Hitungan Tulangan Lentur Sloof Melintang

commit to user Tugas A khir Perencanaan Struktur Gedung Factory Outlet 2 Lantai Bab 7 Perencanaan Portal 400 400 4 D16 Ø8-200 5 D16 5 D16 Penulangan Kolom

7.9. Penulangan Sloof

7.9.1. Hitungan Tulangan Lentur Sloof Melintang

Data perencanaan : h = 300 mm b = 200 mm p = 40 mm fy = 320 Mpa f’c = 25 MPa Ø t = 16 mm Ø s = 8 mm d = h - p - Ø s - ½.Ø t = 300 – 40 – 8 - ½.16 = 244 mm ρb = ⎟⎟ ⎠ ⎞ ⎜⎜ ⎝ ⎛ + fy 600 600 fy c. β 0,85.f = ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ + 320 600 600 85 , 320 25 . 85 , = 0,036 ρ max = 0,75 . ρb = 0,75 . 0,036 commit to user Tugas A khir Perencanaan Struktur Gedung Factory Outlet 2 Lantai Bab 7 Perencanaan Portal = 0,027 ρ min = 0043 , 320 4 , 1 4 , 1 = = fy Daerah Tumpuan Dari Perhitungan SAP 2000 diperoleh momen terbesar pada batang nomor 220. Mu = 2897,29 kgm = 2,89729 × 10 7 Nmm Mn = φ Mu = 8 , 10 89729 , 2 7 × = 3,6216 × 10 7 Nmm Rn = 04 , 3 244 200 10 3,6216 d . b Mn 2 7 2 = × × = m = 05 , 15 25 0,85 320 c 0,85.f fy = × = ρ = ⎟⎟ ⎠ ⎞ ⎜⎜ ⎝ ⎛ − − fy 2.m.Rn 1 1 m 1 = ⎟⎟ ⎠ ⎞ ⎜⎜ ⎝ ⎛ × × − − 320 04 , 3 05 , 15 2 1 1 05 , 15 1 = 0,01 ρ ρ min ρ ρ max → dipakai tulangan tunggal Digunakan ρ = 0,01 As perlu = ρ. b . d = 0,01 × 200 × 244 = 488 mm 2 Digunakan tulangan D 16 n = 96 , 200 488 16 . 4 1 perlu As 2 = π = 2,42 ≈ 3 tulangan As’ = 2 16 . 4 1 π = 2 16 . 14 , 3 . 4 1 = 200,96 mm commit to user Tugas A khir Perencanaan Struktur Gedung Factory Outlet 2 Lantai Bab 7 Perencanaan Portal As ada = 3 × 200,96 = 602,88 mm 2 As’ As………………….aman Ok Jadi dipakai tulangan 3 D 16 Daerah Lapangan Dari Perhitungan SAP 2000 diperoleh momen terbesar pada batang nomor 220. Mu = 1462,86 kgm = 1,46286 × 10 7 Nmm Mn = φ Mu = 8 , 10 46286 , 1 7 × = 1,8285 × 10 7 Nmm Rn = 53 , 1 244 200 10 1,8285 d . b Mn 2 7 2 = × × = m = 05 , 15 25 0,85 320 c 0,85.f fy = × = ρ = ⎟⎟ ⎠ ⎞ ⎜⎜ ⎝ ⎛ − − fy 2.m.Rn 1 1 m 1 = ⎟⎟ ⎠ ⎞ ⎜⎜ ⎝ ⎛ × × − − 320 53 , 1 05 , 15 2 1 1 05 , 15 1 = 0,0049 ρ ρ min ρ ρ max → dipakai tulangan tunggal Digunakan ρ = 0,0049 As perlu = ρ. b . d = 0,0049 × 200 × 244 = 239,12 mm 2 Digunakan tulangan D 16 n = 96 , 200 12 , 239 16 . 4 1 perlu As 2 = π = 1,18 ≈ 2 tulangan As’ = 2 16 . 4 1 π = 2 16 . 14 , 3 . 4 1 = 200,96 commit to user Tugas A khir Perencanaan Struktur Gedung Factory Outlet 2 Lantai Bab 7 Perencanaan Portal As ada = 2 × 200,96 = 401,92 mm 2 As’ As………………….aman Ok Jadi dipakai tulangan 2 D 16 7.9.2. Perhitungan Tulangan Geser Sloof Dari Perhitungan SAP 2000 diperoleh momen terbesar pada batang nomor 220: Vu = 3375,32 kg = 33753,2 N Vc = 1 6 . c f .b .d = 1 6 . 25 .200.244 = 40666,67 N φ Vc = 0,75 . 40666,67 = 30500 N ½ Ø Vc = 0.5 . 30500 = 15250 N 3 φ Vc = 3 . 30500 = 91500 N Syarat tulangan geser : Ø Vc Vu 3 Ø Vc : 30500 N 33753,2 N 91500 N Jadi diperlukan tulangan geser Ø Vs = Vu – Ø Vc = 33753,2 - 30500 = 3253,2 N Vs perlu = 75 , 3253,2 75 , = Vs φ = 4337,6 N Av = 2 . ¼ π 8 2 = 2 . ¼ . 3,14 . 64 = 100,48 mm 2 S = 535 , 1356 4337,6 244 . 240 . 48 , 100 perlu Vs d . fy . Av = = mm S max = d2 = 2 244 = 122 mm Jadi dipakai sengkang dengan tulangan Ø 8 – 100 mm commit to user Tugas A khir Perencanaan Struktur Gedung Factory Outlet 2 Lantai Bab 7 Perencanaan Portal 300 200 3 D16 Ø8-100 2 D16 300 200 2 D16 Ø8-100 2 D16 Tul. Tumpuan Tul. Lapangan Potongan tulangan Sloof

7.9.3. Hitungan Tulangan Lentur Sloof Memanjang