Hitungan Tulangan Lentur Sloof Memanjang

commit to user Tugas A khir Perencanaan Struktur Gedung Factory Outlet 2 Lantai Bab 7 Perencanaan Portal 300 200 3 D16 Ø8-100 2 D16 300 200 2 D16 Ø8-100 2 D16 Tul. Tumpuan Tul. Lapangan Potongan tulangan Sloof

7.9.3. Hitungan Tulangan Lentur Sloof Memanjang

Data perencanaan : h = 300 mm b = 200 mm p = 40 mm fy = 320 Mpa f’c = 25 MPa Ø t = 16 mm Ø s = 8 mm d = h - p - Ø s - ½.Ø t = 300 – 40 – 8 - ½.16 = 244 mm ρb = ⎟⎟ ⎠ ⎞ ⎜⎜ ⎝ ⎛ + fy 600 600 fy c. β 0,85.f = ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ + 320 600 600 85 , 320 25 . 85 , = 0,036 ρ max = 0,75 . ρb = 0,75 . 0,036 = 0,027 commit to user Tugas A khir Perencanaan Struktur Gedung Factory Outlet 2 Lantai Bab 7 Perencanaan Portal ρ min = 0043 , 320 4 , 1 4 , 1 = = fy Daerah Tumpuan Dari Perhitungan SAP 2000 diperoleh momen terbesar pada batang nomor 140. Mu = 1612,15 kgm = 1,61215 × 10 7 Nmm Mn = φ Mu = 8 , 10 61215 , 1 7 × = 2,015 × 10 7 Nmm Rn = 69 , 1 244 200 10 2,015 d . b Mn 2 7 2 = × × = m = 05 , 15 25 0,85 320 c 0,85.f fy = × = ρ = ⎟⎟ ⎠ ⎞ ⎜⎜ ⎝ ⎛ − − fy 2.m.Rn 1 1 m 1 = ⎟⎟ ⎠ ⎞ ⎜⎜ ⎝ ⎛ × × − − 320 69 , 1 05 , 15 2 1 1 05 , 15 1 = 0,0055 ρ ρ min ρ ρ max → dipakai tulangan tunggal Digunakan ρ = 0,0055 As perlu = ρ. b . d = 0,0055 × 200 × 244 = 268,4 mm 2 Digunakan tulangan D 16 n = 96 , 200 4 , 268 16 . 4 1 perlu As 2 = π = 1,33 ≈ 2 tulangan As’ = 2 16 . 4 1 π = 2 16 . 14 , 3 . 4 1 = 200,96 mm As ada = 2 × 200,96 = 401,92 mm 2 commit to user Tugas A khir Perencanaan Struktur Gedung Factory Outlet 2 Lantai Bab 7 Perencanaan Portal As’ As………………….aman Ok Jadi dipakai tulangan 2 D 16 Daerah Lapangan Dari Perhitungan SAP 2000 diperoleh momen terbesar pada batang nomor 140. Mu = 796,45 kgm = 0,79645 × 10 7 Nmm Mn = φ Mu = 8 , 10 79645 , 7 × = 0,996 × 10 7 Nmm Rn = 83 , 244 200 10 0,996 d . b Mn 2 7 2 = × × = m = 05 , 15 25 0,85 320 c 0,85.f fy = × = ρ = ⎟⎟ ⎠ ⎞ ⎜⎜ ⎝ ⎛ − − fy 2.m.Rn 1 1 m 1 = ⎟⎟ ⎠ ⎞ ⎜⎜ ⎝ ⎛ × × − − 320 83 , 05 , 15 2 1 1 05 , 15 1 = 0,0026 ρ ρ min ρ ρ max → dipakai tulangan tunggal Digunakan ρ min = 0,0043 As perlu = ρ. b . d = 0,0043 × 200 × 244 = 209,84 mm 2 Digunakan tulangan D 16 n = 96 , 200 84 , 209 16 . 4 1 perlu As 2 = π = 1,04 ≈ 2 tulangan As’ = 2 16 . 4 1 π = 2 16 . 14 , 3 . 4 1 = 200,96 As ada = 2× 200,96 = 401,92 mm 2 commit to user Tugas A khir Perencanaan Struktur Gedung Factory Outlet 2 Lantai Bab 7 Perencanaan Portal 300 200 2 D16 Ø8-200 2 D16 300 200 2 D16 Ø8-200 2 D16 Tul. Tumpuan Tul. Lapangan As’ As………………….aman Ok Jadi dipakai tulangan 2 D 16 7.9.4 Perhitungan Tulangan Geser Sloof Dari Perhitungan SAP 2000 diperoleh momen terbesar pada batang nomor 147: Vu = 2508,03 kg = 25080,3 N Vc = 1 6 . c f .b .d = 1 6 . 25 .200.244 = 40666,67 N φ Vc = 0,75 . 40666,67 = 30500 N ½ Ø Vc = 0.5 . 30500 = 15250 N 3 φ Vc = 3 . 30500 = 91500 N Syarat tulangan geser : ØVc Vu 3 Ø Vc : 30500 N 25080,3 N 91500 N Tidak diperlukan tulangan geser . Jadi dipakai tulangan geser minimum dengan sengkang tulangan Ø 8 – 200 mm Potongan tulangan Sloof memanjang commit to user Perencanaan Struktur Gedung Factory Outlet 2 Lantai Bab 8 Perencanaan Pondasi 186

BAB 8 PERENCANAAN

PONDASI

8.1. Data Perencanaan

Gambar 8.1. Perencanaan Pondasi Dari perhitungan SAP 2000 pada Frame 84 diperoleh : - Pu = 51461 kgm - Mu = 824,62 kgm 20 30 Tanah Ur ug Pasir t = 5 cm lant ai kerj a t = 10 cm 190 190 40 40 200 75 75