Penulangan Daerah Tumpuan Daerah Tumpuan

commit to user 215 Tugas Akhir Perencanaan Struktur Mall 3 Lantai RAB BAB 7 Portal Untuk perhitungan tulangan lentur balok portal, diambil pada bentang dengan momen terbesar dari perhitungan SAP 2000. Data perencanaan: b = 350 mm h = 600 mm fy = 320 MPa fys = 240 MPa f’c = 25 MPa Ø tulangan = 25 mm Ø sengkang = 10 mm Tebal selimut s = 40 mm d = h – s - Ø sengkang – ½ Ø tul.utama = 600 – 40 – 10 – 1 2 . 25 = 537,5 mm b = fy 600 600 fy c. β 0,85.f = 320 600 600 320 0,85 25 0,85 = 0,037 max = 0,75 . b = 0,75 . 0,037 = 0,028 min = 0044 , 320 4 , 1 fy 1,4 m = 06 , 15 25 0,85 320 c 0,85.f fy

a. Penulangan Daerah Tumpuan

Dari Perhitungan SAP 2000 diperoleh momen terbesar pada Portal batang 386 Mu = 40135,1 kgm = 40,14 ×10 7 Nmm commit to user 216 Tugas Akhir Perencanaan Struktur Mall 3 Lantai RAB BAB 7 Portal Mn = 8 , 10 40,14 7 Mu = 50,175 ×10 7 Nmm Rn = 2 7 2 5 , 537 350 10 175 , 50 .d b Mn 4,96 Nmm 2 = fy 2.m.Rn 1 1 m 1 = 320 96 , 4 06 , 15 2 1 1 06 , 15 1 = 0,018 min max dipakai tulangan tunggal Digunakan ada = 0,018 As perlu = ada . b. d = 0,018 × 350 × 537,5 = 3386,25 mm 2 n = 2 25 4 1 perlu As = 63 , 490 3386,25 6,9 ~ 8 tulangan As’ = 8 × 490,63 = 3925,04 3386,25 mm 2 As’ As………………….aman Ok a = b c f 85 , fy . ada As = 88 , 168 350 25 85 , 320 . 3925,04 S = 1 - n sengkang 2 - tulangan n - 2p - b = 1 8 10 . 2 - 25 8. - 40 . 2 - 35 = 7,14 25 mm dipakai tulangan dua lapis Di pakai d d1 = 537,5 mm d2 = d1 – s – 2 x ½ Ø = 537,5 – 30 – 2 x ½.25 commit to user 217 Tugas Akhir Perencanaan Struktur Mall 3 Lantai RAB BAB 7 Portal = 482,5 mm d x 8 = d1 x 5 + d2 x 3 d 8 3 x 482,5 5 x 537,5 = 516,88 mm Mn ada = As ada . fy d – a2 = 3925,04 . 320 516,88 – 168,882 = 54,32 .10 7 Nmm Mn ada Mn 54,32 .10 7 Nmm 50,431 ×10 7 Nmm Aman.. Jadi dipakai tulangan 8 D 25 mm

b. Penulangan Daerah Lapangan

Dari Perhitungan SAP 2000 diperoleh momen terbesar pada batang 362 Mu = 24070,09 = 24,07 ×10 7 Nmm Mn = 8 , 10 24,07 7 Mu = 30,09 ×10 7 Nmm Rn = 2 7 2 5 , 537 350 10 09 , 30 .d b Mn 2,98 Nmm 2 = fy 2.m.Rn 1 1 m 1 = 320 98 , 2 06 , 15 2 1 1 06 , 15 1 = 0,01 min max dipakai tulangan tunggal Digunakan ada = 0,01 As perlu = ada . b. d = 0,01× 350 × 537,5 = 1881,25 mm 2 commit to user 218 Tugas Akhir Perencanaan Struktur Mall 3 Lantai RAB BAB 7 Portal n = 2 25 4 1 perlu As = 63 , 490 1881,25 3,83 ~ 4 tulangan As’ = 4 × 490,63 = 1962,52 1881,25 mm 2 As’ As………………….aman Ok a = b . c f . 0,85 fy . ada As 350 . 25 . 0,85 320 . 1962,52 = 84,44 Kontrol Spasi : S = 1 - n sengkang 2 - tulangan n - 2p - b = 1 4 10 . 2 - 25 4. - 40 . 2 - 35 = 50 25 mm dipakai tulangan satu lapis Jadi dipakai tulangan 4 D 25 mm

