bab 7 Perencanaan Portal 25 200 3 D 16 Ø8-50 3 D 16 25 200 3 D 16 Ø8 -50 3 D 16 Tul. Tumpuan Tul. Lapangan Potongan balok ring balk

7.7. Penulangan Balok Portal

7.7.1. Perhitungan Tulangan Lentur Balok Portal Memanjang

Data perencanaan : h = 400 mm b = 300 mm p = 40 mm fy = 320 Mpa f’c = 25 MPa Ø t = 19 mm Ø s = 10 mm d = h - p - Ø s - ½.Ø t = 400 – 40 – 10 - ½.19 = 340,5 mm ρb = ⎟⎟ ⎠ ⎞ ⎜⎜ ⎝ ⎛ + fy 600 600 fy c. β 0,85.f = ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ + 320 600 600 85 , 320 25 . 85 , = 0,036 ρ max = 0,75 . ρb commit to user Tugas A khir Perencanaan Struktur Gedung Factory Outlet 2 Lantai Bab 7 Perencanaan Portal = 0,75 . 0,036 = 0,027 ρ min = 0043 , 320 4 , 1 4 , 1 = = fy Daerah Tumpuan Dari Perhitungan SAP 2000 diperoleh momen terbesar pada batang nomor 173 : Mu = 3761,02 kgm = 3,761 × 10 7 Nmm Mn = φ Mu = 8 , 10 761 , 3 7 × = 4,70125 × 10 7 Nmm Rn = 35 , 1 340,5 300 10 4,70125 d . b Mn 2 7 2 = × × = m = 05 , 15 25 0,85 320 c 0,85.f fy = × = ρ = ⎟⎟ ⎠ ⎞ ⎜⎜ ⎝ ⎛ − − fy 2.m.Rn 1 1 m 1 = ⎟⎟ ⎠ ⎞ ⎜⎜ ⎝ ⎛ × × − − 320 35 , 1 05 , 15 2 1 1 05 , 15 1 = 0,0043 ρ = ρ min ρ ρ max → dipakai tulangan tunggal Digunakan ρ min = 0,0043 As perlu = ρ. b . d = 0,0043× 300 × 340,5 = 439,245 mm 2 Digunakan tulangan D 19 n = 528 , 283 245 , 439 19 . 4 1 perlu As 2 = π = 1,55 ≈ 2 tulangan commit to user Tugas A khir Perencanaan Struktur Gedung Factory Outlet 2 Lantai Bab 7 Perencanaan Portal As’ = 2 19 . 4 1 π = 283,528 mm As ada = 2 × 283,528 = 567,05 mm 2 As’ As………………….aman Ok Jadi dipakai tulangan 2 D 19 Daerah Lapangan Dari Perhitungan SAP 2000 diperoleh momen terbesar pada batang nomor 173 : Mu = 2356,29 kgm = 2,356 × 10 7 Nmm Mn = φ Mu = 8 , 10 356 , 2 7 × = 2,945 × 10 7 Nmm Rn = 846 , 340,5 300 10 2,945 d . b Mn 2 7 2 = × × = m = 05 , 15 25 0,85 320 c 0,85.f fy = × = ρ = ⎟⎟ ⎠ ⎞ ⎜⎜ ⎝ ⎛ − − fy 2.m.Rn 1 1 m 1 = ⎟⎟ ⎠ ⎞ ⎜⎜ ⎝ ⎛ × × − − 320 846 , 05 , 15 2 1 1 05 , 15 1 = 0,0026 ρ ρ min ρ ρ max → dipakai tulangan tunggal Digunakan ρ min = 0,0043 As perlu = ρ. b . d = 0,0043 × 300 × 340,5 = 439,245 mm 2 Digunakan tulangan D 19 n = 385 , 283 245 , 439 19 . 4 1 perlu As 2 = π = 1,55 ≈ 2 tulangan commit to user Tugas A khir Perencanaan Struktur Gedung Factory Outlet 2 Lantai Bab 7 Perencanaan Portal As’ = 2 19 . 4 1 π = 283,528 mm As ada = 2 × 283,385 = 567,05 mm 2 As’ As………………….aman Ok Jadi dipakai tulangan 2 D 19 7.7.2. Perhitungan Tulangan Geser Portal Memanjang Dari Perhitungan SAP 2000 diperoleh momen terbesar pada batang nomor 173: Vu = 6138,35 kg = 61383,5 N f’c = 25 Mpa fy = 320 Mpa d = 340,5 Vc = 1 6 . c f .b .d = 1 6 . 25 .300.340,5 = 85125 N φ Vc = 0,75 .85125 = 63843,75 N ½ Ø Vc = 0,5 . 63843,75 = 31921,875 N 3 φ Vc = 3 . 63843,75 = 191531,25 N Syarat tulangan geser : ½ Ø Vc Vu Ø Vc : 31921,875 N 61383,5 N 63843,75 N Jadi diperlukan tulangan geser Ø Vs = Vu – ½ Ø Vc = 61383,5 - 31921,878 = 29461,622 N Vs perlu = 75 , 29461,622 75 , = Vs φ = 39282,163 N Av = 2 . ¼ π 8 2 = 100,48 mm 2 S = 71 , 278 39282,163 5 , 340 . 320 . 4 , 100 perlu Vs d . fy . Av = = mm commit to user Tugas A khir Perencanaan Struktur Gedung Factory Outlet 2 Lantai Bab 7 Perencanaan Portal 300 2 D19 Ø8 -150 2 D19 300 2 D19 Ø8 -150 2 D19 Tul. Tumpuan Tul. Lapangan 40 40 S max = d2 = 2 5 , 340 = 175,25 mm Jadi dipakai sengkang dengan tulangan Ø 8 – 150 mm Potongan balok portal memanjang

7.7.3. Perhitungan Tulangan Lentur Balok Portal Melintang