7.4.6. Perhitungan Tulangan Geser

Dari Perhitungan SAP 2000 diperoleh momen terbesar pada bentang 503 Vu = 12303,77 kg = 123037,7 N Vc = 16 . c f .b.d = 16 . 25 . 350 . 539 = 157208,33 N Ø Vc = 0,6. Vc = 94325 N 3 Ø Vc = 282975 N Syarat tulangan geser : Ø Vc Vu 3Ø Vc Jadi diperlukan tulangan geser Ø Vs = Vu - Ø Vc = 123037,7 – 94325 = 28712,7 N Vs perlu = 6 , Vs = 6 , 28712,7 = 47854,5 N Av = 2 . ¼ 10 2 = 2 . ¼ . 3,14 . 100 = 157 mm 2 commit to user 219 Tugas Akhir Perencanaan Struktur Mall 3 Lantai RAB BAB 7 Portal S = Vsperlu d fy Av . . = 47854,5 539 240 157 = 424,4 mm Smax = d2 = 5392 = 269,5 mm Dipakai tulangan Ø 10 – 400 mm: Vs ada = S d fy Av . . = 400 539 240 157 = 50773,8 N Vs ada Vs perlu 50773,8 N 47854,5 N........Aman Jadi dipakai sengkang dengan tulangan Ø 10 – 400 mm

7.4.7. Penulangan Kolom

Untuk contoh pehitungan tulangan lentur kolom diambil momen terbesar dari perhitungan dengan SAP 2000, yaitu batang 31 Data perencanaan : b = 500 mm h = 500 mm f’c = 25 MPa fy = 320 MPa Ø tulangan =22 mm Ø sengkang = 10 mm s tebal selimut = 40 mm Dari perhitungan SAP didapat : Pu = 104496,36 kg = 1044963,6 N Mu = 38263,1 kgm = 38,26 × 10 7 Nmm d = h – s – Ø sengkang –½ Ø tulangan utama = 500 – 40 – 10 –½ .22 = 439 mm d’ = h – d = 500 – 439= 61 mm e = 1044963,6 10 26 , 38 7 Pu Mu commit to user 220 Tugas Akhir Perencanaan Struktur Mall 3 Lantai RAB BAB 7 Portal = 366,14 mm e min = 0,1.h = 0,1. 500 = 50 mm Cb = 439 . 320 600 600 . 600 600 d fy = 286,30 ab = β 1 .cb = 0,85 × 286,30 = 243,36 Pn b = 0,85 × f’c × ab × b = 0,85 × 25 × 243,36 × 500 = 25,86 × 10 5 N Pn Perlu = 65 , Pnb 65 , 10 25,86 5 = 39,78×10 5 N Pn perlu Pn b analisis keruntuhan tekan K 1 = 5 , d d e = 5 , 61 439 50 = 0,63 K 2 = 18 , 1 3 2 d e h = 18 , 1 439 50 500 3 2 = 1,57 y = b × h × fc’ = 500 × 500 × 25 = 6,25 ×10 6 N As’ = y K K Perlu P K fy n . . 1 2 1 1 = 6 5 10 25 , 6 57 , 1 63 , 10 78 , 39 63 , 320 1 = -5,69 mm 2 As t = 1 Ag =0,01 . 500. 500 = 2500 mm 2 As t = As’ + As , dimana As t As’ commit to user 221 Tugas Akhir Perencanaan Struktur Mall 3 Lantai RAB BAB 7 Portal As’ = 2 mm 1250 2 2500 2 t As Dipakai As’ = 1250 mm 2 Menghitung jumlah tulangan : n = 2 22 . . 4 1 1250 3,29 ≈ 4 tulangan As ada = 4 . ¼ . π . 22 2 = 1519,76 mm 2 1250 mm 2 As ada As perlu………….. Ok Kontrol Spasi : S = 1 - n sengkang 2 - tulangan n - 2p - b = 1 4 10 . 2 - 22 4. - 40 . 2 - 50 = 104 25 mm Jadi dipakai tulangan 4 D 22

7.4.8. Hitungan Tulangan Geser Kolom

Vu = 14830,38 kg = 14,83 × 10 4 N Pu = 104496,36 kg = 1044963,6 N Vc = d b c f Ag Pu . . 6 . 14 1 = 4 10 18 , 58 439 500 6 25 500 500 14 1044963,6 1 N Ø Vc = 0,6 × Vc = 34,91 × 10 4 N 0,5 Ø Vc = 17,45 × 10 4 N Vu 0,5 Ø Vc = tanpa diperlukan tulangan geser. Dipakai sengkang praktis untuk penghubung tulangan memanjang : 10 – 150 mm. commit to user 222 Tugas Akhir Perencanaan Struktur Mall 3 Lantai RAB BAB 7 Portal

7.4.9. Perhitungan Tulangan Lentur Sloof

Bidang momen balok portal melintang dan bidang geser balok portal melintang terlihat pada Gambar 7.9 dan 7.10. Gambar 7.11. Bidang Momen Sloof commit to user 223 Tugas Akhir Perencanaan Struktur Mall 3 Lantai RAB BAB 7 Portal Gambar 7.12. Bidang Geser Sloof Data perencanaan : b = 200 mm d = h – p –Ø s - ½Ø t h = 350 mm = 350 – 40 – 10 – ½.19 f’c = 25 MPa = 290,5 mm fy = 320 MPa b = fy 600 600 fy c. β 0,85.f = 320 600 600 320 0,85 25 0,85 = 0,037 max = 0,75 . b = 0,75 . 0,037 = 0,028 min = 0044 , 320 4 , 1 fy 1,4 commit to user 224 Tugas Akhir Perencanaan Struktur Mall 3 Lantai RAB BAB 7 Portal

a. Daerah Tumpuan

Dari Perhitungan SAP 2000 diperoleh momen terbesar pada batang 252 Mu = 7358,62 kgm = 7,36 × 10 7 Nmm Mn = φ Mu = 8 , 10 36 , 7 7 = 9,2 × 10 7 Nmm Rn = 2 7 2 290,5 200 10 9,2 d . b Mn 5,45 Nmm 2 m = 06 , 15 25 0,85 320 c 0,85.f fy = fy 2.m.Rn 1 1 m 1 = 320 45 , 5 06 , 15 2 1 1 06 , 15 1 = 0,02 min max Digunakan ada = 0,02 As perlu = ada . b. d = 0,02 × 200 × 290,5 = 1162 mm 2 n = 2 19 4 1 perlu As = 39 , 283 1162 4,1 ~ 5 tulangan As’ = 5 × 283,39 = 1416,95 mm 2 1162 mm 2 As’ As………………….aman a = b c f 85 , fy . ada As = 69 , 106 200 25 85 , 320 . 1416,95 Kontrol Spasi : S = 1 - n sengkang 2 - tulangan n - 2p - b commit to user 225 Tugas Akhir Perencanaan Struktur Mall 3 Lantai RAB BAB 7 Portal = 1 5 10 . 2 - 19 5. - 40 . 2 - 20 = 1,25 25 mm dipakai tulangan dua lapis Di pakai d d1 = 290,5 mm d2 = d1 – s – 2 x ½ Ø = 290,5 – 30 – 2 x ½.19 = 241,5 mm d x 5 = d1 x 3 + d2 x 2 d 5 2 x 241,5 3 290,5x = 270,9 mm Mn ada = As ada . fy d – a2 = 1416,95 . 320 270,9 – 106,692 = 9,86 .10 7 Nmm Mn ada Mn 9,86 .10 7 Nmm 9,19 × 10 7 Nmm Aman.. Jadi dipakai tulangan 5 D 19 mm

b. Daerah Lapangan